Pay applications and the schedule of values

Updated
Written by
Alexander J. Hale
Reading time
11 min
Sheet
23 of 44

A pay application, or payment application, is the contractor’s monthly bill on a construction project, measured line by line against the schedule of values, a priced list that divides the contract sum among the parts of the job and goes to the architect ahead of any billing. On contracts written on American Institute of Architects (AIA) forms, the G703 continuation sheet lists each line’s value, the work done so far and the materials stored, and the G702 application and certificate for payment totals those lines, subtracts the share the owner holds back until the end, called retainage, and what was certified before, and shows the amount due this month. The architect certifies what is owed, and on a financed job the owner’s lender pays it from the construction loan once lien waivers and the bank’s own inspection back the number up.

What a schedule of values is

Every dollar of the price has to land on some line, so the lines total the contract sum exactly. A201-2017, the AIA’s general conditions, asks for a schedule of values on fixed-price (stipulated sum) and guaranteed maximum price (GMP) contracts and has the contractor submit it before the first application (section 9.2). The architect decides the format, and once it has no objection the schedule is the basis for reviewing each application.

The AIA’s G703 instructions let the lines follow sections of the work or the subcontracts, and they ask for the same breakdown from start to finish. Detail is what makes a bill checkable. With one line for a building’s acoustic ceilings, the architect Bill Schmalz wrote in a 2018 post for the AIA’s contract administration community, the reviewer must walk the whole building each month and still has only a rough figure. Grid and panel lines for each floor let the reviewer skip floors with nothing billed. The University of Houston’s master specification takes its lines from the project manual’s table of contents, one or more per specification section, and adds a dedicated line wherever bought but uninstalled material may be billed.

On a cost-plus job with a GMP, the AIA’s summary form is G702GMP-2021, whose first line reads “Original Guaranteed Maximum Price,” paired with a continuation sheet, G703CW-2021, that tracks how actual costs drift from the estimate.

Front-loading

Front-loading puts more of the price on the first lines built, such as mobilization, excavation and foundations, than that work is worth. Kevin O’Beirne, writing on the Construction Specifications Institute’s blog in 2022, traces the habit to cash flow, since a contractor pays crews and suppliers before the owner pays it. Owners and sureties want each payment to match acceptable work, because they fear a default. A contractor that has already collected for inflated early lines leaves behind a balance that may not pay a replacement to finish, and A201 lets the architect withhold a certificate on reasonable evidence that the unpaid balance won’t complete the work (section 9.5.1.4). The Office of the Comptroller of the Currency (OCC), which supervises national banks, puts “draw requests ahead of schedule for work yet to be completed” on its list of warning indicators for bank examiners.

How a pay application works, month by month

The days in steps 3 to 6 are A201’s, and many contracts change them.

  1. The general contractor collects each subcontractor’s bill, tests each percentage against the work actually in place, and gathers the backup for stored materials and last month’s lien waivers.
  2. A draft goes to the architect and owner. The University of Houston template wants it seven days before the application is due.
  3. The formal application, a signed G702 with the G703 attached and notarized if the contract requires it, reaches the architect ten or more days ahead of the payment date (A201 section 9.3.1).
  4. Within seven days the architect certifies all of it, certifies part with written reasons, or withholds all of it with reasons (9.4.1).
  5. On a financed job the owner sends the certificate to its lender inside a draw request, then pays. Each subcontractor’s payment is due within seven days after the general contractor is paid, short only by the retainage rate the owner applied to that sub’s part of the work (9.6.2).
  6. If the architect doesn’t act within seven days through no fault of the contractor, or the owner pays more than seven days late, the contractor may give seven more days’ notice and then stop work until paid (9.7).

The AIA G703 continuation sheet, column by column

The AIA’s current continuation sheet is the 1992 edition. The table gives each column, then fills it in for one illustrative line, windows on a five-floor apartment job. Last month that line showed $300,000 installed and $250,000 more in storage. This month crews installed $350,000 of work, $200,000 of it windows taken from storage, and a new $180,000 delivery arrived.

Column on the form What goes in it The windows line this month
A, item no. The line number 12
B, description of work The section of the work or the subcontract Windows, levels 2 to 6
C, scheduled value The line’s share of the price. Change orders usually go on added lines at the end or on a separate sheet $1,200,000
D, work completed from previous application Last month’s D plus E, never last month’s stored materials $300,000
E, work completed this period This month’s work, including stored materials that got installed $350,000, with the $200,000 of windows that left storage
F, materials presently stored (not in D or E) Everything delivered and not yet installed, recounted monthly $230,000, which is $250,000 minus $200,000 installed, plus $180,000 delivered
G, total completed and stored to date D plus E plus F $880,000
Percent (G ÷ C) How far along the line is 73
H, balance to finish C minus G $320,000
I, retainage (if variable rate) Normally used only when the holdback rate varies by line Blank, since one rate covers the job

The line stood at $550,000 last month and $880,000 now, so it adds $330,000 to the bill, or $297,000 after 10 percent retainage. Adding the $350,000 installed to the $180,000 delivered would bill $530,000 and charge the owner twice for $200,000 of windows.

Column F starts most arguments. Unless the contract says otherwise, A201 pays for materials delivered and suitably stored on site. Materials kept elsewhere qualify only if the owner approves in advance and the location is agreed in writing, and either way the contractor must follow procedures the owner accepts for securing its title (section 9.3.2). The University of Michigan’s form for stored materials asks for paid receipts and, when the material is off site, a storage address the owner can visit, photos showing a readable packing slip, and an insurance certificate naming the university. The AIA’s instructions add a rule newcomers miss. Paying for stored materials doesn’t move them out of column F. Installing them does.

The AIA G702 application and certificate for payment

The G702 is a single page. Its left side has nine numbered lines that sum up the G703, and its right side carries the contractor’s signature, a notary block and the architect’s certificate.

Line on the form How it’s figured
1. Original contract sum The price in the agreement
2. Net change by change orders Approved changes, added and deducted
3. Contract sum to date Line 1 plus or minus line 2
4. Total completed and stored to date The column G total from the G703
5. Retainage Held on completed work (5a) and on stored material (5b), at rates that can differ
6. Total earned less retainage Line 4 minus line 5
7. Less previous certificates for payment Line 6 of the last certificate
8. Current payment due Line 6 minus line 7
9. Balance to finish, including retainage Line 3 minus line 6

The holdback on line 5 has its own rules, covered on the retainage page. Line 2 takes only approved change orders, though A201 also lets the contractor bill work properly authorized by a construction change directive before the change order is signed (section 9.3.1.1). A change still being priced with no directive behind it, the kind tracked through RFIs, submittals and change orders, stays off the bill.

Who certifies a pay application

The contractor’s signature comes first. By signing, the contractor states, as far as it knows, that the billed work follows the contract documents, that the subcontractors and suppliers behind every earlier paid certificate have received their money, and that the amount shown is now due. The architect’s certificate then makes three representations to the owner, limited to what the architect knows from the work and the application. The work has reached the stage billed. Its quality meets the contract documents. The contractor is entitled to the amount certified (A201 section 9.4.2). A201 is plain about the limits. The certificate isn’t an exhaustive inspection, a review of how the contractor builds or an audit of where earlier payments went. A cut comes with the architect’s initials on each changed figure and a written explanation. The owner pays on the certificate, and a lender runs its own check.

How the lender’s draw and lien waivers ride along

The certified application becomes the core of the owner’s draw request, its monthly request for a share of the construction loan. Lien waivers from the trades and suppliers go inside that request, and the OCC’s handbook for bank examiners has the borrower certify in it that those firms have been paid. According to the same handbook, banks typically require an architect’s or engineer’s inspection report with each draw, and the lender’s title policy should be brought up to date with each draw so the title company can confirm no liens are outstanding. A bank’s policy, it adds, should have the borrower’s equity in the project before loan money starts going out.

A mechanic’s lien is an unpaid builder’s or supplier’s legal claim against the land and building it worked on, and a lien waiver is the signed paper that gives up that claim in exchange for payment, both covered on the lien waivers page. On a monthly job the paper trails the money by one cycle. California’s contractors board advises owners to get a conditional release before each payment and an unconditional release after it. The state’s conditional form is effective only once the claimant receives payment from the bank the check is drawn on, and the unconditional form warns that it can be enforced against a signer who was never paid. So this month’s application carries conditional releases for this month’s money and unconditional ones for last month’s.

Pay application 9 at 1200 Walnut Street

1200 Walnut Street, the fictional six-story building the book follows, is a $60 million GMP job for Fernwood Development, and every number here is illustrative. Pay application 9 covers month 9 of a build of about 20 months, with the wood-frame apartment floors going up. Line 8 of the G702 is the current payment due, line 6 minus line 7. The retainage rate hasn’t changed since application 8, so line 8 equals this month’s added billing less the 10 percent held on it.

Step Who Amount What has to be in hand
This month’s work plus the rise in stored material, on the G703 Nia Newman, assistant project manager for the contractor $3,350,000 Each subcontractor’s percentage checked against the building
Retainage at 10 percent Minus $335,000 The job isn’t yet half done, when Walnut Street’s rate drops to 5 percent
Line 8, current payment due The contractor, signing before a notary $3,015,000 Last month’s unconditional waivers in the file
Architect’s certificate Rosa Archer, the project architect Up to $3,015,000 Her own site visits behind the percentages
Draw request Lana Landry, Fernwood’s development manager $3,015,000 requested Fernwood’s equity already spent, so the loan pays from here on
Funding The bank’s loan officer From the $50 million construction loan An inspection report and a clean title update

Each draw adds to the balance the bank charges interest on. At the assumed 8 percent rate, this one adds about $660 a day to Fernwood’s interest bill for as long as the loan stays out.

Why a pay application gets cut

A201 lets the architect cut a certificate only as far as needed to protect the owner, and section 9.5.1 lists the grounds.

What the reviewer finds Where the rule comes from
A percentage ahead of the work in place A201 9.4.2 and 9.5.1
Stored materials without the title proof, insurance or agreed storage site the owner requires A201 9.3.2
A change billed before it’s approved or directed A201 9.3.1.1
Missing lien waivers or other backup the owner asked for A201 9.3.1
Subcontractors not paid out of last month’s money A201 9.5.1.3
Defective work still not fixed A201 9.5.1.1
A balance too small to finish, or a delay the balance won’t cover in damages A201 9.5.1.4 and 9.5.1.6
A form left incomplete Some owners’ specifications, such as the University of Houston’s, send it back without action

Once the reason is cleared, A201 has the architect certify what it held back (section 9.5.3), so a cut usually moves money into next month’s bill.