A certificate of occupancy (CO) is the building department’s written permission to use a building, or a part of one, for a stated purpose, issued once the final inspections find the work meets the code. Under Section 111 of the International Building Code, nobody may occupy a new building, or change what an existing one is used for, until the building official issues it. A temporary certificate of occupancy (TCO) allows move-ins in the finished, safe parts of a building while crews keep working on the rest, and it carries an expiration date chosen by the building official.
What a certificate of occupancy means
The International Building Code (IBC) is the model code published by the International Code Council (ICC), which states and cities adopt with their own amendments. Its 2021 and 2024 editions both put the certificate in Section 111. Section 111.1 bars using or occupying a building, in whole or in part, without a certificate, and bars any change of occupancy without one, though work exempt from permits needs none. Under 111.2 the building official inspects and issues the certificate only after finding no violations. Section 111.3 covers the temporary version, and 111.4 lets the building official revoke a certificate issued in error or for a building later found in violation. Some states write their own version, and Virginia’s statewide building code puts the rule in its Section 116.
Section 111.2 also lists what the certificate has to state, and most of that list is below.
| What the certificate states | What it tells you |
|---|---|
| Permit number, address and owner | Which permit the building was approved under, so its history can be traced |
| The portion of the structure it covers | Whether it’s for the whole building or one floor or tenant space |
| The code edition of the permit | The rules the building was judged against |
| Use and occupancy group | What the space may legally be used for, such as R-2 apartments or M retail |
| Type of construction | How fire-resistant the structure was built to be |
| Design occupant load | How many people the space was designed to hold |
| Whether sprinklers are required, where installed | Whether the code demanded the sprinklers or the owner added them by choice |
The groups and types on that list have their own page, occupancy and construction types.
When a certificate of occupancy is needed
A new building needs a CO before anyone moves in, an addition needs one, and so does a change of occupancy in an existing building. In New York City, any work that changes an existing building’s use, exits or type of occupancy needs a current or amended CO, and minor alterations get a Letter of Completion instead.
Change of occupancy catches people out because no new building is involved. A shop that becomes a restaurant can move from the mercantile group to an assembly group, and the new certificate waits on work a shop never needed. In Alexandria, Virginia, a food business needs the health department’s sign-off first, covering its kitchen equipment, a tested exhaust hood, grease interceptors and backflow protection.
Final inspections and sign-offs needed for a CO
The building official signs the certificate, but other people sign first. Under IBC 110.3.12 the final inspection comes once all the work on the permit is complete, and on a commercial job several agencies inspect their own pieces too. Alexandria’s published procedure lists six city offices whose approval may be needed, from planning and zoning to the health and fire departments. The checklist below follows that pattern, and many cities post their own.
| Done | Sign-off | Who gives it | What has to be true |
|---|---|---|---|
| ☐ | Building final | The city’s building inspector | All work on the permit is finished, and every earlier inspection on the card is signed |
| ☐ | Trade finals | Electrical, plumbing and mechanical inspectors | Each trade permit has its own approved final |
| ☐ | Fire alarm and sprinklers | The fire department or fire marshal | Acceptance tests passed, with stair signs, evacuation plans and a firefighters’ key box in place |
| ☐ | Elevators | The elevator inspector, under a state or city program | Each car has passed its inspection |
| ☐ | Special inspection final report | The owner’s special inspection agency, with the owner submitting it to the building official | Every required special inspection and test is documented, along with how each problem was corrected, and the report is in at the point agreed before work began (IBC 1704.2.4) |
| ☐ | Health department, where it applies | City or county health staff | Food service, pools and spas, and child care meet health rules |
| ☐ | Public works and utilities | The public works or utilities department | Sewers are clean, inspected by camera and accepted, site lights work, and accessible parking is marked |
| ☐ | Planning and zoning | Planning staff | Landscaping is planted, parking is striped, outdoor equipment is screened, and the land-use conditions are met |
| ☐ | Paperwork | The building department | Fees are paid and open violations are resolved |
Book these early. In Alexandria, the planning, public works, fire and health departments can each take up to five days to inspect, and the city warns that the certificate usually can’t be issued on the same day as the inspections. It also warns that a passed final inspection on a building or trade permit is a separate document from the CO, and nobody moves in on a final inspection alone.
Temporary certificate of occupancy (TCO)
The IBC’s rule for a TCO, Section 111.3, is short. If a portion of the building is safe to occupy, the building official may certify it before the rest of the permitted work is finished, and the certificate is good only for the period the official names. Owners ask for one because a building earns nothing until people use it. Portland, Oregon’s program guide gives the example of a leasing office opening early in a new apartment building. Some cities make TCOs an exception, and Alexandria calls them generally discouraged.
TCO requirements
The conditions below come from Portland’s commercial program and Alexandria’s procedure.
- Fire and life-safety work for the occupied area is complete and approved, or Portland approves temporary measures in some cases.
- Every inspection discipline agrees to the TCO before it is issued.
- The occupied area has free access and is fenced off from the construction where needed.
- The TCO lists the work left to do, a completion date and an expiration date.
- The owner pays a fee, and Portland can require security worth 120 percent of the unfinished work.
- Planning conditions such as landscaping still have to be met before the final certificate.
How long a TCO lasts
Defaults vary widely. Portland’s TCOs expire within 30 days unless the city notes otherwise, and an extension is negotiated with the inspector for an added fee. When the inspector returns, the final certificate is issued, a new TCO lists what’s left, or the city opens a violation case.
New York City’s TCOs typically expire 90 days after issuance and can be renewed while work remains, which can mean a renewal filing every three months until a project is done. A law the City Council passed on December 10, 2020, Local Law 6 of 2021, added the interim certificate of occupancy, which covers finished floors that pass a city inspection and stays in effect until the final certificate, with no renewals. It applies only to sprinklered buildings of noncombustible construction, and residential buildings under eight stories don’t qualify.
A worked example with two TCOs at 1200 Walnut Street
1200 Walnut Street, the fictional six-story building the book follows, puts 200 apartments on five wood-frame floors above a concrete podium, which holds the lobby, a street-level garage and two retail spaces. Its numbers are illustrative.
| When | City paper or milestone | What it opens up |
|---|---|---|
| Month 19 | First TCO, covering the podium and levels 2 to 4, with painters still on 5 and 6 | Leasing and move-ins on three of the five apartment floors |
| About three weeks later | Second TCO, adding levels 5 and 6 | Move-ins on all 200 apartments |
| Three months into lease-up | About 80 of 200 apartments leased | Rent begins to offset part of the loan interest |
| Roughly 15 months after move-ins begin | 180 apartments occupied for three straight months | The permanent loan pays off the construction loan |
Lana Landry, Fernwood Development’s development manager, splits the move-in across two TCOs. The $50 million construction loan, at an assumed 8 percent, costs Fernwood roughly $11,000 in interest a day once fully drawn, whether or not anyone has moved in. Each apartment on levels 2 to 4 leased three weeks sooner brings the building closer to the 180 the permanent lender is waiting for. Before they expire, both TCOs give way to one final certificate listing R-2 apartments, an S-2 garage and M shops.
Certificate of occupancy vs substantial completion vs final completion
The certificate of occupancy comes from the city under the building code. Substantial completion and final completion come from the construction contract, and the architect certifies both. AIA document A201-2017 sets substantial completion at the point when the owner can put the work, or a portion the parties name, to its intended use. That definition says nothing about the certificate, so an owner who wants the two dates tied together writes it into the contract, for example by making the CO’s issue date the substantial completion date.
| Certificate of occupancy | Substantial completion | Final completion | |
|---|---|---|---|
| Who decides | The building official | The architect, on AIA form G704, accepted by owner and contractor | The architect, by issuing the final Certificate for Payment |
| Where the rule comes from | The building code | The contract (A201 section 9.8) | The contract (A201 section 9.10) |
| What it says | The building or part may legally be occupied for its stated use | The work can be used as intended, with a punch list attached | All the work is done, punch list included |
| What it starts or ends | Legal move-ins | Warranties start, and builder’s risk insurance typically ends | Final payment and any retainage still held |
The punch list page follows the walk between the two contract dates, and the retainage page covers the money held back until the second.
What lenders and insurers need
A construction lender wants the certificate before it releases its last dollars. The Office of the Comptroller of the Currency, which supervises national banks, lists confirming the CO, collecting lien waivers and reading the final inspection report as controls before a bank pays a construction loan’s final draw.
On an FHA-insured apartment loan, HUD’s MAP Guide has the borrower attach a CO, or the local equivalent, for every unit and facility on its Permission to Occupy form, along with a certificate of property and liability insurance, and the lender signs that the insurance risks are covered.
New York City’s Department of Buildings warns that once a TCO expires without renewal, buying insurance, selling or refinancing can become difficult or impossible, and it tells buyers to consider closing on a final CO.
Builder’s risk insurance protects a project during construction and usually lapses at substantial completion, so the owner’s permanent property policy has to be in force by that date. Builder’s risk policies often limit coverage once people move in, too. A standard builder’s risk form reviewed by the insurance reference service FC&S in 2018 ends coverage 60 days after a building is occupied, even in part, unless the insurer agrees otherwise in writing. A policy FC&S examined in 2008 went further and barred any occupancy or use without the insurer’s written consent. Telling the insurer before any keys go out under a new TCO keeps the building from falling into a gap between the builder’s risk policy and the owner’s own.
Sources
- Chapter 1 Scope and Administration, 2024 International Building Code as adopted in the GSA Building Code 2024, UpCodes, accessed November 26, 2026
- Section 111 Certificate of Occupancy, 2024 International Building Code as adopted by the Texas Windstorm Insurance Association, UpCodes, accessed November 26, 2026
- Chapter 1 Scope and Administration, 2021 International Building Code (Colorado adoption), UpCodes, accessed November 26, 2026
- Chapter 17 Special Inspections and Tests, 2024 International Building Code as adopted in the GSA Building Code 2024, UpCodes, accessed November 26, 2026
- International Codes, Adoption by State, International Code Council, accessed November 26, 2026
- 13VAC5-63-160, Section 116 Certificates of Occupancy, Virginia Uniform Statewide Building Code, Virginia Administrative Code, accessed November 26, 2026
- Certificate of Occupancy Procedures, City of Alexandria, Virginia, Department of Code Administration, rev. August 2021, accessed November 26, 2026
- Commercial Temporary Certificate of Occupancy and Substantial Completion, Program Guide, City of Portland Bureau of Development Services, revised December 22, 2017, accessed November 26, 2026
- Temporary Certificate of Occupancy, NYC Department of Buildings, accessed November 26, 2026
- Obtain a Certificate of Occupancy, NYC Department of Buildings, accessed November 26, 2026
- Tool Kit: Certificates of Occupancy, NYC Department of Buildings, accessed November 26, 2026
- City Council Passes Interim Certificate of Occupancy Bill, NYC Department of Buildings, December 10, 2020, accessed November 26, 2026
- Local Law No. 6 of 2021, Interim Certificates of Occupancy, City of New York, accessed November 26, 2026
- Certificate of Occupancy, Los Angeles Department of Building and Safety, accessed November 26, 2026
- The Construction Schedule: Substantial Completion Considerations, AIA Contract Documents, March 1, 2024, accessed November 26, 2026
- Summary: G704-2017, Certificate of Substantial Completion, AIA Contract Documents, accessed November 26, 2026
- The Four Most Overlooked Realities of Substantial Completion, AIA Contract Documents, accessed November 26, 2026
- AIA Document A201-2017, General Conditions of the Contract for Construction, blank copy posted with bid documents, City of Rochester, New Hampshire, accessed November 26, 2026
- Substantial Completion Defined, Patrick Barthet, Construction Executive, September 8, 2020, accessed November 26, 2026
- Commercial Real Estate Lending, Comptroller’s Handbook, Version 2.0, Office of the Comptroller of the Currency, March 2022, accessed November 26, 2026
- Multifamily Accelerated Processing (MAP) Guide, 4430.G, section 12.14.3, US Department of Housing and Urban Development, revised March 19, 2021, accessed November 26, 2026
- Builders Risk Coverage Form, Christine G. Barlow, FC&S, PropertyCasualty360, July 9, 2018, accessed November 26, 2026
- Builders Risk: Does Occupancy Equal Completion?, Jim Grady, FC&S, PropertyCasualty360, July 24, 2008, accessed November 26, 2026