What is a punch list? How a building gets finished

Updated
Written by
Alexander J. Hale
Reading time
11 min
Sheet
42 of 44

A punch list is the list of small things still unfinished or wrong when a building is nearly done, such as a door that won’t latch or a scratch in new glass. The contractor writes it when it believes the work has reached substantial completion, the point when the owner can start using the building, and the architect and the owner then walk the work and add whatever the contractor missed. The owner’s final payment waits until the list is closed, along with whatever is left of the share it held back from every monthly bill, called retainage.

What a punch list is in construction

These items pile up in the last weeks, when several trades work in finished rooms at once. Carts scuff fresh paint, and an electrician leaves one cover plate in the box. None of it stops anyone from moving in, and all of it is work the contract already requires.

A201, the general conditions of the construction contract published by the American Institute of Architects (AIA), has the contractor write down the “items to be completed or corrected prior to final payment.” That covers work never done, like the missing cover plate, and work done wrong, like tile set out of line, and the difference can count in court. In California, for one, a court deciding whether a job is legally complete looks at the punch work still open, and completion starts deadlines such as the window for filing a lien. Procore, the construction software, calls the same tool a snag list in its British edition and a deficiency list in its Canadian one.

When the punch list happens

The list starts when the contractor believes the work, or a part the owner has agreed to take over separately, is substantially complete. A201 defines that as the stage when the work is “sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use.” A building handed over in phases gets a list for each phase.

Both sides want that date, the owner to move in or start collecting rent and the contractor for what comes with it. Warranties start then unless the parties agree otherwise, the AIA’s Certificate of Substantial Completion (form G704) records who now answers for utilities, maintenance and insurance, and the builder’s risk policy typically ends. Substantial completion also usually stops liquidated damages, the daily charge a contract can set for finishing late, so an owner can’t keep collecting them over a missing cover plate.

Who creates the punch list

The general contractor writes the first version, because it knows best what isn’t done. Its superintendent walks every room and writes each problem down, and a contractor that sends each trade through its own work first hands the architect a shorter list.

Federal jobs put that walk in the specifications. The guide specifications shared by the Army Corps of Engineers, the Navy and the Air Force have the contractor’s quality control manager run a punch-out inspection, give each item a target fix date and confirm the fixes before the government’s pre-final inspection. Work still unfinished at the final acceptance inspection lets the government bill the contractor for the extra inspection.

Then the architect walks, often with the owner’s representative. Under A201 it inspects after getting the contractor’s list, and anything that would keep the owner from using the space must be finished and inspected again before the certificate is issued. The architect signs that certificate, which gives it a stake in being thorough. An item missed on every walk is still owed, because A201 says leaving it off the list doesn’t change the contractor’s duty to complete the work.

What goes on a punch list

Typical items are finish damage (paint touch-ups, scratched counters, chipped tile), adjustments (doors that bind, a closer that slams), missing small parts (cover plates, the trim rings around sprinkler heads, a blank circuit directory in an electrical panel), equipment that needs tuning, and final cleaning. A room without its flooring or a system that hasn’t passed its test is too big for the list, since the owner can’t use that space yet.

A sample punch list

Here is one illustrative page for the second floor of a made-up office building, after the contractor’s walk and the architect’s.

No. Room or location Item Found by Trade responsible Status
1 Conference 201 Scuff on north wall beside light switch. Touch up to match. Contractor Painting Closed
2 Conference 201 Ceiling tile stained at northeast corner. Replace. Contractor Acoustical ceilings Ready for recheck
3 Break room 204 1/8-inch gap between backsplash and wall. Caulk to match. Architect Casework Open
4 Corridor 2A Door 2A-3 doesn’t latch when released from fully open. Adjust closer. Architect Doors and hardware Open
5 Corridor 2A Cover plate missing at outlet beside drinking fountain. Contractor Electrical Closed
6 Open office 210 Carpet seam lifting at doorway. Re-seam. Contractor Flooring Open
7 Open office 210 Scratch in lower left pane of window 2-14. Replace glass. Owner Glazing In dispute (contractor says owner’s movers did it)
8 Office 208 Supply air diffuser rattles when fan runs. Architect Mechanical Ready for recheck

Ready for recheck means the trade says it’s done, and closed means someone other than that trade has looked and agreed. Item 7 shows the punch walk’s other job, sorting what the contractor owes from damage someone else caused, and the date the scratch was first written down is the evidence both sides will cite.

How punch list items get assigned, fixed and closed

  1. Someone writes the item, with a photo and a pin on the drawing if the job runs on software such as Procore.
  2. The contractor assigns it to the subcontractor whose work it is. If that trade won’t come back, the contractor can fix it with its own crew and, where the subcontract allows, charge the trade for it, a back-charge.
  3. The trade fixes it and marks it ready for review.
  4. The contractor rechecks it and closes it or sends it back.
  5. The architect confirms the fixes on a later walk before certifying the final payment.

Whoever fixed an item shouldn’t be the one to close it, and Procore builds that in by giving the close to a final approver, often whoever created the item. Items stall between steps 2 and 3, waiting on a painter who has already moved to the next job.

Substantial completion vs final completion

Final completion is the end of the contract’s work, every punch item included. Under A201 the architect inspects once more after the contractor’s final application for payment and issues the final Certificate for Payment when it finds the contract fully performed.

Substantial completion Final completion
What it means The owner can occupy or use the work for its intended use All work done, punch list included
Who certifies it The architect, on the G704, accepted by owner and contractor The architect, through the final Certificate for Payment
The punch list Attached to the G704 with a deadline Closed
Money Under A201, retainage on that work, reduced for anything incomplete Final payment and any retainage still held
Paperwork The G704 Affidavit that bills are paid, lien releases, surety’s consent, closeout documents
What starts or stops Warranties start, builder’s risk typically ends, liquidated damages usually stop The contractor’s work ends and its warranty duties continue

How retainage and the final payment tie to the punch list

Retainage protects the owner if work is left unfinished or defective or a subcontractor goes unpaid, and the owner-contractor agreement sets the rate. Federal construction contracts allow it only when progress is unsatisfactory, and never more than 10 percent of a payment. New York caps it at 5 percent on private projects of $150,000 or more, apart from some housing, and California set the same cap for most private contracts signed from January 1, 2026.

A201’s default releases most of it at substantial completion. Once the G704 is accepted, and the surety consents if there is one, the owner pays the retainage on that work, less an amount for work that is incomplete or wrong. Florida fixes that amount by law on local government jobs, which must pay the balance within 20 business days after the list is drawn up, minus 150 percent of the estimated cost to finish the listed items. Other owners keep all of it until final completion.

Final payment typically follows a passed final inspection, once the owner is satisfied the punch items are done and the contractor has signed an affidavit that its project debts are paid (AIA form G706), backed by lien releases and the surety’s consent. Those last dollars are the contractor’s reason to close the list, and the subcontractors’ too, since their retainage comes through the contractor.

At 1200 Walnut Street, the fictional building the book follows, the first punch walk comes in month 19. The superintendent goes room by room through the lobby, the garage and every apartment on the second, third and fourth floors, and his notes become the opening list. Rosa Archer, the project architect, retraces his route and writes in what he passed over. Fernwood Development, the owner, holds about $3 million of retainage, and its contract releases none of it at substantial completion. The check goes out at final completion, roughly three months past the first temporary certificate of occupancy, once the last item is signed off and every closeout document is in.

Punch list items vs warranty claims vs latent defects

All three are work that doesn’t match the contract. They differ in when they turn up and in what the owner still holds over the contractor.

Punch list item Warranty claim Latent defect
When it turns up At the end-of-job walks, before final completion After substantial completion, during the warranty period Later, because no reasonable inspection at handover would have found it
Illustrative example A door that won’t latch A water heater that fails the first winter Flashing left out behind brick, found when the wall leaks in year three
What the owner holds Retainage and the final payment The contract’s warranty terms and any manufacturer’s warranty The contractor’s warranty and the state’s deadlines for suing

Under A201 the correction period runs one year from substantial completion. The contractor must promptly fix nonconforming work found in that year once the owner gives written notice, and an owner that finds a problem that year but never gives notice and a chance to fix it gives up both the fix and any warranty claim over it. People call it the one-year warranty, but it limits only the duty to come back. The contractor’s separate warranty that the work conforms has no end date of its own, so an owner can still sue over a defect found later, within the state’s deadlines for suing, which end at the statute of repose, an outer cutoff usually counted from substantial completion. Colorado allows six years, or as many as eight when the claim arises late, and California allows ten for hidden defects. A201 adds its own outer limit of 10 years after substantial completion, even where state law allows longer.

A latent defect, in the federal acquisition rules’ definition, exists at acceptance but can’t be found by a reasonable inspection. Federal acceptance is final except for latent defects, fraud, gross mistakes amounting to fraud and warranty rights, so the walk before acceptance is the government’s best chance to call out anything it can see.

What newcomers get wrong about punch lists

  1. Treating substantial completion as finished. The G704 arrives with a list attached and a deadline to clear it.
  2. Saving big unfinished work for the list. If the owner can’t use the room yet, the certificate waits for another inspection.
  3. Writing items nobody can act on. A useful item gives the room and door numbers from the drawings, the exact spot and what finished looks like. “Fix paint, unit 3” sends a painter hunting. “Unit 304, bedroom, 6-inch scuff on the wall behind the door” gets fixed on the first visit.
  4. Adding new wishes. A different paint color or an extra outlet is a change to the contract, priced through a change order.