What is a GMP (guaranteed maximum price)?

Updated
Written by
Alexander J. Hale
Reading time
11 min
Sheet
20 of 44

A guaranteed maximum price (GMP) is a cap on a construction contract under which the owner pays the contractor’s actual costs plus a fee. The owner reimburses documented costs up to that cap, the contractor pays for anything above it unless a change order raises it, and money left under it goes back to the owner unless the contract splits it. GMPs are the usual price on construction manager at risk jobs, where the builder commits to the number once the design is far enough along to price, a point that Maryland’s procurement rules set at no earlier than 50 percent of the construction documents and the federal rules for General Services Administration jobs generally at 75 percent.

What a GMP means in a construction contract

A133, the American Institute of Architects (AIA) standard agreement for this arrangement, adds up three figures to reach the GMP. They are the construction manager’s estimate of the cost of the work, its own contingency, and its fee. The federal General Services Administration (GSA) builds the number from the same pieces on its at-risk jobs and caps the final settlement at that total.

The owner doesn’t write a check for the GMP. Each month it pays the contract sum, which A133 defines as the cost of the work plus the fee, and the GMP caps that sum. Cost of the work means the costs the contractor necessarily incurs to build the job properly, limited to the categories the agreement lists. Because the owner pays real costs, A133 lets the owner and its auditors see the contractor’s job cost reports, subcontracts, invoices and receipts, and builders call this an open-book contract. Under a lump sum the contractor’s actual costs stay private.

The cap also moves. Owner-requested changes, corrections to the drawings and hidden site conditions usually reach it through change orders, which the RFIs, submittals and change orders page walks through, so the GMP at closeout is the signed number plus or minus every approved change.

What’s inside a GMP

Labels vary from contract to contract. These are the usual pieces.

Line What it pays for What happens to money left over
Cost of the work Subcontracts, materials, equipment and the contractor’s own crews Becomes savings, kept by the owner or shared, as the contract says
General conditions Costs of running the site, such as supervision, site setup, temporary construction, safety, testing, housekeeping, bonds, permits and insurance Same as the cost of the work
Contractor’s contingency Errors of the contractor’s own making that no change order covers, such as estimating mistakes and scope gaps found at buyout Usually returns to the owner, sometimes split
Allowances Sums held for items nobody has picked yet, such as tile or light fixtures Trued up by change order once the real price is known
Fee The contractor’s profit and its head-office costs Set as a lump sum or a percentage. The contract says how it moves when the work changes

Massachusetts law requires a public CM at risk GMP to break the cost down by trade and to show the contingency, the general conditions and the fee as separate dollar amounts. Private owners should ask for the same layout, because a single “overhead” line hides the three numbers most worth watching.

None of these lines holds the owner’s contingency. That reserve lives in the owner’s own project budget, next to soft costs such as design fees and loan interest. The contingency vs allowance page sorts out which reserve pays for what.

How to read a GMP proposal

Under A133 the GMP proposal arrives with a written statement of its basis, and that statement defines what the owner is buying more exactly than the total does. Read it in this order.

  1. The drawings list. Every sheet and specification the price rests on, with dates. Work shown only on a later revision sits outside the number.
  2. Clarifications and assumptions. What the contractor priced wherever the drawings were silent. Where the final drawings depart from one of these, expect a change order.
  3. Cost by trade, with allowances. Check each allowance against what the owner expects to choose.
  4. The contingency and the fee. Weigh the contingency against how complete the drawings were.
  5. The substantial completion date. The general conditions are priced to it.
  6. The acceptance date. The price holds only until then.

When the GMP is set

Under construction manager at risk, the owner hires the builder partway through design, pays it to estimate and check the drawings during preconstruction, and asks for the GMP once enough is drawn to price. The project delivery methods page compares that method with design-bid-build and design-build. Some public owners put a floor under the timing in law or regulation.

Public rule Earliest point for the GMP
Maryland procurement regulations, COMAR 21.05.10.04 Design documents at least 50 percent construction documents for the scope being priced
Massachusetts General Laws, chapter 149A, section 7 At least 60 percent construction documents, signed before construction starts, though early work can go ahead under a separate amendment
GSA acquisition manual, section 536.7105-2 Generally no earlier than 75 percent construction documents, and before 100 percent

Setting the number early gives the owner a ceiling sooner, but the price leans on more guesses, and GSA’s manual notes that early designs may call for a bigger contractor’s contingency. Waiting yields a tighter number, though if it lands over budget there is less design time left to take scope out. For a building whose floors repeat, such as an apartment block, late in construction documents is usually the better moment, since by then the repeating floors are drawn and a modest contingency can carry what’s left.

Savings and overruns under a GMP

Costs above the cap belong to the contractor, and A133 says the owner doesn’t reimburse them. An overrun eats the contractor’s contingency, then the fee it expected to earn, then the firm’s own money.

Plenty of extra cost never counts as an overrun. A133 keeps inside the GMP any further design development that is reasonably inferable from the documents the contractor priced. A change of scope or systems, or a switch to a different kind or quality of product, comes by change order and raises the cap. The Massachusetts Clean Energy Center’s edited version of the form lists design changes, design corrections and concealed conditions among the costs that go to a change order instead of the contractor’s contingency.

Below the cap, the outcome is negotiated. The AIA form leaves a blank for “bonus, cost savings or other incentives,” and contracts fill it in very differently.

Contract Savings below the GMP
AIA A133, as published Blank, for the parties to write in a bonus, a shared-savings split or nothing
Massachusetts public CM at risk law All to the public owner. The firm can’t share savings, and any incentive is capped at 1 percent of estimated construction cost
GSA’s federal clause A share for the contractor, at a percentage the contracting officer fills in for each contract
Owner-edited A133 copies from the City of Happy Valley, Oregon, and the Massachusetts Clean Energy Center 100 percent to the owner, by language each owner wrote into the blank

Owners often accept a split because it gives the contractor a reason to hold costs down, and some contracts share unused contingency too. None of it is standard. The AIA’s best-practice note on contingencies says leftover contractor’s contingency on a CM job belongs to the owner.

Here is one hypothetical $20 million GMP settled three ways. The 75/25 split is made up for the example.

Outcome Actual cost of the work plus fee Owner pays Contractor’s result
$600,000 over the cap $20.6 million $20.0 million Absorbs $600,000
$600,000 under, all savings to the owner $19.4 million $19.4 million Cost plus fee, nothing more
$600,000 under, savings split 75/25 $19.4 million $19.55 million Cost plus fee and a $150,000 share

GMP vs lump sum vs cost plus

The general contractor page has the short version of who pays an overrun under each. On a real job, the bigger differences are when the price stops moving and how much the owner gets to see.

Lump sum (stipulated sum) Cost plus a fee, no cap Cost plus a fee with a GMP
Price fixed At bid or award, usually on finished drawings Never When the GMP is signed, often before the drawings are finished
What the owner sees The price and a billing breakdown Actual costs Actual costs, with audit rights
Savings go to The contractor The owner The owner, or shared if the contract says so
AIA owner-contractor form A101 A103 A102, or A133 with a construction manager
Usual fit A clearly defined scope Large or complex projects Large projects where the owner wants a maximum price

Of the three, the GMP asks the most of the owner’s staff. Someone has to read monthly cost reports, question contingency draws and audit the final accounting, work a lump-sum owner never does.

Where GMPs go wrong

  1. Reading the cap as a fixed price for whatever the design becomes. An article published by the Construction Management Association of America (CMAA) traces many GMP disputes to this gap. Owners tend to see a firm price for the whole project, while construction managers see a number tied to what was shown when it was set.
  2. Signing too early. Fewer drawings mean more assumptions, a bigger contingency and more change orders later. The same CMAA article singles out a GMP set before design or pricing is settled.
  3. Vague contingency rules. Who approves a draw, above what amount, and who keeps the rest are all contract terms, and public owners set them very differently. The City of Happy Valley’s edited copy of A133 makes the construction manager seek approval for any single draw over $10,000 and lets the owner review draws weekly. The Massachusetts Clean Energy Center’s edited copy adds a blank for a monthly sum the construction manager may spend without asking.
  4. Thin allowances. An allowance set below what the owner will really pick makes the GMP look smaller than the building. Under A201, the AIA’s standard terms for construction, the difference comes back as a change order.
  5. Treating each line as its own cap. A133 says the split of the GMP in the schedule of values is not a separate maximum for each line. A cheaper drywall buyout can pay for a pricier elevator before anything counts as savings to the owner.

At 1200 Walnut Street

At 1200 Walnut Street, the fictional six-story building the book follows, the contractor came on as construction manager at risk once schematic design was finished. Victor Price, its chief estimator, priced from the 90 percent set, a Friday issue, on a three-week deadline. All Walnut Street figures are illustrative.

Piece Walnut Street Basis
The GMP $60.0 million About 200,000 gross square feet at about $300 each, or $300,000 for each of 200 apartments
Fee $2.4 million to $4.2 million 4 to 7 percent of the GMP
General conditions $3.6 million to $7.2 million Roughly 600 days at about $6,000 to $12,000 a day
Cost of the work plus the contractor’s contingency About $48.6 million to $54.0 million Worked out here by subtraction, $60.0 million less the fee and general conditions ranges above, and not a figure set for the building
Fernwood’s owner’s contingency $3.0 million Not in the GMP. Equal to 5 percent of it, held in Fernwood Development’s budget

With the $60 million GMP signed, Fernwood’s lender closed the construction loan. The GMP is the biggest line in the $87 million development budget that the loan and Fernwood’s equity pay for together. A late unit-plan revision had moved one drain stack, but the 90 percent set behind the GMP still drew it on its old route. In the field the moved stack came down on a podium beam, and Fernwood and the contractor argued over which contingency should pay for the fix.