Retainage in construction

Updated
Written by
Alexander J. Hale
Reading time
12 min
Sheet
24 of 44

When a construction owner pays its contractor each month, it keeps back a share of the bill, usually 5 to 10 percent, until the work is finished, and that held money is called retainage, or retention in some state statutes. It gives the owner a reserve to draw on if work is left undone or done wrong, or if an unpaid trade files a lien, and the general contractor keeps back a matching share from each subcontractor, so money is held at every tier of the job. The contract sets the rate, any step-down and the release point, which is substantial completion under the AIA’s standard general conditions unless the contract moves it, and some states and the federal government cap how much can be held.

What retainage means in construction contracts

Retainage is money the contractor has already earned. The work is in place and billed, and the owner owes it but pays it at the end. A 2025 article from ConsensusDocs, a publisher of standard construction contracts, gives the owner’s reasons. Held money gives the contractor a reason to finish on time and finish well, and it covers the owner against liens, delays and defects. The first reason earns its keep at closeout, when the contractor’s people are needed on other projects and the held money is what gets someone to come back for the last punch items.

The federal government takes a narrower view. FAR 32.103 lets a contracting officer hold back part of a progress payment when the contractor’s progress hasn’t been satisfactory, requires the amount to be set case by case, and warns against using retainage in place of good contract management or withholding money without cause. For the trades, the cost is cash. A subcontractor meets payroll every week and may wait months past the end of its own work for its retainage, which a Washington State workgroup on public works payment called an unexpected barrier for firms on public jobs, noting the harm to small and diverse businesses.

Typical retainage rates and how they step down

The state limits in the table below fall between 5 and 10 percent, and federal contracts top out at 10. In the AIA’s CM-at-risk agreement, A133-2019, the parties fill in the percentage, list any items left out of it and write the terms for reducing it (section 11.1.8). The AIA’s instructions favor reducing retainage as fast as possible, provided the architect judges the work to be going well. On a bonded job the surety consents first, and AIA form G707A records that the reduction doesn’t release the surety.

Step-downs come in two main versions, and they leave the contractor with different cash in the middle of the job. In the first, the owner cuts what it holds to 5 percent of the completed work once the job is half complete, pays out the difference, and keeps 5 percent of each later bill. Illinois law points this way for private contracts, cutting the amount held at the halfway mark so no more than 5 percent stays back. In the second, the owner keeps its rate, say 10 percent, until the halfway mark and then holds nothing more from later bills, the structure the ConsensusDocs 200 owner-contractor agreement uses (section 9.2.4.1). Lawyers at Troutman Pepper Locke note that this structure fits New York’s 5 percent cap, which applies to the whole contract sum. Starting from 10 percent, both finish holding 5 percent of the contract, and the difference sits in the middle of the job. On a $60 million contract three-quarters done, the first version holds $2.25 million and the second $3 million.

When retainage is released

Under A201-2017, the AIA’s general conditions, the owner pays the retainage on the work once the owner and contractor accept the architect’s certificate of substantial completion and any surety consents, less an amount for work that is incomplete or doesn’t meet the contract (section 9.8.5). The AIA’s agreement instructions say most retainage is often paid at that point. ConsensusDocs 200 releases it at the same milestone but keeps back 150 percent of the estimated cost to finish or correct what remains (section 9.6.4). The punch list page sets substantial and final completion side by side.

Whatever is still held waits for final completion. A201 makes it due only after the contractor delivers, among other papers, an affidavit that its bills are paid, the surety’s consent and, if the owner asks, lien releases (section 9.10.2). An owner can write the whole release to final completion into the agreement. A construction lender’s holdback is a separate thing. Retainage is money the owner keeps from its contractor under the construction contract, while a holdback is loan money the bank keeps from the borrower under the loan agreement. The Office of the Comptroller of the Currency (OCC), which supervises national banks, says a bank funding a commercial project on a progress payment plan normally holds back 10 to 20 percent of each payment to cover cost overruns or unpaid supplier and subcontractor bills. The holdback usually goes out with the final draw, after the bank confirms the lien waivers, reviews a final inspection report and sees the certificate of occupancy.

How retainage flows down to subcontractors

A201 gives the general contractor seven days after it is paid to pay each subcontractor, holding back no more than the percentage the owner actually kept on that sub’s work, and has it push the same terms down to lower tiers (section 9.6.2). The general contractor page covers its other duties to subcontractors. New York lets a contractor or subcontractor keep no more than 5 percent and never more than the owner kept. California bars any lower-tier rate above the owner’s and gives the direct contractor 10 days to pass on a retention payment, though in a good-faith dispute it may keep up to 150 percent of the amount in dispute.

The longest wait belongs to the early trades. Retention is tied to the prime contract and not to each subcontractor’s work, the Washington workgroup pointed out, so a company that finishes in the first months waits for the whole project to close, and on Washington public jobs the state agencies’ own releases can stretch that into years. Washington carves out one exception for public jobs built under its general contractor/construction manager procedure, letting the owner release retainage on a subcontract finished within the first half of the contract time, after public notice and a 45-day lien period. On private work, early release exists only where the contracts provide for it, so the release clause is the first thing a sitework or foundation subcontractor should read.

The workgroup also flagged retainage in disguise, closeout or demobilization lines set as a flat percentage of the contract, paid only at the end and unconnected to real costs. The University of Houston’s master specification, for one, offers an option for closeout line items totaling 5 percent of the contract sum. The workgroup’s test for a line like that is whether it matches what closeout actually requires.

Retainage laws by state, with federal rules

These examples show the range and aren’t a 50-state survey. Statutes change, New York’s in 2023 and again in 2025, so check the current text for the project’s state.

Where Which contracts The rule
Federal, FAR 32.103 Federal construction contracts May be held when progress isn’t satisfactory, decided case by case, at most 10 percent of the approved estimated amount, and paid promptly once every contract requirement is met
New York, General Business Law 756, 756-c and 757 Private contracts of $150,000 or more, except some residential projects At most 5 percent of the contract sum for contracts entered into from November 17, 2023. For contracts from December 19, 2025, a clause asking for more is void. Released within 30 days of final approval, with 1 percent a month interest if late
California, Civil Code 8811, 8812 and 8814 Private contracts entered into on or after January 1, 2026, except residential projects of four stories or fewer that aren’t mixed-use At most 5 percent of each payment and of the contract price, unless a subcontractor fails to furnish a bond it was told would be required. The owner pays within 45 days after completion
Illinois, 815 ILCS 603/20 Private construction contracts, except houses and residential buildings of 12 or fewer units Up to 10 percent until half complete, then reduced so no more than 5 percent is held
Texas, Property Code 53.101 Private work on which a mechanic’s lien can be claimed The reverse of a cap. The owner must hold 10 percent through the work and for 30 days past its completion, a fund that secures unpaid trades and suppliers
Washington, RCW 60.28.011 Public improvement contracts Retainage must be held, at most 5 percent of money earned, a bond may replace all or part of it, and some finished subcontracts can be released early

Retainage vs a retainage bond

A retainage bond, also called a release of retainage bond, is a surety’s guarantee posted in place of the held cash. The owner pays out the retainage and relies on the bond for what the cash was covering.

Cash retainage Retainage bond
What the owner holds The contractor’s earned money A surety’s promise to pay if the contractor doesn’t perform
Cost to the contractor The wait for its money A premium, typically 1 to 2 percent of the bond amount according to a 2026 Miller Nash guide, plus personal guarantees to the surety
Owner’s say Sets the rate, within the law Can refuse it unless a statute or the contract requires acceptance
What it covers What the contract says retainage is for What the bond’s wording says, sometimes with a deadline for claims

Washington requires a public owner to accept a qualifying retainage bond, the Miller Nash guide explains, unless the owner can show good cause or another narrow exception applies, and ConsensusDocs 200 lets the contractor offer a retention bond or other security the owner accepts. The Washington workgroup heard of prime contractors charging subcontractors an administrative fee on top of the premium when they bonded off their own retainage. A retainage bond can also overlap a performance bond already on the job, which the Miller Nash guide gives as one reason some owners and general contractors push back.

Retainage accounting

On a contractor’s books, retainage shows up on both sides. Under the revenue standard, ASC Topic 606, retainage the owner owes counts as a receivable only when the right to it is unconditional, meaning nothing but time stands in the way. Retainage that still depends on the contractor’s future work goes into that contract’s single net contract asset or contract liability, a point a 2025 Financial Accounting Standards Board (FASB) staff paper clarified without changing the rules. Retainage carried as a receivable has its own disclosure under ASC 910-10-50-7, including how much the contractor expects to collect after more than a year, and sureties told the FASB that retainage figures feed their analysis.

The general contractor’s retainage on its subcontractors is the mirror image, a liability. Contractors usually classify contract-related balances as current because they clear in the normal course of finishing the job, even when that takes more than a year. Sample statements from the Construction Industry CPAs/Consultants Association (CICPAC) fold retainage owed to subcontractors into accounts payable and add a note giving the amount and the part not expected to be paid within a year. A $400,000 subcontractor bill with 10 percent held becomes $360,000 due now and $40,000 held until release.

Retainage at 1200 Walnut Street, worked through

1200 Walnut Street, the fictional six-story building the book follows, has a $60 million guaranteed maximum price (GMP), and every number here is illustrative. Fernwood Development’s contract follows the first version above, with a 10 percent rate that falls to 5 percent of everything completed once the job passes the halfway mark. Pay application 9, which the pay applications page follows from the form to the bank, still lost the full 10 percent, $335,000 of $3,350,000 billed. Nothing comes back at substantial completion. The city’s first temporary occupancy certificate arrives in month 19, and Fernwood pays the whole amount at final completion, roughly three months on. The table ignores change orders and sets Walnut Street beside two other ways to write the same contract.

Work completed to date Walnut Street, 10 percent then 5 percent of the total Flat 10 percent 10 percent, then nothing held after half
$30 million, before the step-down $3.0 million held $3.0 million $3.0 million
$30 million, after the step-down $1.5 million, with $1.5 million paid back $3.0 million $3.0 million
$45 million $2.25 million $4.5 million $3.0 million
$60 million, work complete $3.0 million $6.0 million $3.0 million
Final completion, about month 22 All $3.0 million paid All $6.0 million paid All $3.0 million paid

The $3 million held at the end is about the size of the contractor’s whole fee, which Walnut Street’s numbers put at $2.4 million to $4.2 million, though most of it belongs to the roughly 30 subcontractors. Picture, as an illustration, the excavation subcontractor that dug the shallow street-level garage in the first months, the dig where loose fill turned up in month 2. Its work ends early in the job, and it still waits until about month 22 for its share. Fernwood has its own reason to hold on, since every retained dollar is one not yet drawn on the construction loan, and at the assumed 8 percent rate $3 million left undrawn saves about $660 a day in interest.

Sources