What is a general contractor, and what do they do?

Updated
Written by
Alexander J. Hale
Reading time
11 min
Sheet
6 of 44

A general contractor (GC) is the company that signs the contract with a building’s owner to build it, for a fixed price or for its costs plus a fee. It hires and manages the specialist firms, called subcontractors, that do most of the hands-on work, decides how the building gets built, runs the site and its safety program, and pays the trades out of the owner’s progress payments. The architect and engineers design the building, and the GC answers to the owner for building what they drew.

What does a general contractor do?

A GC buys a building in pieces and then answers for the whole thing. It signs a separate subcontract for each trade, from concrete and framing to plumbing and roofing, and its own staff spend most of their time pricing and scheduling that work and checking it.

Before construction, the people who price the job measure the drawings, collect subcontractor prices and turn them into one number the company will be held to. During construction, the field staff run the site while the office staff move paper between the site and the designers. Shop drawings go to the architect for review as submittals, questions about the drawings go out as requests for information (RFIs), agreed changes are signed as change orders, and a regular application for payment rolls up every subcontractor’s bill. At the end, the GC works through the punch list, hands over the closeout paperwork and comes back during the first year to fix defective work.

What is a general contractor responsible for?

The duties below come from A201-2017, “General Conditions of the Contract for Construction,” a standard form the American Institute of Architects (AIA) publishes for use with its owner-contractor agreements. Any clause can be rewritten, so on a real job the signed contract is the one to read.

How the work gets built, from where the crane sits to which crew goes first, is the contractor’s call, and builders call those choices means and methods. The same form says the architect has no control over them and no responsibility for them (section 4.2.2), so a designer asked how to build something will describe the finished work and stop there.

Responsibility What A201-2017 assigns the GC Section
Means and methods Sole control of how the work is built, including its techniques, sequences and procedures, and of coordinating all of it 3.3.1
Subcontractors Answers to the owner for its subcontractors’ acts and omissions, and binds each one to the contract’s obligations, safety included 3.3.2, 5.3
Schedule Submits a construction schedule promptly after award, running to substantial completion, and revises it as the job goes 3.10.1
Site safety Starts, maintains and supervises all safety precautions and programs, and names an on-site person to prevent accidents, by default its top person on site 10.1, 10.2.6
Paying subcontractors Pays each sub within seven days of being paid by the owner, reflecting the share the owner actually retained on that sub’s work 9.6.2
Permits Secures and pays for the building permit and other customary permits and inspections, unless the contract says otherwise. The owner handles approvals and easements for the permanent building 3.7.1, 2.3.1
Warranty Warrants new, good-quality materials and work that matches the contract documents, and corrects defective work found within one year of substantial completion 3.5.1, 12.2.2.1

Federal safety enforcement adds a second layer. Under OSHA’s multi-employer citation policy, a GC with general supervisory authority over a site is a controlling employer, expected to use reasonable care to prevent and detect hazards there, including hazards that a subcontractor’s workers face.

The people on a general contractor’s team

Inside a GC, pricing a job and running it are separate jobs, and running it splits between the office and the field.

Role Where they work What they own
Estimator The office, mostly before construction starts Reading drawings and specifications, pricing the work and preparing the bid
Project manager (PM) The office or the site trailer The contract, budget, schedule, choice of subcontractors, change orders and the bill to the owner
Superintendent The site, every working day Scheduling the crews, checking the work for safety and against the specifications, and coordinating the trades. Under A201, what’s said to the superintendent binds the company
Project engineer The office and the site The submittal and RFI logs, updated drawings and job paperwork, worked alongside the superintendent

The Bureau of Labor Statistics describes construction managers as “often called general contractors or project managers,” so the same words can name a company or a person.

One morning in construction month 9

At 1200 Walnut Street, the fictional building the book follows, the GC was hired during design. Nine months into construction, it holds about 30 subcontracts. In the site trailer, Nia Newman, the assistant project manager, who joined from a bank eight months ago, writes RFI 187. The framing foreman has found that the drawings show a third-floor plumbing wall shallower than the drain pipe it has to hold. The roof truss submittal has just come back from the structural engineer marked revise and resubmit. Before the day ends, Nia checks the framing subcontractor’s bill in pay application 9 against the walls actually standing. The application will ask the owner for $3,015,000.

How a general contractor is hired and paid

Under design-bid-build, the design is finished first, contractors bid on it, and the lowest responsible bidder typically wins a fixed-price contract. When the owner instead brings the builder in during design and settles the price as the drawings develop, the method is construction manager at risk. When one company is hired at the start to both design and build, it’s design-build. The payment terms then decide who absorbs a bad estimate.

Method How the price works If costs run over If costs come in under AIA owner-contractor form
Lump sum, also called stipulated sum One fixed price for the scope in the contract The GC absorbs it The GC keeps the difference A101
Cost plus a fee The owner pays what the work actually costs, plus a fee, with no cap The owner pays The owner saves A103
Guaranteed maximum price (GMP) Actual cost plus a fee, up to a ceiling The GC pays above the ceiling The owner saves, or the two share it if the contract says so A102, or A133 when the GC is hired as CM at risk

A fixed price suits a well-defined scope, and an underestimate comes straight out of the GC’s profit. A GMP sits between that and open-ended cost plus, and is most often used on large projects where the owner wants a ceiling. Under all three, change orders still move the contract sum, and the owner usually holds back a share of each payment, called retainage. A201 releases it at substantial completion, less an amount for unfinished or defective work (section 9.8.5), but many contracts keep part of it until final completion.

General contractor vs construction manager

“Construction manager” names two different arrangements, and only one of them builds anything.

A construction manager at risk (CM at risk, sometimes CM/GC) joins during design and advises the owner on cost and buildability. Once the design is far enough along, it negotiates a price to build the job, typically a GMP. The owner can refuse that price and bid the work out instead. After both sides sign, the CM is legally in a general contractor’s position, with the trade contracts and the cost risk.

An agency construction manager, or CM as adviser, works as the owner’s representative at any phase and under any delivery method. The construction contracts are the owner’s own, at times split among several separate prime contractors, and those contractors carry the cost risk. The agency CM earns a professional fee, billed by the hour, as a lump sum or as cost plus a fixed fee.

General contractor (design-bid-build) CM at risk Agency CM
When it’s hired After design, by bid During design Any phase
Holds the trade contracts Yes Yes, once the price is signed No, the owner does
Carries the cost risk Yes, at a fixed price Yes, above the GMP No
How it’s paid Lump sum Cost plus a fee, usually up to a GMP A professional fee
Stake in the construction price Its own bid The price it will negotiate None

During construction a CM at risk and a GC are hard to tell apart, and the AIA and Associated General Contractors’ joint primer says the CM becomes a general contractor through the at-risk agreement. What separates them is when the builder joined and how the price was set. An owner hires an agency CM to get construction advice from a firm with no stake in what the building costs.

General contractor vs subcontractor

A subcontractor has a direct contract with the GC to do a portion of the work at the site, and A201 says nothing in the contract documents creates a contractual relationship between the owner and a sub. Firms that do one kind of work, such as concrete, plumbing or electrical, are called specialty trade contractors, and they usually work as subcontractors.

That chain of contracts sets who talks to whom. Under A201, communications with subcontractors go through the contractor, so a plumber’s question about the drawings travels through the GC to the architect and back. It also sets where a mistake lands. A sub that bid at a fixed price absorbs the cost of its own slow crew, and the GC answers to the owner for the sub’s work either way.

Do general contractors need a license?

Contractor licensing is set state by state, so the answer depends on where the building is. In California, anyone who contracts for work valued at $1,000 or more in combined labor and materials needs a license from the Contractors State License Board, as does anyone doing work that needs a building permit or uses employees. A general building contractor there that takes on specialty work must hold that specialty license or have a licensed specialty contractor do it, unless the job involves more than two types of work.

The closest thing to a national credential is a commercial building exam accredited by the National Association of State Contractors Licensing Agencies, which participating states accept in place of their own trade exam. It isn’t a license, and the contractor still applies to each state. The trades carry their own licenses too, and most states require electricians to pass a test and be licensed.

What newcomers get wrong about general contractors

Assuming the GC’s own crews build the building

Specialty trade contractors held about 63 percent of the roughly 8.4 million payroll jobs in US construction in October 2026 (a preliminary BLS count), and the federal industry definition of a building contractor lets it subcontract part or all of the construction. A GC can win a job, run it well and pour none of its own concrete. What the owner gets is one company to hold accountable for all of it.

Assuming the GC answers for the design

On a design-bid-build or CM-at-risk job, the drawings come from the owner’s architect and engineers. Since the Supreme Court’s 1918 decision in United States v. Spearin, the usual rule has been that a contractor required to build to plans the owner supplied isn’t responsible for the consequences of defects in them. A201 still requires the GC to report any error it discovers, as an RFI. Design-build is the exception, with one contract for design and construction and one company responsible for both.

Assuming the warranty lasts one year

The one year in A201 is a correction period, the GC’s duty to come back and fix defective work when the owner gives notice. The separate warranty in section 3.5.1, that the finished work meets the contract’s requirements, has no time limit written into it, and section 12.2.5 says the one-year period sets no limit on the GC’s other obligations. How long an owner can wait before suing is set by state statutes of limitation and repose.

Reading “project engineer” as an engineering job

At a GC, project engineers are often the newest people on the site, and some have just finished a construction management degree. The job is the RFI and submittal logs, drawing updates and safety paperwork, learned day by day from the superintendent and the foremen.