Design phases: schematic design, design development and construction documents

Updated
Written by
Alexander J. Hale
Reading time
12 min
Sheet
29 of 44

US architects usually design a building in three drawing phases that follow the owner’s program. Schematic design (SD) fixes the building’s size, shape, layout and main systems in a short set of plans, sections and elevations, design development (DD) draws the structure and building systems at real size with outline specifications, and construction documents (CDs) add every dimension, detail, schedule and written specification needed to permit, price and build the work. The owner approves each phase before the next begins, and each approval raises the cost of changing what it covered.

For the architect’s role in every phase, see what an architect does. This page covers what each set holds and locks in, and how to tell which phase a set came from.

Design phases at a glance

The standard definitions of the three drawing phases are in B101, the American Institute of Architects (AIA) contract form for owners and architects. It ends each one with the architect’s documents, a cost estimate and a request for the owner’s approval.

Phase What’s drawn What’s decided What the owner signs off on
Programming Space lists, area tables and relationship diagrams Which spaces, how big, which sit together, the budget The program, checked by the architect against site, budget and schedule
Schematic design Site plan and preliminary plans, sections and elevations. Engineers mostly write narratives Size, shape, layout, floor-to-floor height, structure, cores and main systems The SD set and the first cost estimate
Design development Dimensioned plans, sections and elevations, typical details and diagram-level system layouts The size and character of every system, major materials and quality levels The DD set, outline specifications and any change to the estimate
Construction documents Every dimension, specific details, schedules, full engineering layouts and the project manual Quality levels and performance criteria for every material and system, and code compliance The CD set and updated estimate, before bids or a negotiated price

Programming, before schematic design

The program is the owner’s written statement of what the building must hold, listing every space with its size and users, which spaces sit together, and the budget. The Whole Building Design Guide (WBDG), from the National Institute of Building Sciences, notes that standard AIA agreements make programming the owner’s job.

Programs count rooms in net assignable square feet, the space people actually use, and add an allowance for corridors, walls, shafts and mechanical rooms to reach the gross area. WBDG calls the ratio the building’s efficiency and gives no standard figure, so assume 75 percent for illustration. A program of 60,000 net square feet then means an 80,000-square-foot building, and each point of efficiency lost in design adds about 1,000 square feet the owner pays to build.

What gets drawn and decided in schematic design

Under B101, schematic design produces a site plan where needed, preliminary floor plans, sections and elevations, and possibly study models, sketches or renderings, with the major systems and materials picked in preliminary form. An AIA Best Practices quality checklist for the phase lets the main systems’ performance criteria be written as narratives, so the mechanical engineer may deliver a few pages on heating and cooling and no duct on any sheet.

What SD settles is mostly geometry. The footprint, the number of floors, the structural system, the location of the cores (the stacked stairs, elevators and shafts) and the floor-to-floor height all get fixed here. That last number deserves the hardest look, since it sets the depth left over each ceiling for structure, ductwork and piping, and nobody can add an inch once the frame is up.

The checklist adds that SD documents can go to zoning or planning bodies, and owner approval may reach a board or a lender. A facade that wins a planning vote in March is hard to change in June.

Design development

Design development draws each system at its true size for the first time. B101 calls for plans, sections, elevations, typical construction details and diagrammatic layouts of the building systems, enough to fix the size and character of each, and the AIA’s own description adds full dimensions and door and window details.

DD adds outline specifications that name major materials and systems and set their general quality. Its companion checklist for DD says DD documents may be submitted for a foundation permit, or even the full building permit. It’s the best moment for an outside review, since enough is drawn to show whether things fit and a fix still costs only drawing time.

What’s in a construction documents set

Construction documents are the set a contractor prices and builds from. B101 asks for drawings and specifications that set out the quality and performance of every material and system and include the requirements of the building department. The architect also compiles the project manual, the bound volume of specifications, contract conditions and, on a bid job, bidding forms. Next to a DD set, a CD set usually adds these:

  • dimensions on every wall, opening and grid line
  • enlarged plans of stairs, restrooms and other crowded rooms
  • a detail for each distinct condition, where DD drew typical ones
  • schedules for doors, hardware, windows, finishes and equipment
  • engineering layouts down to branch ducts, pipes and circuits

B101 still expects the contractor to supply shop drawings, product data and samples for the architect’s review. The page on RFIs, submittals and change orders follows that paperwork.

Construction document milestones: 50%, 90% and 100%

Owners often ask to see construction documents partway through, and each sets its own stops. The US General Services Administration’s submittal matrix for federal buildings has a 65 percent CD stage it calls in progress, a 95 percent stage it calls pre-final, and a final stage it calls issued for construction. The University of Alabama’s deliverables list has 60 and 90 percent CD stages. The University of California reviews at 50 and 100 percent and lets the design professional decide when a set has reached 100.

The percentage is a judgment, so hold each milestone to a written list of contents agreed early. Those AIA checklists note that clients often don’t know what a phase will deliver until it arrives.

On a construction manager at risk job, a set short of 100 percent can become the pricing set. The AIA’s A133 agreement has the contractor list the drawings behind its guaranteed maximum price (GMP), which covers further development the documents reasonably imply, while changes in scope or systems still need a change order. Project delivery methods explains the contract.

At 1200 Walnut Street, the fictional building the book follows, the GMP is priced from the 90 percent set. Rosa Archer, the project architect, then takes those drawings to 100 percent for the permit and answers one round of city comments. The set the price rests on and the set the city stamps are different documents, and the GMP’s list of priced drawings is what tells them apart.

Permit set vs bid set vs issued-for-construction set

Set Who receives it How to recognize it How it changes
Permit set The building department’s plan reviewers Sealed and signed sheets, then the department’s approval stamp Plan review comments, answered by resubmittal
Bid set Bidders, or a construction manager’s subcontractors A project manual with bidding requirements and bid forms Addenda, formal changes issued before the contract is signed
Issued-for-construction (IFC) set The builder’s field team The bid set with every addendum and accepted change folded in Revisions and change orders after award

Under the International Building Code (IBC), the building official approves the documents as “Reviewed for Code Compliance,” in writing or by stamp, when issuing the permit, keeps one set, and returns the other to be kept on site for inspectors.

In Canada, the Ontario Association of Architects (OAA) defines an IFC set as the bid documents updated for every addendum, chosen alternate and negotiated change, and notes the AIA’s word for it is “conformed.” Contractors once made their own with tape and staples. The OAA’s warning about the modern version is that a designer tidying files can drop a change or slip in an unofficial fix.

Construction specifications and how they relate to drawings

The drawings show where each thing goes, how big it is and how many there are. Construction specifications say what it’s made of, how well it must perform, how it’s installed and what the contractor submits for approval first. The guide to reading construction drawings covers which governs when they disagree.

Specifications grow with the drawings. In SD they’re a note on a sheet or a short narrative, sometimes a preliminary project description organized by UniFormat, a Construction Specifications Institute (CSI) system that sorts a building by functional element (substructure, shell, interiors, services) whatever the materials. DD turns them into outline specifications, and CDs into full sections in the project manual.

Those sections are numbered under MasterFormat, which CSI maintains jointly with Construction Specifications Canada. The 2004 edition expanded it from 16 divisions to 50, some left blank for the future, and the 2026 edition added 2,185 new listings. Numbers read in pairs, so 07 84 00 is Division 07, Thermal and Moisture Protection, narrowed to firestopping. Divisions 00 and 01 hold the contract paperwork and rules for every trade, and the work itself fills divisions such as 03 Concrete, 09 Finishes, 23 Heating, Ventilating, and Air Conditioning, and 26 Electrical.

Inside each section, CSI’s SectionFormat sets three parts. Part 1, General, holds administrative requirements such as submittals. Part 2, Products, describes materials and equipment. Part 3, Execution, covers installation, from checking the surface to protecting the finished work.

How cost estimates sharpen phase by phase

An estimate can only be as detailed as the drawings behind it. B101 has the architect estimate cost at the end of SD and update the figure in DD and CDs, using area, volume or similar conceptual techniques, and it gives the architect’s reason for hedging. Neither architect nor owner controls labor prices, material prices or bidding conditions, so the architect doesn’t promise that bids will match.

The AIA’s description of SD bases that first estimate on overall project volume, and CSI says UniFormat’s primary use is formatting estimates during schematic design. DD drawings generally support a trade-by-trade estimate, according to the DD checklist, and finished CDs produce the contractors’ final numbers.

Cost engineers grade estimates by how much of the project is defined. AACE International publishes the classes for buildings as Recommended Practice 56R-08, and ASTM International’s standard E2516 draws on AACE’s practices. The project definition and accuracy columns below are 56R-08’s. The basis and use column follows the summary that Alberta Infrastructure, a Canadian provincial department that uses the ASTM version, publishes for building and general construction.

Class Basis and typical use Project definition Typical accuracy range
5 Minimal information, screening 0 to 2% Low -20% to -30%, high +30% to +50%
4 Schematic layouts, concept study 1 to 15% Low -10% to -20%, high +20% to +30%
3 Design development, budget authorization 10 to 40% Low -5% to -15%, high +10% to +20%
2 Detailed design and specifications, control or bid 30 to 75% Low -5% to -10%, high +5% to +15%
1 Detailed to full design, bid check 65 to 100% Low -3% to -5%, high +3% to +10%

AACE warns that the ranges show relative improvement from class to class and aren’t targets, and that the high side on complex projects can exceed twice the published figure. Even the typical Class 4 range is wide. A schematic estimate of $50 million, at the edges of that row, covers a final cost from about $40 million to $65 million.

How to tell which phase a drawing set is from

A reviewer who mistakes a DD set for a permit set will fill pages with comments about details nobody was meant to draw yet.

  1. Read the title block’s issue line. Labels such as SD, DD, 50% CD or Issued for Permit usually settle it.
  2. Look for a disclaimer where the seal would be. Texas, for one, makes drawings issued for anything but regulatory approval, permitting or construction say so in a conspicuous statement. A note like that in place of a seal means a progress set.
  3. Look for the building department’s stamp. It marks the permitted set or a copy of it.
  4. Check the engineering sheets. Narratives, or no mechanical, electrical and plumbing (MEP) sheets at all, suggest SD, main runs drawn as diagrams suggest DD, and every branch with riser diagrams and filled-in equipment schedules suggests CDs.
  5. Count the details. A set with only typical details points to DD. A detail for every condition, plus enlarged plans of stairs and restrooms, points to CDs.
  6. Weigh the specifications. None, or a description by building element, means SD. Outline specifications mean DD. Full MasterFormat sections in a bound project manual mean CDs, and bid forms in Division 00 mean a bid set.
  7. Look for clouds and addendum numbers. A cloud means the sheet changed after an earlier issue, and addendum references put the set in or after bidding.
  8. Look for a list of deferred submittals. The IBC wants pieces submitted after the permit application, such as engineered wood trusses, listed on the documents, so the list tends to show up as a set nears permit.
  9. Read the cover notes for incomplete portions. The AIA says a CD set that goes out for bid before it is complete carries a note saying so. A gap the notes admit is expected. An unlisted gap in a set labeled 100 percent is a question for the architect.