How buildings get built: the construction process, start to finish

Updated
Written by
Alexander J. Hale
Reading time
11 min
Sheet
1 of 44

A commercial or apartment building moves through seven stages in order: predevelopment and feasibility, design, permits and pricing, contracts and financing, construction, closeout and move-in, and finally operations, which last for decades. The owner decides the building is worth doing, an architect and engineers draw it, the city reviews the drawings and issues a building permit, and a general contractor builds it under inspection until the city issues the document that lets people move in, a certificate of occupancy. Construction alone averaged 19.1 months for US residential buildings of 20 or more units completed in 2025, according to the Census Bureau, and most of the design and permit work happens before that clock starts.

Construction phases at a glance

Firms split a project into different numbers of phases under different names, and neighboring stages overlap. The order holds because each stage hands the next one something it can’t start without.

Stage Who leads Typical length What comes out of it
Predevelopment and feasibility The owner, usually a developer No standard length. It ends when the numbers work or the deal dies A decision to buy the land and build, backed by site studies and a budget
Design The architect and its engineers Months to years. One public owner, Vermont’s state buildings department, plans on 16 to 47 months of design for its own projects Drawings and specifications detailed enough to permit, price and build
Permits and pricing The city’s building department, and the contractor’s estimators Months. Large commercial permits in Denver averaged 266 days in mid-2025 A building permit and a construction price
Contracts and financing The owner, with its lender and contractor Runs alongside permits and pricing A signed construction contract and a construction loan
Construction The general contractor 19.1 months on average for buildings of 20 or more units (2025) The building, inspected layer by layer
Closeout and move-in The contractor and architect, with city inspectors Overlaps the last months of construction Substantial completion, a certificate of occupancy and a worked-off punch list
Operations The owner and its property manager Decades Rent, repairs and the replacement of worn-out parts

The construction process before groundbreaking

Predevelopment and feasibility

Every project starts with an owner betting that the completed building can earn back its cost and more. On commercial and apartment work that owner is usually a developer, the company that finds the land, raises the money and hires everyone else. Before buying, it pays for due diligence, studies that hunt for anything able to stop the project or change its price, such as a survey of the lot, soil borings, a zoning check and an environmental review. A spreadsheet of costs against expected rent, the pro forma, decides whether the project goes ahead. Bank examiners expect a construction lender to see feasibility work of this kind before it lends.

Design

Design comes in passes, each more detailed than the last, and the design phases page takes them one at a time. The standard owner-architect agreement from the American Institute of Architects (AIA), B101, lists five phases of the architect’s work, and the first three are the drawing passes, schematic design, design development and construction documents. Schematic design turns the owner’s needs into plans and elevations with a probable cost. Design development sizes the structure and the mechanical, electrical and plumbing (MEP) systems. Construction documents are the complete drawings and specifications that the bids and the construction contract rest on.

Pricing, contracts and financing

Who prices the job, and when, depends on the project delivery method. The three common methods differ in the number of contracts and in the point at which the builder comes aboard. Under design-bid-build, the architect and the builder each hold their own contract with the owner, and the builder wins the job by bid once design is done. Under construction manager at risk, the general contractor is hired during design and often commits to a guaranteed maximum price (GMP). Under design-build, one company signs a single contract for both.

The money usually comes from the owner’s equity plus a construction loan, paid out in installments called draws as the work goes in. Bank examiners check that the loan agreement releases money only as work progresses, after a site inspection and signed lien waivers from subcontractors, and keeps the contractor from starting until the lender authorizes it.

The building permit process

A new building needs two separate approvals from local government. Zoning decides what may be built where, including which uses each district allows, where a building sits on its lot, and how tall and large it can be. The building code sets minimum requirements for building it safely, from structural strength and exits to fire protection and energy use. New York State’s code office sums up the split as where against how, and a building has to satisfy both. The two overlap in places. The gap between a building and its property line is a setback under zoning and a fire separation distance under the building code, and each rulebook asks different things of it.

Most US building codes start from the International Building Code (IBC), a model code that the International Code Council (ICC) writes. It binds no one until a state or city adopts it, sometimes with local amendments. The ICC says the IBC is in use or adopted in all 50 states, so the first question on any project is which edition the city has adopted and what it changed.

On a commercial or apartment project the steps run in this order, the same sequence the Los Angeles Department of Building and Safety lays out for its own permits.

  1. Confirm the zoning. Los Angeles points applicants to ZIMAS, its planning department’s online lookup. A project the zoning won’t allow needs a variance or a rezoning first.
  2. Apply with the construction documents. The IBC wants a written application describing the work, the building’s use and the value of the work. A large building’s package adds the drawings, a geotechnical report on the soil and a statement of special inspections, the extra checks of structural work by an agency the owner hires, not the contractor.
  3. Plan review. The building official checks the documents against the code, and departments such as planning, fire and public works may review them too. The design team answers each round of comments and resubmits until every reviewer approves.
  4. Permit issued. The approved set is stamped “Reviewed for Code Compliance,” with one copy kept by the building department and one on site for the inspectors. Under the model code, a permit lapses if work hasn’t started within 180 days.
  5. Inspections during construction. The contractor calls for an inspection when each stage is ready, and work can’t continue past that point until it passes. Los Angeles records each one on a building card, and the approved plans have to be on hand for every inspection.
  6. Final inspection and certificate of occupancy. The final inspection follows the last permitted work. Nobody may occupy the building until the official issues a certificate of occupancy, though a temporary one can open finished portions that are safe to occupy.

Permitting alone can take most of a year. In June 2025, large commercial developments in Denver were averaging 266 days of permitting time, just as the city began holding itself to 180 calendar days of its own review time on new submittals. Denver stops that clock while a set is back with the applicant for corrections, so an owner waits longer than the city’s count.

How buildings are built, from site work to finishes

Construction follows the order in which things get buried. Each layer is built, and usually inspected, before the next one hides it, so a superintendent schedules inspections as carefully as crews.

Crews clear and grade the lot, dig for the foundations and any below-grade parking, and bring water, sewer and power to the site. The city inspects the footings once the trenches are dug and the reinforcing steel and forms are in place, before concrete buries the steel. The owner’s special inspectors check the same steel, then the concrete’s mix, placement and curing.

The structure rises floor by floor in concrete, steel or wood, and the day it reaches full height is called topping out. The roof, exterior walls and windows then close the building against weather. Once rain stays out, the building is dried in, and drywall and flooring can go in without being ruined.

Inside the open walls and ceilings, the MEP trades run ducts, pipes, conduit and wire, a stage called rough-in. The IBC holds the city’s framing inspection until the rough electrical, plumbing and heating work is approved, and no seal around a pipe or duct through a fire-rated wall or floor can be covered before it’s inspected. Insulation gets an energy inspection, and drywall in a fire-rated wall is inspected once the boards are up, while the seams are still bare. Painting, flooring, cabinets and ceilings follow, then the trim-out, when electricians and plumbers set fixtures, outlets and equipment.

Paper moves alongside the crews, and the RFIs, submittals and change orders page follows it. A question about the drawings, a trade’s product data for the designers to review and a change to the contract each travel as their own document, with a log of their own.

Closeout, move-in and operations

Near the end, the contractor lists everything still unfinished or wrong on the punch list. Under the standard AIA contracts, the architect certifies substantial completion on form G704 once the owner can put the work to its intended use, after checking the contractor’s list and adding what it finds. Warranties start that day unless the certificate says otherwise. After the final inspections comes the certificate of occupancy, which bank examiners expect a lender to confirm before releasing the last of the loan.

Operations is the longest stage. The owner and a property manager lease the building, take the first warranty calls and pay for a new roof or boiler when the old one wears out.

How long construction takes

The Census Bureau’s Survey of Construction tracks new US housing from the month construction starts to the month it’s finished. Buildings with 20 or more units completed in 2025 averaged 19.1 months, up from 14.3 months in 2015, and 82 percent of their units took 13 months or more. A single-family house averaged 7.4 months that year. In 2025 the same survey put the gap from permit to groundbreaking for buildings of 20 or more units at about 2.6 months, a count that starts after plan review is over.

For design, one public owner’s planning ranges give a sense of scale. In a 2023 briefing for state legislators, Vermont’s Department of Buildings and General Services gave 5 to 15 months for schematic design, 5 to 12 for design development and 6 to 20 for construction documents on state building projects. Set a design schedule like that beside a permit review like Denver’s, and the work before groundbreaking can take as long as the construction after it.

Construction for beginners: what newcomers get wrong

Picturing the stages one after another

Real projects overlap them on purpose. A construction manager at risk joins while the drawings can still change. The IBC lets the building official accept deferred submittals, parts of the design such as a truss maker’s engineering that are approved after the permit and can’t be installed before then. Denver encourages running site plan review and building permit review at the same time.

At 1200 Walnut Street, the fictional building the book follows, month 9 of construction shows the overlap. Carpenters are framing the wood apartment floors under a permit the city issued before the contractor’s trailer arrived. The roof trusses above them exist only as a package from the truss plant, and the structural engineer has just sent it back after 12 days, marked revise and resubmit. Once corrected and approved, the package still has to go to the city as a deferred submittal, months after the permit.

Treating the permit as the city’s guarantee

The IBC states that issuing a permit doesn’t approve any violation of the code, and it says the same of a certificate of occupancy. When a plan reviewer overlooks an error, the code still lets the building official order it corrected later.

Assuming one inspector checks everything

Three kinds of inspector can visit a large job. The city’s building inspector checks code items at each stage. Special inspectors hired by the owner check structural work such as concrete, steel and soils. The lender sends its own inspector before it releases a draw. Each works for a different party, and a city sign-off doesn’t release a loan draw.

Confusing a zoning approval with a building permit

A zoning approval says a building of that use and size may go on that lot. It says nothing about whether the drawings meet the building code. New York’s state code office notes that zoning is enforced locally, sometimes by the same official who enforces the building code, and that a building must comply with both.