RFIs, submittals and change orders in construction, explained

Updated
Written by
Alexander J. Hale
Reading time
13 min
Sheet
41 of 44

An RFI, short for request for information, is how a contractor asks the designers in writing what the drawings or specifications mean when they are unclear, disagree with each other or leave something out. A submittal travels the same route before a piece of the work is built and shows exactly what the contractor plans to install, as shop drawings, product data or samples, and the reviewer marks it with an action such as “approved as noted” or “revise and resubmit.” A change order is the signed agreement between the owner and the contractor, with the architect also signing on AIA contracts, that changes the work, the price or the schedule, and it is where an RFI answer that adds work ends up once the price is settled.

What is an RFI in construction

Most RFIs start in the field, when a foreman finds a dimension missing from a plan or an existing slab thinner than the drawings say.

Asking is a duty. A201, the American Institute of Architects’ (AIA) standard general conditions for construction contracts, has the contractor compare the documents before each part of the work begins and send the architect any “errors, inconsistencies or omissions” it turns up “as a request for information.” A contractor that keeps that duty isn’t liable for the design’s mistakes, and one that skips it pays whatever an early report would have saved.

The RFI goes out under the general contractor’s name, usually from a project engineer or project manager, even when a subcontractor raised it, and Kutztown University’s specifications, one public owner’s version, accept RFIs from the contractor only. The architect answers in writing or passes the question to the engineer who drew that part.

Architects answer narrowly, and newcomers sometimes read that as stonewalling. A201 holds every interpretation to the documents’ intent and to what can reasonably be inferred from them, and bars the architect from favoring either side, so an answer that redesigns more than the question asked can hand one party a cost the other never accepted.

How long an RFI response takes

A201 sets no number of days for RFIs or submittals. The architect answers within whatever limits the parties agreed, or otherwise “with reasonable promptness,” so the real clock sits in Division 01, the general requirements at the front of the project specifications.

Document Clock it sets
Kutztown University, Division 01 (2023) 5 working days for an RFI answer, 14 days for a submittal review
University of Houston master specification 7 working days for an RFI answer
UFGS 01 33 00, the US military’s guide specification (2026) 30 calendar days for a government submittal review by default, and the same again for each resubmittal

Kutztown’s version rewards asking early. An RFI on an activity with no more than five working days of float, the days an activity can slip before it delays the finish, earns no time extension if the answer arrives inside the five days. In Aconex records from 1,362 projects, about 79 percent of them in Australia and New Zealand, analyzed by the Navigant Construction Forum in 2013, the first reply to an RFI took 6.4 days on average. Most of those jobs were outside the US, so the figure is only a rough guide for American work.

An example RFI, filled in

This illustrative RFI comes from a made-up two-story office building.

Field Entry
RFI number 042
Date sent Tuesday, March 3
From Project engineer, general contractor
To Project architect
Subject Wall type 5 at the second-floor corridor is not defined
References A-102 (second floor plan), A-501 (wall types), G-002 (life safety plan), section 09 21 16 (gypsum board assemblies)
Question A-102 tags the corridor walls between gridlines C and F as wall type 5. The wall type schedule on A-501 shows types 1 to 4 only. G-002 shows this corridor as one-hour rated. Please define wall type 5.
Contractor’s suggested answer Build it as wall type 3, the schedule’s one-hour wall, with 3-5/8-inch metal studs and one layer of 5/8-inch Type X gypsum board each side, full height to the deck
Cost or schedule impact None if the suggested answer is accepted
Answer needed by Tuesday, March 10 (five working days). Second-floor wall layout starts March 16.
Architect’s answer, March 6 Wall type 5 is wall type 3 with 3-1/2-inch sound attenuation batts filling the stud cavity, full height. See ASI 7 and revised A-501. No change in contract sum or contract time.

It sticks to one subject and cites exact sheets, which how to read construction drawings explains, and it offers the contractor’s own answer and its cost effect, as both universities require. An RFI that reads “please clarify corridor walls” tends to come back with a question of its own.

What is a submittal in construction

Before a fabricator cuts steel or a supplier orders 80 door frames, the contractor shows the designers exactly what it means to provide. A201 names three kinds of package. Shop drawings are drawn for this project by whoever builds or supplies that part, such as a steel fabricator’s drawing of every beam connection. Product data are catalog sheets, performance charts and instructions for a standard product. Samples are physical pieces, like a tile, and the finished work is judged against them. The US military’s guide specification splits submittals into 11 numbered types, from preconstruction submittals to closeout.

A submittal isn’t a contract document, so a stamp can’t rewrite the contract. By sending a package, the contractor vouches that it has approved it, checked field measurements and fitted it to the surrounding work. The reviewer looks only at its fit with the design concept and the documents. Dimensions and quantities remain the contractor’s job, and approval doesn’t cover a deviation the contractor didn’t point out when it submitted. Each side checks what it controls, since the contractor runs the means and methods and the architect isn’t the fabricator’s engineer.

Order the packages by lead time. A201 bars work that needs a submittal until it is approved, and Kutztown tells contractors to expect at least one resubmittal on complex packages such as structural steel and HVAC controls. Custom switchgear usually waits on approved drawings before production starts, so each extra review cycle pushes back the delivery.

Submittal review stamps

The architect, or the engineer whose discipline the package covers, marks an action on it, in wording that varies by firm and owner.

Stamp What it means Can the work go ahead
Approved Matches the design as sent Yes
Approved as noted Matches once the reviewer’s marked corrections are made Yes, with the corrections, usually without resubmitting
Revise and resubmit Needs changes before it can be approved No. Fix it and send it again.
Rejected Doesn’t meet the requirements, often a product the specification doesn’t allow No. It needs a whole new submittal, and a different product goes through the substitution process.
No action taken Not required by the contract, so not reviewed Returned unreviewed

Kutztown’s version calls a rejection “not approved” and also allows a “partial approval.” A reviewer’s note can also add work, and the federal specification tells a contractor that sees a correction as a change to give notice under the contract’s changes clause.

What is a submittal log

A submittal log, or submittal register, lists every package the specifications require and tracks each one until it comes back approved. Kutztown asks at minimum for the specification section, the submittal’s name and type, the date it goes out and the date approval is needed, updated at least monthly. The federal register adds the reviewer, the action code, every date in and out and the date the material is needed, and the federal format numbers a resubmittal with a suffix, so 18 becomes 18.1.

Here is an illustrative page for the same made-up office building.

No. Item Type Reviewer Sent Returned Action Needed on site
07 54 23-01 TPO roof membrane Product data Architect Feb 16 Feb 27 Rejected Apr 20
08 11 13-01 Hollow metal door frames Shop drawings and product data Architect Feb 9 Feb 23 Revise and resubmit May 4
08 11 13-01.1 Hollow metal door frames, resubmitted Shop drawings and product data Architect Mar 2 Under review May 4
26 24 13-01 Main switchboard Shop drawings and product data Electrical engineer Jan 26 Feb 9 Approved as noted June 1

The date the material is needed, minus the maker’s lead time, the review period and one resubmittal for anything complex, gives the day the package has to go out, which is why the switchboard went first. The rejected roof membrane, a product the specification doesn’t name, is now the row to worry about, with seven weeks until the roofers need it.

How an RFI answer can turn into a change order

Most answers clarify and cost nothing. When one adds work, the contractor has to say so quickly. A201 treats the extra cost or time as a claim, due within 21 days of the event or of the day the contractor first recognizes it, whichever is later. Owners’ specifications often set shorter windows. Kutztown’s gives seven days and treats silence as a waiver, and Houston’s asks for notice within ten. For an architect’s minor change, A201 wants notice before the work is done, and building it first waives any adjustment.

In the illustrative RFI 042, ASI 7 says no change, but the project engineer finds sound batts in none of the bid set’s wall types. On March 9, inside this job’s seven-day window, the contractor writes that it considers them added work and logs a potential change order (PCO), a change still being priced or argued. The architect had read a rated wall beside private offices as an acoustic wall. The contractor priced what was drawn. The owner would have paid for batts in the bid had they been drawn, so it agrees to pay for them now. Because the question came before framing, nothing has to come out. Asked after the drywall, the same answer would have meant cutting open one face of 220 feet of finished corridor wall.

What is a change order in construction

A change order is the contract changing itself. Under A201 the architect prepares it and the owner, contractor and architect sign it, agreeing on the change in the work, the contract sum and the contract time. Once signed it becomes one of the contract documents. On AIA jobs the form is G701, which carries the original sum or guaranteed maximum price (GMP), the changes so far, the new sum and the new date of substantial completion. Besides RFIs, changes come from owners who change their minds and from hidden conditions that differ from the drawings, which A201 makes the contractor report within 14 days of first seeing them.

Two lighter documents often come first. The architect’s supplemental instructions (ASI), AIA form G710, is the architect’s own instruction, interpretation or minor change, and the AIA says it shouldn’t be used to change price or time. The construction change directive (CCD) orders work that can’t wait for a price. The owner and architect sign it, and the contractor proceeds promptly while the price is worked out. The AIA’s instructions for form G714 want the owner’s signer to have legal authority to approve added funds, since the directive commits money before anyone has agreed on the amount, and meanwhile the contractor bills the work monthly on the architect’s interim figure.

Document What it does Who signs Changes price or time AIA form
RFI Asks what the documents mean Contractor sends, architect answers No, unless the answer leads to a change G716, optional. A201 lets the architect set the format
ASI Gives an instruction, interpretation or minor change Architect alone No G710
Proposal request Asks the contractor to price a possible change Architect No, and it directs no work G709
Construction change directive Orders the work now and settles price and time later Owner and architect Yes, once settled G714
Change order Records agreement on the work, price and time Owner, contractor and architect Yes G701

How change orders get priced

A201 allows four methods for a directed change. The parties can accept an itemized lump sum with enough backup to check it, use unit prices in the contract or agreed later, or pay cost plus a fixed or percentage fee. When the contractor won’t agree, the architect sets the figure from reasonable costs plus overhead and profit. Unit prices suit work whose quantity nobody can know in advance, such as rock excavation by the cubic yard. Time and materials pays for the hours and materials actually used, and it is only as good as the daily tickets someone checks. Deleted work comes back to the owner at its actual net cost.

Owners tighten this in Division 01. Kutztown’s wants labor, materials and equipment itemized by hours, quantities and rates. On contracts up to $6 million it caps combined overhead and profit at 15 percent of labor cost and 10 percent of materials, equipment and subcontract costs.

Here is the PCO from RFI 042 priced with Kutztown-style caps at both tiers, using illustrative hours and costs.

Line Basis Amount
Installer labor 30 hours at an illustrative $90 an hour, fully loaded with payroll taxes, insurance and benefits $2,700
Subcontractor’s markup on labor 15 percent $405
Sound attenuation batts Illustrative cost for about 220 feet of wall, 10 feet high $1,650
Subcontractor’s markup on materials 10 percent $165
Drywall subcontractor’s price $4,920
General contractor’s markup on the subcontract 10 percent $492
Change order total, with no added days $5,412

The signed order gives the new contract sum and completion date, and Kutztown’s change orders also carry a release in which both sides give up later claims over that change’s price, time and “impacts.”

What newcomers get wrong

  1. Grading the architect by RFI count. A 2012 study of nine Wisconsin highway projects, cited by the Navigant Construction Forum, sorted RFIs into 14 categories, including added scope and differing site conditions, neither of them a drafting mistake, and judged 13.2 percent not justifiable at all.
  2. Reading “approved” as the architect taking over. Dimensions, quantities and any deviation the contractor didn’t flag stay with the contractor.
  3. Building ahead of the stamp. Under revise and resubmit, the work waits for the approved resubmittal.
  4. Letting the notice window close. An ASI marked “no change” stays that way once the contractor builds it without objecting in time.
  5. Using an RFI to ask for money or a substitution. Houston’s specification sends those back without action.
  6. Signing the release unread. Twelve small releases can sign away the cost of a schedule that twelve small changes knocked apart.