Builder's risk insurance and construction bonds
- Updated
- Written by
- Alexander J. Hale
- Reading time
- 10 min
- Sheet
- 28 of 44
Builder’s risk insurance is property insurance on a building while it is under construction, paying to repair or rebuild the work, the materials and the temporary structures after sudden physical damage such as fire, theft, vandalism or wind. It usually excludes the cost of redoing faulty work, wear and tear, mechanical breakdown and, unless the buyer adds them, flood and earthquake. Construction bonds are a surety company’s guarantee of the contractor’s promises, with a bid bond behind its bid, a performance bond behind finishing the work and a payment bond behind paying its subcontractors and suppliers, and federal and state laws require the last two on most public construction.
What builder’s risk insurance covers
The standard contract forms published by the American Institute of Architects (AIA) spell out the policy in an insurance exhibit to the A101-2017 owner-contractor agreement. Its terms bind only the parties who sign it. They call for an “all-risks” policy written for the project’s full finished value from the start, called a completed value form, at replacement cost and for at least the contract sum plus changes and work supplied by others. The exhibit says the policy must
- not exclude fire, explosion, theft, vandalism, malicious mischief, collapse, earthquake, flood or windstorm
- cover damage that results from errors in design, specifications, workmanship, materials or construction methods
- cover falsework and other temporary structures, and building systems damaged in testing and startup
- pay for debris removal, demolition that code enforcement requires, and the architect’s and contractor’s extra services after a loss
- insure the owner, the contractor and subcontractors at every tier, with the lender as a loss payee
Insurers don’t always sell that by default. Earthquake, flood, wind and beach zones are usually excluded, Erin Rotz wrote in Construction Executive in 2021, and the exhibit leaves blanks for sublimits on each peril.
What builder’s risk doesn’t cover
| Commonly excluded | What it means on site | Notes |
|---|---|---|
| Faulty design, workmanship or materials | Tearing out and redoing the defective part | Damage the defect causes elsewhere is usually still covered, through an ensuing loss exception |
| Wear and tear, mechanical breakdown, employee theft, mold, pollution, water intrusion, earth movement, war and terrorism | Equipment that fails on its own, materials taken by the insured’s own workers, or damage from those causes | Usual exclusions or omissions, some available by extension, Rotz notes |
| The contractor’s own tools and equipment | Its cranes, scaffolding and gear | A separate policy on contractor-owned equipment is an option in the AIA exhibit |
A less common policy form excludes all damage caused by faulty workmanship and should be avoided, Jeffrey Cavignac wrote in Construction Executive in 2021. The common form excludes only the bad work, so if badly mixed concrete cracks a foundation and the structure above it shifts, the re-pour is excluded and the damage to the rest of the structure is covered. Endorsements labeled LEG 1 to LEG 3 move that line, and only the broadest, LEG 3, also pays to replace the defective part once it has caused damage.
Delay is a separate purchase. The AIA exhibit lists optional delay coverage, including soft cost insurance for the extra loan interest and fees, professional fees, taxes and premiums a covered loss causes. Under A201-2017, the AIA’s general conditions, the owner waives claims against the contractor and architect for loss of use of its property from fire or other hazards, so an owner that skips the delay coverage carries that loss itself.
Who buys builder’s risk, and when coverage ends
On the AIA forms the owner buys builder’s risk unless the parties tick the box that moves the purchase to the contractor. An owner that won’t buy it has to tell the contractor in writing before work starts, and the contractor may then buy coverage and charge the owner by change order (A201, section 11.2.2). Lenders want the policy too, and the Office of the Comptroller of the Currency (OCC) lists it among the papers a construction loan file typically holds.
Because everyone on the job is insured under one policy, A201 section 11.3 has the owner and contractor give up claims against each other, the architect and every subcontractor for fire and other losses, to the extent the property insurance covers them. That waiver of subrogation keeps the insurer, after it pays, from suing the subcontractor whose torch started the fire.
The exhibit keeps the policy in force until substantial completion and then, continued or replaced, through the one-year period for correcting work. It bars occupying any part of the building before substantial completion until the insurer consents in writing, and A201 makes that consent a condition of partial occupancy. A typical policy ends once the building is occupied or put to its intended use, Rotz wrote. The certificate of occupancy page follows a building that opens in stages.
Builder’s risk vs general liability
| Builder’s risk | Commercial general liability (CGL) | |
|---|---|---|
| What it insures | The work itself, its materials and temporary structures | The insured’s legal liability to other people |
| Kind of insurance | First-party property | Third-party liability |
| Who buys it on AIA forms | The owner, unless moved to the contractor | The contractor, naming the owner, architect and architect’s consultants as additional insureds |
| A typical claim | A fire destroys the partly built structure | Falling debris injures a pedestrian, or a crane damages the building next door |
The two policies are built to meet without overlapping. Two exclusions in the standard CGL policy, known as j(5) and j(6), drop damage to “that particular part” of the property the contractor is working on and the cost of redoing work done wrong, while damage that spreads to other property stays covered, Cavignac explained. For apartment builders, the AIA exhibit also bars the contractor’s CGL from excluding claims tied to residential, multifamily or other habitational projects.
Fire watch at Walnut Street, worked through
1200 Walnut Street, the fictional six-story building the book follows, stacks its apartments in five wood-frame stories over a concrete base, and every number here is illustrative. Framing runs from about month 6 to month 11, and through those months the open frame is lumber without the sprinklers and alarms that will protect the finished building. The National Fire Protection Association (NFPA) counted an average of about 4,440 fires a year in US structures under construction from 2017 to 2021, and the 18 percent that started between midnight and 6 a.m. caused just over half of the property damage. From about the fourth floor up, Walnut Street keeps a fire watch on site every night.
If a fire got past the watch, builder’s risk would pay to clear the debris and rebuild, and under AIA-style terms the insurer couldn’t sue the trade that started it. The construction loan would keep charging interest, up to about $11,000 a day once fully drawn, and only optional soft cost coverage would pay the extra interest from the delay. When the first temporary certificate opens the podium and levels 2 to 4 in month 19, painters are still on 5 and 6, so the insurer’s written consent to partial occupancy has to be in hand first.
What bid, performance and payment bonds do
A surety bond is a three-party contract in which a surety company guarantees to the obligee, here the project owner, that the principal, the contractor, will keep its promise. The last column gives the amounts the Federal Acquisition Regulation (FAR) sets for federal jobs.
| Bond | What it guarantees | Who can claim | Federal amount under the FAR |
|---|---|---|---|
| Bid bond | The bidder won’t withdraw its bid, and will sign the contract and furnish the required bonds on time | The owner, typically for the cost of rebidding or the gap to the next bidder | At least 20 percent of the bid price, capped at $3 million |
| Performance bond | The contractor will perform the contract | The owner. The surety can finish the work, pay to have it finished, or pay damages up to the bond’s limit | 100 percent of the original contract price |
| Payment bond | The contractor will pay for the labor and materials on the job | Covered subcontractors, suppliers and workers | 100 percent of the original contract price |
A surety underwrites a bond much as a bank underwrites a loan, says the National Association of Surety Bond Producers (NASBP), a trade group for the agents and brokers who sell surety bonds. It studies the contractor’s credit, finances, experience, work in progress and character, and expects no loss. Before a surety issues bonds, the contractor, its owners, their spouses and often affiliated companies sign a general agreement of indemnity, so a surety that pays a claim comes after them for the money. A bond’s limit is its penal sum, the amount written into it.
The trade group puts a performance bond’s one-time premium at 0.5 to 3 percent of the contract amount, with the payment bond usually included at no extra charge and bid bonds typically free. Rates are filed with state insurance departments, and established, financially strong contractors often pay less. The contractor buys the bonds and the owner typically pays the premium in the first pay request, NASBP says.
A performance bond pays nothing until the owner follows its terms, and NASBP notes that some require the owner to terminate the contractor under the construction contract first. Private work carries no bond mandate, but many private owners ask for bonds, prime contractors often require them of subcontractors, and lenders sometimes make them a condition of a construction loan, though the OCC notes that a contractor related to the borrower generally can’t be bonded.
The Miller Act and state Little Miller Acts
Public property can’t be liened, so on public work the payment bond may be an unpaid trade’s only protection, NASBP points out. The lien waivers page covers liens on private jobs. The federal Miller Act (40 U.S.C. 3131 to 3134) requires a performance bond and a payment bond before a federal construction contract over $150,000 is awarded. The statute still says $100,000, but a 2010 inflation adjustment raised the FAR’s figure to $150,000. Between $35,000 and $150,000, the contractor furnishes one of two or more payment protections the contracting officer picks, such as a payment bond.
Under the act, anyone unpaid 90 days after their last labor or material may sue on the payment bond, and must do so within one year of that last work. A claimant with a contract only with a subcontractor must first give the prime contractor written notice within those 90 days. Courts have read the act to stop at the second tier, so a supplier to a supplier, or a third-tier subcontractor, can’t recover, a line traced to the US Supreme Court’s 1944 MacEvoy decision.
Every state has its own version for state public works, NASBP says, and they vary. Florida’s rule, for one, requires bonds on state contracts over $100,000 and lets local public owners waive them at $200,000 or less. Washington’s requires them on public works but lets a contractor on a job of $150,000 or less choose a 10 percent holdback instead.
What newcomers get wrong
- Treating a bond as the contractor’s insurance. The surety pays the owner or the unpaid trades, then collects from the contractor and its owners under the indemnity agreement.
- Expecting builder’s risk to pay for fixing bad work. Most policies pay for the damage bad work causes, and the party responsible pays to redo the work itself.
Sources
- AIA Document A101-2017 Exhibit A, Insurance and Bonds, American Institute of Architects (copy posted with bid documents by Sauk County, Wisconsin), accessed November 26, 2026
- How to Manage Risk Using Construction Insurance and Bonds, Part 3: Commercial General Liability, AIA Contract Documents, December 1, 2022, accessed November 26, 2026
- Insurance and Bonds for Construction Project Owners: A Complete Guide, AIA Contract Documents, accessed November 26, 2026
- In New Contract Documents, AIA Bolsters Insurance Requirements: An In-Depth Look, Faegre Drinker, April 24, 2017, accessed November 26, 2026
- AIA Document A201-2017, General Conditions of the Contract for Construction, American Institute of Architects (blank copy posted with bid documents by the City of Rochester, New Hampshire), accessed November 26, 2026
- Understanding Builder’s Risk Insurance Coverages and Exclusions, Erin Rotz, Construction Executive, August 18, 2021, accessed November 26, 2026
- CGL, Builders Risk Coverage and Exclusions When Construction Defects Cause Property Damage, Jeffrey Cavignac, Construction Executive, April 23, 2021, accessed November 26, 2026
- Comptroller’s Handbook: Commercial Real Estate Lending, Version 2.0, Office of the Comptroller of the Currency, March 2022, accessed November 26, 2026
- Fires in Structures Under Construction, Richard Campbell, National Fire Protection Association, September 30, 2023, accessed November 26, 2026
- What Are Surety Bonds?, National Association of Surety Bond Producers, accessed November 26, 2026
- FAR 28.001, Definitions, Acquisition.gov, accessed November 26, 2026
- FAR 28.101-2, Solicitation provision or contract clause (bid guarantee amount), Acquisition.gov, accessed November 26, 2026
- FAR 28.102-1, General (Miller Act bonds and alternative payment protections), Acquisition.gov, accessed November 26, 2026
- FAR 28.102-2, Amount required, Acquisition.gov, accessed November 26, 2026
- Federal Acquisition Regulation: Exemption of Certain Contracts From the Periodic Inflation Adjustments to the Acquisition-Related Thresholds, proposed rule, Federal Register, September 26, 2022, accessed November 26, 2026
- 40 U.S.C. 3131, Bonds of contractors of public buildings or works, Legal Information Institute, accessed November 26, 2026
- 40 U.S.C. 3133, Rights of persons furnishing labor or material, Legal Information Institute, accessed November 26, 2026
- An Essential Brick and Its Chip: A Refresher on Payment Bond Claims Under the Miller Act and the “Little Miller Act”, Jason T. Strickland, Ward and Smith, May 24, 2011, accessed November 26, 2026
- Florida Statutes 255.05, Bond of contractor constructing public buildings, Florida Legislature, 2026, accessed November 26, 2026
- RCW 39.08.010, Contractor’s bond required, Washington State Legislature, accessed November 26, 2026