Hard costs pay for the physical building and its site, the labor, materials and equipment plus the contractor’s jobsite overhead and fee, and on most projects they add up to the construction contract. Soft costs are everything else an owner pays to get the building designed, approved, financed and opened, such as design fees, permit and impact fees, legal work, insurance, the developer fee and construction-loan interest. With land and a contingency on lines of their own, they make up total development cost, and Harvard’s Joint Center for Housing Studies puts soft costs at about 20 to 30 percent of that total on a straightforward apartment project.
Hard costs vs soft costs in construction
Guidance for bank examiners from the Office of the Comptroller of the Currency (OCC) says construction budgets typically sort costs into these two groups. The split also tracks who controls the money. Once the construction contract is signed, the contractor answers for the hard costs, and the soft costs stay in the owner’s hands.
| Cost | Usually falls under |
|---|---|
| Site work, foundations, structure, building systems, finishes, landscaping | Hard |
| Contractor’s general conditions, fee, own insurance and bonds | Hard |
| Builder’s risk insurance on the building itself | Soft if the owner buys it, hard if the contract has the contractor buy it |
| Architect’s and engineers’ fees | Soft |
| Building permit, plan review, impact and utility fees | Soft |
| Legal, title, survey and site reports | Soft |
| Developer fee | Soft |
| Construction-loan interest and loan fees | Soft |
| Land price and closing costs | Land, its own line |
| Owner’s contingency | Its own line, outside the construction contract |
What counts as hard costs
The OCC’s handbook lists on-site and off-site improvements, the building’s construction, the contractor’s general conditions and fee, and the other items normally inside a construction contract, bonds and the contractor’s insurance among them. On a job with a guaranteed maximum price, nearly all of it sits inside that one number, which the GMP page takes apart.
Procore’s guide to the topic files the contractor’s general conditions, such as site management and temporary utilities, under soft costs. The OCC’s handbook keeps them with hard costs, beside the contractor’s fee, and names trailers, vehicles, dumpsters and cleanup as examples. That’s the convention to follow when reading a lender’s budget or a draw request.
What counts as soft costs
The same handbook defines soft costs as interest and other development costs such as fees and predevelopment spending. A developer fee paid to the developer for managing the project counts too, when it’s in line with what an outside firm would charge, and the OCC says it typically doesn’t exceed 4 percent of project cost. Interest or preferred returns owed to equity partners or junior lenders stay out of the construction budget.
Where builder’s risk, design fees, permit fees and loan interest fall
Builder’s risk insurance
Builder’s risk covers the building and its materials while it’s going up. It costs more than insurance on a finished building, the Massachusetts housing agency’s construction finance explainer notes, because the sprinklers and fire detection aren’t running yet and an unoccupied site invites vandalism. Under the 2017 AIA documents, the owner buys an “all-risks” completed-value policy unless the parties choose the option that hands the purchase to the contractor, according to summaries by IRMI and the law firm Faegre Drinker. When the owner buys, the premium is a soft cost in the owner’s budget. When the contractor buys, the premium rides inside the contract price as a hard cost, like the contractor’s other insurance. A budget should carry it in exactly one place, and the builder’s risk and bonds page covers what the policy pays for.
Design fees
The architect’s and engineers’ fees are soft costs, paid by the owner from the first sketches through closeout. Washington State’s schedule for its own buildings puts apartments on its middle complexity table. At a $60 million base, that table’s basic fee is 6.48 percent on a design-bid-build job and 7.25 percent where a contractor joins during design. Where the contractor joins during design, the base is only the direct cost of construction, which leaves out the contractor’s fee, field and home-office overhead, risk contingency and preconstruction services. On those jobs the percentage doesn’t apply to the whole contract price. Its phase split leaves 27 percent of the fee for construction and 2 percent for closeout, so about 71 percent is earned before construction starts. Its basic fees range between roughly 4 and 12 percent across every table.
Permit, impact and utility fees
These go to the city and the utilities, and all of them are soft costs. The International Code Council (ICC) publishes average construction costs per square foot so building departments can set permit fees from a building’s value, multiplying gross floor area by the square-foot cost and a local permit fee multiplier. Impact fees are separate payments that Massachusetts describes as going to cities or utilities to upgrade infrastructure or provide community benefits.
Construction-loan interest and fees
Interest on the construction loan is a soft cost, and the loan often lends the money to pay its own interest. The OCC describes an interest reserve as an account the lender sets up to cover interest during construction and lease-up, typically funded as a line in the loan budget. In the Massachusetts survey this capitalized interest averaged about 4 percent of total development cost, and it grows with every month the job runs. Origination and other loan fees sit beside it. The construction loans page explains how the reserve is sized.
Land and contingency
Land is its own line, the price plus closing costs, and its share swings with location. Harvard’s Joint Center put land at roughly 10 to 20 percent of total cost on a typical apartment project in 2020. Massachusetts puts Metro Boston land at about $40,000 to $60,000 per apartment, and a sample of developments there at 7 to 10 percent of total cost.
A contingency is money held for costs nobody can name yet. The owner’s sits on its own line, outside the construction contract, while the contractor keeps a separate one inside its price. The OCC sees contingency in construction budgets usually running 5 to 10 percent of the overall budget, and the contingency vs allowance page sorts out which reserve pays for what.
Hard and soft costs at 1200 Walnut Street
1200 Walnut Street, the fictional six-story building the book follows, has 200 apartments above a concrete podium holding a lobby, a small garage and two shops, about 200,000 gross square feet in all. Its owner, Fernwood Development, budgets $87.0 million. With about 1,000 gross square feet per apartment, each per-square-foot figure below is the per-apartment figure divided by 1,000. All Walnut Street numbers are illustrative.
| Line | Total | Per apartment | Per gross sq ft | Share of total |
|---|---|---|---|---|
| Land | $7.5 million | $37,500 | $37.50 | 8.6% |
| Hard costs (the contractor’s GMP) | $60.0 million | $300,000 | $300 | 69.0% |
| Owner’s contingency | $3.0 million | $15,000 | $15 | 3.4% |
| Soft costs, total | $16.5 million | $82,500 | $82.50 | 19.0% |
| Design (architect and engineers) | $4.0 million | $20,000 | $20 | 4.6% |
| Fees to the city and utilities | $3.5 million | $17,500 | $17.50 | 4.0% |
| Legal, title, survey, reports, insurance | $2.0 million | $10,000 | $10 | 2.3% |
| Developer fee | $2.5 million | $12,500 | $12.50 | 2.9% |
| Construction-loan interest (the interest reserve) | $4.0 million | $20,000 | $20 | 4.6% |
| Loan fees | $0.5 million | $2,500 | $2.50 | 0.6% |
| All-in total | $87.0 million | $435,000 | $435 | 100% |
The contractor’s $60 million price covers its general conditions, fee and own contingency, while Fernwood’s $3.0 million contingency, equal to 5 percent of that price, stays in Fernwood’s budget. Fernwood’s $4.0 million design fee is about 6.7 percent of the contractor’s price. Washington’s table, applied to Walnut Street’s construction cost once the contractor’s fee and general conditions come out of the $60 million, would land between $3.7 million and $4.0 million. The guidance lowers the figure again when trade contractors take over part of the design, as the framing and MEP subcontractors did here through design-assist. The $2.0 million line covers legal work, title, the survey, reports and insurance. The income side of the same project, from rent to yield on cost, is on the development pro forma page.
Soft costs as a share of total cost
Published shares disagree mostly because they draw the line in different places.
| Source | What it files as soft | Soft share of total cost |
|---|---|---|
| Harvard Joint Center for Housing Studies, 2020 | Everything except land and hard costs, including design, engineering, financing, permits and impact fees | About 20 to 30 percent on a straightforward project, much higher with a rezoning or heavy opposition |
| Massachusetts housing agency survey of developers | Surveys, design, zoning and environmental permits, engineering reports and legal work | 10 to 12 percent, with loan interest (about 4 percent) and the developer fee (about 3 percent) on separate lines |
| 1200 Walnut Street (fictional) | The six soft-cost lines in its budget above | 19.0 percent |
Adding Massachusetts’ two separate lines back in gives about 17 to 19 percent, still before impact fees and builder’s risk. Soft costs also climb with time. Interest runs by the month, and the Massachusetts explainer notes that each extra round of redesign for a review board adds architecture and engineering fees.
Construction cost per square foot
A figure per square foot means little until it says which costs and which square feet. Gross square feet cover the entire building, corridors, lobby, garage and shops included, while net rentable square feet count only the space tenants lease, such as the inside of each apartment. Walnut Street’s apartments average about 630 square feet inside, about 126,000 in all, so the same budget gives four different answers.
| Measure | Hard costs only ($60.0 million) | Total development cost ($87.0 million) |
|---|---|---|
| Per gross square foot (about 200,000) | About $300 | About $435 |
| Per net rentable apartment square foot (about 126,000) | About $476 | About $690 |
A Massachusetts survey of developers reported hard costs averaging $370 per square foot for that state’s mid-rise wood-frame buildings without saying which square feet, and about $550,000 per apartment for new buildings of 100 or more units. The ICC’s square-foot table, built for permit fees, leaves out land and says it isn’t meant as an estimating guide.
What newcomers get wrong
- Calling the construction contract the project’s cost. Walnut Street’s $60 million price is 69 percent of what Fernwood spends, and the lender measures its loan against the $87.0 million total.
- Comparing soft-cost percentages from different sources. Check whether loan interest, the developer fee and impact fees are inside a number before calling a budget high or low.
- Quoting a cost per square foot without its basis. Ask whether it covers hard costs or the whole budget, and gross or net rentable area, before setting it beside another.
- Assuming the contractor insures the building. Under the standard AIA forms the owner buys builder’s risk unless the contract says otherwise.
Sources
- Making Apartments More Affordable Starts with Understanding the Costs of Building Them, Hannah Hoyt and Jenny Schuetz, Harvard Joint Center for Housing Studies, May 5, 2020, accessed November 26, 2026
- Home for Everyone: Construction Finance Explainer, Massachusetts Executive Office of Housing and Livable Communities, Mass.gov, accessed November 26, 2026
- Comptroller’s Handbook: Commercial Real Estate Lending, Version 2.0, Office of the Comptroller of the Currency, accessed November 26, 2026
- Builders Risk: New AIA Requirements, Steven Coombs, IRMI, May 25, 2018, accessed November 26, 2026
- In New Contract Documents, AIA Bolsters Insurance Requirements: An In-Depth Look, Faegre Drinker Biddle and Reath, April 24, 2017, accessed November 26, 2026
- Chapter 08: Architect/Engineer Fee Guidelines and Fee Schedule, 2027-29 Budget Instructions, Washington State Office of Financial Management, accessed November 26, 2026
- Building Valuation Data, August 2020, International Code Council, Building Safety Journal, accessed November 26, 2026
- Balancing Hard Costs vs. Soft Costs in Construction, Procore, accessed November 26, 2026