Contingency vs allowance in construction
- Updated
- Written by
- Alexander J. Hale
- Reading time
- 11 min
- Sheet
- 22 of 44
An allowance is a sum written into a construction contract for work everyone knows is coming but nobody has chosen yet, such as lobby light fixtures, and it’s trued up by change order once the real price is known. A contingency is money held back for costs nobody can name yet, and a typical job carries three of them, with the design contingency inside the estimate, the contractor’s contingency inside the contractor’s price and the owner’s contingency in the owner’s own budget. Which pot pays for a given problem depends on what caused it and on what the contract says each pot may be spent on.
Allowance vs contingency at a glance
| Pot | Where it sits | Who controls it | What it pays for | What happens to the rest |
|---|---|---|---|---|
| Allowance | Inside the contract sum, and inside a GMP | The owner picks the item, and the contractor buys and installs it | A named item whose details aren’t settled | The contract sum moves up or down by change order |
| Design contingency | Inside the estimate, before the price is fixed | The owner, holding it for the architect’s use | Design detail not drawn yet | Shrinks as the drawings are finished, and any remainder is the owner’s |
| Contractor’s contingency, often called the construction contingency | Inside the GMP | The contractor, under the contract’s approval rules | The contractor’s own misses that no change order covers | Usually returns to the owner, sometimes shared |
| Owner’s contingency | Outside the construction contract, in the owner’s budget | The owner, with its lender watching the balance | Change orders during construction | Stays with the owner |
The cost policy of the US General Services Administration (GSA) follows an ASTM standard and gives each idea one line. Allowances cover planned items until they can be better defined, contingencies cover unintended events nobody directly controls, and reserves are held by management for changes in what the project needs. GSA also bars estimators from hiding either one inside unit prices or quantities, so each shows up as its own line.
Owner’s contingency vs contractor’s contingency vs design contingency
Owner’s contingency
The owner keeps this pot outside the contract and spends it through change orders. The American Institute of Architects (AIA) lists its uses as errors and omissions in the construction documents, changes to the project’s scope and unknown conditions. On a real job that means the owner changes its mind, a drawing proves wrong although nobody was negligent, or the ground or an existing building hides something that differs materially from the contract documents, which AIA’s A201 contract terms make the contractor report within 14 days.
Lenders watch this pot closely. The Office of the Comptroller of the Currency (OCC), which supervises national banks, tells its examiners that construction budgets typically carry a contingency for unanticipated overruns, usually 5 to 10 percent of the overall budget, and the handbook’s internal control questionnaire asks whether a bank makes independent proofs of its contingency accounts at least monthly.
Contractor’s contingency
This pot sits inside the guaranteed maximum price (GMP), and it pays for the contractor’s own misses. GSA’s federal clause gives the contractor sole use of the money for reimbursable costs that no change order covers, and names mistakes in estimating, scheduling and planning among them. The Massachusetts Clean Energy Center’s edited version of the AIA form adds scope gaps found during buyout, when the contractor signs its subcontracts. An article published by ConsensusDocs, which issues standard construction contracts, also lists escalation, acceleration, subcontractor default and general conditions overruns.
The line it can’t cross is work that already earns a change order. A cost that raises the GMP, such as an owner’s change or a design correction, comes from the owner’s pot. Fixing the contractor’s own bad work is where contracts part ways. ConsensusDocs lists fixing it as a common use of the contingency, while the Massachusetts agency’s edited form makes the contractor pay for it outright. On a design-bid-build job the contractor’s cushion is hidden inside its lump sum, the fixed price the general contractor page describes, and AIA’s note suggests putting a contingency amount in the bid documents, or telling bidders that one will be negotiated at award. The project delivery methods page explains how those methods differ.
Design contingency
The design contingency covers detail the designers haven’t drawn yet, and it lives in the estimate during design. AIA’s best-practice note says the owner holds it for the architect, who draws on it only with the owner’s approval, and on construction manager jobs it can run into construction so the architect has room to work out design issues. GSA’s policy steps it down as the drawings mature, reaching zero on final construction documents. Once a GMP is signed, AIA’s A133 agreement folds whatever further design development is reasonably inferable from the priced drawings into the GMP itself, so that late detail becomes the contractor’s to carry.
Construction contingency percentage: what published guidance says
Vendor blogs quote all sorts of figures. These are the ones with an agency or professional body behind them.
| Source | Pot | Published size |
|---|---|---|
| GSA cost policy P-120 (2022), new construction | Design contingency, as a share of direct cost | Planning 10 percent, concept design 7.5 to 10, design development 5 to 7.5, 75 percent construction documents 2 to 5, 90 percent construction documents 1 to 3, final documents 0 |
| AIA Best Practices (2023) | Design contingency | Typically 5 to 10 percent of overall construction cost |
| GSA acquisition manual, section 536.7105-2 | Contractor’s contingency on GSA’s CM at risk jobs | No more than 3 percent of the estimated cost of the work, or up to 5 percent with written approval |
| GSA cost policy P-120 (2022) | Owner’s construction contingency | 7 percent for new construction, 10 percent for modernization and for repair and alteration work, as a share of estimated construction cost at award |
| OCC Comptroller’s Handbook, Commercial Real Estate Lending (2022), page 32 | All contingency in a construction loan budget | Usually 5 to 10 percent of the overall budget |
| AIA Best Practices (2023) | Owner’s contingency | No one-size-fits-all amount |
Watch the base. GSA measures its owner’s contingency against construction cost, and the OCC measures against the overall budget, soft costs included, so the same dollars read as a bigger percentage under GSA’s rule than under the bank’s. The AIA note gives one real example of building an owner’s contingency from its parts. On the Utah State Capitol, the owner carried 3 percent for program and design, 2 percent for risk and 1 percent for political factors, 6 percent in all. A contingency built from named risks like that holds up better in a budget meeting than a flat percentage, because each dollar has a reason attached.
How allowances reconcile
Under A201, the contractor puts every allowance stated in the contract documents into its price, and the owner picks the items with reasonable promptness. Unless the contract says otherwise, the allowance covers only the cost of the materials and equipment delivered to the site, with taxes and less trade discounts. Unloading, handling, labor, installation, overhead and profit are priced separately, in the contract sum. When the real cost lands above or below the allowance, a change order adjusts the contract sum by the difference, plus any change in the contractor’s handling and installation costs.
In Canada, the standard stipulated price contract, CCDC 2 2020, calls this kind of sum a cash allowance and adds a pooling rule that A201 lacks. An overrun on one cash allowance is first covered by money left unspent on the others, and the contractor gets overhead and profit only on any net excess across all of them. The same Canadian contract has a separate contingency allowance, which already includes the contractor’s overhead and profit and is spent through change orders and change directives.
Here is a hypothetical reconciliation under A201’s default rules.
| Allowance | In the contract | Actual delivered cost, with tax, less discounts | Change order |
|---|---|---|---|
| Lobby light fixtures | $40,000 | $46,200 | Adds $6,200 |
| Door hardware | $25,000 | $22,000 | Deducts $3,000 |
| Net | $65,000 | $68,200 | Adds $3,200, plus any change in installation cost |
The electricians’ labor to hang the fixtures was in the contract sum all along. If the owner’s choice takes more work to install than the drawings assumed, that difference joins the same change order. Some owners tighten the rules. The University of Houston’s master specification allows no change in the contractor’s indirect costs when the owner picks a higher- or lower-priced product of the same kind, and it credits any unused contingency allowance back to the owner at closeout. On a GMP job the allowances sit inside the cost of the work, and the RFIs, submittals and change orders page covers how the change order itself gets signed.
Which pot pays for what
| What happened | Pot that usually pays | Why |
|---|---|---|
| The owner adds a room or upgrades a finish after the price is signed | Owner’s contingency, through a change order | A change in scope moves the GMP under A133 |
| A drawing is wrong and nobody was negligent | Owner’s contingency, through a change order | The Massachusetts agency’s edited A133 sends design corrections to change orders |
| Buried conditions differ materially from the contract documents | Owner’s contingency, through a change order | A201 allows an adjustment after prompt notice, once the architect confirms the difference |
| The estimator missed work the drawings clearly showed | Contractor’s contingency | An estimating error earns no change order |
| A trade package buys out above what was carried | Contractor’s contingency, often after savings on other packages | The schedule of values isn’t a separate cap for each line, and some contracts move buyout savings into the contingency |
| A subcontractor goes broke mid-job | Contractor’s contingency | ConsensusDocs lists subcontractor default among the usual uses |
| The contractor’s crew builds something wrong | The contractor, from its contingency or its own pocket, depending on the contract | Under A201, work the architect rejects is corrected at the contractor’s cost |
| The owner’s chosen tile costs more than the allowance | The owner’s budget, through the allowance change order | A201 adjusts the contract sum by the difference |
| Detail not yet drawn when the estimate was made | Design contingency before the GMP, the GMP itself after | GSA’s design contingency, then A133’s reasonably inferable rule |
At 1200 Walnut Street
At 1200 Walnut Street, the fictional six-story building the book follows, Fernwood Development set its owner’s contingency at $3.0 million, a sum equal to 5 percent of the $60 million GMP. Fernwood plans to spend $87 million in all, so the owner’s pot alone comes to 3.4 percent of the total, short of the OCC’s 5 to 10 percent, though the contractor’s separate contingency inside the GMP adds to the cushion. All Walnut Street figures are illustrative.
About eight months into construction, during rough-in, the plumbing crew found a drain stack coming down onto a podium beam. Rosa Archer, the project architect, had moved that stack in a late unit-plan revision. The revision came after the last weekly clash run and after the plumbing foreman’s sleeve check for that area, but before the GMP, so the 90 percent set that Victor Price, the contractor’s chief estimator, priced still drew the earlier route.
Each side wanted the other’s pot to pay. Victor’s case rested on the drawing list behind his GMP, which named the 90 percent set and nothing later. Lana Landry, Fernwood’s development manager, pointed to the preconstruction fee Fernwood had paid the contractor to coordinate the drawings. After two weeks of letters, the two of them settled it in a single meeting.
| Cost | Who paid | From which pot |
|---|---|---|
| Crew hours to take down the pipe already hung on the old route | The contractor | Its contingency inside the GMP |
| Redesign and new pipe | Fernwood | Its $3.0 million owner’s contingency |
What newcomers get wrong
- Assuming “construction contingency” always means the same pot. In the Massachusetts Clean Energy Center’s edited A133, the Construction Contingency is the contractor’s money inside the GMP. In GSA’s cost policy, the same words name the owner’s own contingency for changes in contract cost during construction. Ask whose it is before discussing what it covers.
- Treating an allowance overrun as the contractor’s problem. Under A201 the contract sum moves with the owner’s choice, so a pricier fixture is the owner’s cost.
- Reading leftover contractor’s contingency as the contractor’s profit. AIA’s best-practice note says that on a construction manager job the remainder belongs to the owner, and the Massachusetts agency’s edited form returns the unused balance to the owner by a deductive change order.
- Using one flat percentage for every pot and every stage. GSA’s design contingency falls from 10 percent to zero as the drawings are finished, its CM at risk contingency is capped at 3 percent without written approval, and AIA declines to name one figure for an owner’s contingency.
Sources
- AIA Document A201-2017, General Conditions of the Contract for Construction (sample), American Institute of Architects, posted by the City of Rochester, NH, accessed November 26, 2026
- AIA Document A133-2019, Owner and Construction Manager as Constructor, Cost of the Work Plus a Fee with a Guaranteed Maximum Price, contract exhibit, City of Happy Valley, Oregon, accessed November 26, 2026
- AIA Document A133-2019, Exhibit E1 to a solicitation, Massachusetts Clean Energy Center, accessed November 26, 2026
- GSAR 552.236-79, Construction-Manager-As-Constructor, Acquisition.gov, accessed November 26, 2026
- GSAM 536.7105-2, Guaranteed Maximum Price, Acquisition.gov, accessed November 26, 2026
- P-120, PBS Cost and Schedule Management Policy Requirements (GSA Order PBS 1000.6B), US General Services Administration, November 7, 2022, hosted by the Whole Building Design Guide, accessed November 26, 2026
- Managing the contingency allowance, David H. Hart, AIA Best Practices, November 30, 2023, accessed November 26, 2026
- Comptroller’s Handbook: Commercial Real Estate Lending, Version 2.0, Office of the Comptroller of the Currency, March 2022, accessed November 26, 2026
- The Contractor’s Contingency: What Contractors and Construction Managers Need to Know and Be Wary Of, Sklyer Santomartino, ConsensusDocs, November 3, 2023, accessed November 26, 2026
- CCDC 2 2020, Stipulated Price Contract, Canadian Construction Documents Committee, copy posted by the District of Hudson’s Hope, accessed November 26, 2026
- Section 01 2100, Allowances, University of Houston Master Specification, July 2023, accessed November 26, 2026