Design-build vs design-bid-build vs CM at risk: project delivery methods explained

Updated
Written by
Alexander J. Hale
Reading time
12 min
Sheet
16 of 44

A project delivery method is the contract arrangement an owner uses to get a building designed and built, defined by how many contracts the owner holds and how early the builder comes aboard. In design-bid-build, the owner hires an architect, finishes the design, takes bids and signs the lowest responsible bidder to a fixed price. In construction manager at risk, the builder is hired partway through design and later commits to a guaranteed maximum price, and in design-build, a single firm holds both the design and the construction under one contract.

What is a project delivery method?

The method decides who hires the designer and the builder, in what order and on what terms. That settles whether the builder is picked on price or on qualifications, how early the owner learns the cost, and who pays when a drawing turns out wrong. Because it fixes when the builder can join, it shapes every phase of the project.

Design-bid-build

Design-bid-build (DBB) is named for its three steps, which run one after another. The architect’s team carries the design all the way to finished construction documents, contractors bid on that set, and the job typically goes to the lowest responsible bidder for a fixed lump sum, also called a stipulated sum.

Low bid suits public agencies because the award is hard to challenge. Every bidder prices the same documents, the low number wins, and a losing bidder or an auditor can check the result. The owner also keeps its architect as an adviser with no stake in the construction price, and federal rules generally bar the firm that designed a project from winning the contract to build it.

The weakness is timing. A builder first sees the drawings when they’re done, too late to suggest a cheaper wall or flag a pipe that won’t fit. A contractor that won on a thin margin prices what the sheets show, and gaps in them often reach the owner later as change orders.

Construction manager at risk (CMAR or CM/GC)

Construction manager at risk (CMAR, also written CM@R) keeps separate contracts for the architect and the builder and moves the builder’s start date up. The construction manager is typically hired when 20 to 60 percent of the design is drawn, mostly on qualifications and fee, and spends the rest of design on what the trade calls preconstruction, estimating cost and checking whether details can be built. Then, in most cases, it commits to a guaranteed maximum price (GMP), signs the trade subcontracts and runs the job. Because it ends up in the general contractor’s seat, the AIA and the Associated General Contractors of America (AGC) note the method is sometimes called CM/GC, and Washington State’s public works law calls it GC/CM.

Owners pick CMAR to have the firm that will carry the price reading the drawings while changes are still cheap. The friction sits in the GMP. A construction manager sets that number on what the drawings showed the day it priced them, while owners often treat it as covering wherever the design goes next, a mismatch that an article published by the Construction Management Association of America (CMAA) traces many GMP disputes to. The general contractor page explains how a CM at risk differs from an agency CM, who advises and builds nothing.

Design-build

In design-build (DB), the owner holds a single contract, and the design-builder on the other side answers for the drawings and the construction alike. It may keep designers and builders on its own staff or be a team of separate design and contracting firms. It comes aboard when design is between untouched and about 20 percent done, picked on qualifications or on a blend of price and technical proposal that procurement rules call best value.

The owner gets one point of responsibility. When a duct turns out to run through a beam, there is nobody else to bill. The repair comes out of the design-builder’s pocket, and it settles the matter with its own engineers. Design and construction can overlap, with foundations going in while upper floors are still being drawn. The cost is control, because the architect now works for the builder.

Progressive design-build moves the price later. Selection rests mainly on qualifications, and the two parties work through early design and estimating in a first phase before negotiating a GMP or lump sum for final design and construction. If they can’t agree on price, an off-ramp in the contract lets the owner walk away, and the ConsensusDocs 411 standard form gives that right to either side. The Design-Build Institute of America (DBIA), citing a 2024 study by the consulting firm FMI, says the progressive version now makes up roughly one-third of design-build procurements. That figure is the average answer in FMI’s survey of industry respondents, and it counts progressive and other qualifications-based selection together.

Design-build vs design-bid-build vs CM at risk compared

Design-bid-build CM at risk Design-build
Contracts the owner signs for design and construction Two, architect and contractor Two, architect and construction manager One, with the design-builder
When the builder joins After design is finished Usually at 20 to 60 percent of design At or near the start, up to about 20 percent
How the builder is chosen Lowest responsible bid Mostly qualifications and fee Qualifications, or best value that weighs price
How the price is set Lump sum bid on finished drawings GMP once design is far enough along Lump sum or GMP, at award or later
Who answers to the builder for design errors The owner The owner, though the CM can share blame The design-builder
Speed, design through completion (CII study) Slowest About 25 percent faster than DBB About twice DBB’s rate
Where it fits Defined scope, public low-bid rules Complex, phased or occupied buildings Tight schedules and needs that can be written down early

The speed figures come from a 2018 study for the Construction Industry Institute (CII) and the Charles Pankow Foundation by Keith Molenaar of the University of Colorado Boulder and Bryan Franz of the University of Florida. It covered 212 US building projects finished over the prior decade, 62 percent of them publicly funded. With other factors held constant, cost growth on design-build jobs ran 3.8 percent below design-bid-build and 2.4 percent below CM at risk, and construction went 36 percent faster than design-bid-build, counted in square feet finished per month. CM at risk beat design-bid-build on speed and cost growth and trailed it slightly on cost per square foot and schedule growth.

The authors’ own numbers argue for modesty. Cost per square foot came out nearly even, with design-build 0.3 percent below design-bid-build. The cost-growth and schedule-growth models each explained only about a fifth of the variation between projects, so most of what drove overruns and delays lay outside everything they measured. Interviews pointed at timing and people, though only 16 project teams took part. Of the 9 best performers interviewed, 78 percent had the designer and the builder both on contract and collaborating by design development, against 29 percent of the 7 worst.

DBIA, the method’s trade group, reports that FMI’s 2024 study forecasts design-build at more than 47 percent of construction spending by 2028. That share covers only the nonresidential segments FMI assessed, from manufacturing and highways to lodging, which add up to about half of all US construction spending. Housing isn’t among them.

Design-build vs construction manager at risk

With low bid ruled out, these are the two main methods left, and the choice often turns on the architect. Under CM at risk, the owner holds the architect’s contract, so the designer can side with the owner when cost and quality pull apart. Under design-build, the architect’s client is the design-builder. An owner that plans to hold a building for a generation, or has firm views on systems and finishes, tends to want that direct line. One that wants a single company to call, and a price early, tends to give it up.

Design risk follows the contracts. Since the Supreme Court’s 1918 decision in United States v. Spearin, an owner that supplies the plans has generally answered to the contractor for their defects. With CM at risk the plans still come from the owner’s architect, so an error found after the GMP is signed tends to become the owner’s cost through a change order. The CMAA-published article notes that courts have occasionally found a duty to catch errors in a CM’s design-phase reviews. Under design-build, the error belongs to the design-builder.

One building, three ways

1200 Walnut Street, the fictional building the book follows, used CM at risk, with the builder hired at the end of schematic design. Pricing the design development set, the builder’s team found four plumbing stacks coming down into the garage drive aisle, and the fix happened on paper. The other two methods are a what-if. Under design-bid-build, no builder would have opened those sheets until the finished set went out for bids, and a fix after award would have reached the owner as a change order. Under design-build, the stacks would have been the design-builder’s own problem from the first sketch.

How each method is paid: lump sum and GMP

On most building jobs, design-bid-build ends in a lump sum, so the contractor keeps what it saves and absorbs what it overspends. CM at risk usually ends in a GMP, under which the owner pays actual cost plus the fee up to a ceiling, and unspent money goes back to the owner or is shared, depending on the contract. Design-build can go either way. The AIA’s owner and design-builder agreement, A141, offers a stipulated sum, cost plus a fee, or cost plus a fee with a GMP. The general contractor page sets the payment types side by side.

Multiple prime, IPD and P3

Under multiple prime contracting, the owner skips the general contractor and signs directly with several trade contractors. New York’s Wicks Law, section 135 of the State Finance Law, has the state write separate specifications, each open to its own bids, for plumbing, for heating, ventilating and air conditioning, and for electrical work. It applies once a project passes $3 million in New York City, $1.5 million in Nassau, Suffolk and Westchester counties and $500,000 elsewhere, unless a labor-law exception covers the job.

Integrated project delivery (IPD) puts the owner, architect, contractor and sometimes other major participants on one agreement. Under the AIA’s C191 form, the architect and contractor work at cost, and their profit depends on meeting agreed goals and finishing below a target cost.

A public-private partnership (P3) goes past construction. In the model the Federal Highway Administration calls design-build-finance-operate-maintain (DBFOM), an agency awards all of those jobs to one private partner or consortium.

How public owners choose a delivery method

A private owner can use any method it can negotiate. A public owner picks from what its legislature has authorized, and the rules differ by state, by agency and sometimes by project size.

Federal agencies hire architects and engineers on qualifications under the Brooks Act, which begins at 40 U.S.C. 1101. They rank the best-qualified firms and negotiate a fair and reasonable price with the top one, moving down the list only if talks fail. For design-build, the Federal Acquisition Regulation first scores teams on qualifications and technical approach with price left out, and shortlists no more than five unless the contracting officer documents a reason for more. Only the shortlisted teams then submit technical and price proposals.

Washington State’s law, RCW 39.10, allows design-build, GC/CM and job order contracting as alternatives to low bid, and an agency not certified for design-build or GC/CM needs a state committee’s approval project by project. Design-build is open to jobs over $2 million that are highly specialized, gain from designer and builder working together, or would save significant time. GC/CM needs one of six conditions, among them complex phasing and an occupied building that must keep operating. Its finalists bid a percentage fee and can’t be asked for a project price, and the law requires the winner’s subcontract work to be bid in public, apart from an approved alternative process for subcontracts over $3 million.

Questions an owner asks to pick a method

Start with what the law and the money allow. Most projects collect more than one yes, so the answers get weighed against each other.

Question A yes points toward Why
Does a statute, grant or board policy require award to the low bidder? Design-bid-build, or only the alternatives the law names Public owners need authority for anything else
Can the whole scope be drawn before anyone prices it? Design-bid-build Every bidder prices the same finished set
Is the opening date fixed and close? Design-build Design and construction overlap
Does the owner want its own contract with the architect? CM at risk or design-bid-build Under design-build the architect works for the builder
Will the building stay occupied, or go up in phases? CM at risk A builder involved in design can plan the sequence
Does the owner want one firm answering for design errors? Design-build The firm that draws the building pays for its own mistakes
Can the owner make design decisions fast and staff the early phases? Progressive design-build or CM at risk Both rely on an owner that answers questions while the design is still moving

Sources