How construction loans work

Updated
Written by
Alexander J. Hale
Reading time
9 min
Sheet
15 of 44

A construction loan is a short-term loan that pays for a building in monthly installments, called draws, as the work goes in, and the borrower typically owes interest only on the money drawn so far. The lender caps it at a share of the project’s total cost and of the finished building’s appraised value, insists the owner’s own money is spent first, checks every draw against the work in place, and is repaid when a long-term permanent loan replaces it after the building is complete and rented. A home construction loan follows the same pattern for one house and often turns into the owner’s mortgage at the end.

How lenders size a construction loan with loan-to-cost and loan-to-value

Loan-to-cost divides the loan by the total development cost, which counts land, construction, design and permit fees, contingency, and the loan’s own interest and fees. Loan-to-value divides it by the appraised value. A building that doesn’t exist yet has no sale price, so the appraiser estimates future values, and the handbook the Office of the Comptroller of the Currency (OCC) writes for national bank examiners names two. The as-complete value is what the property should be worth when construction ends, and the as-stabilized value is its worth once it has leased up to a normal occupancy. The owner’s own estimate comes from its development pro forma.

Loan-to-value protects the bank when the finished building would be worth too little to repay it. Loan-to-cost protects it when the owner has too little of its own money in the deal, and the OCC tells examiners that checking cost alongside value helps make sure the borrower puts in enough equity. The OCC’s examination questions add a third cap tied to the take-out commitment, the permanent lender’s promise to lend once the building reaches set rents or occupancy, by asking whether the construction loan is held to the commitment’s floor, the amount that funds even if those targets are missed. A loan held to all three limits comes out at the smallest of them.

The federal bank regulators also cap the value test. The Interagency Guidelines for Real Estate Lending Policies, which the OCC, the Federal Deposit Insurance Corporation (FDIC) and the Federal Reserve each publish, tell banks to keep their internal loan-to-value limits at or below these, measured at origination.

Loan category Supervisory loan-to-value limit
Raw land 65 percent
Land development 75 percent
Construction of commercial, multifamily and other nonresidential buildings 80 percent
Construction of one- to four-family homes 85 percent
Improved property, such as a finished apartment or commercial building 85 percent

Why the owner’s equity goes in first

The bank’s collateral is a building nobody has built, so it wants the owner’s cash spent before any loan money moves. The OCC says a bank’s policy should require equity to be contributed before construction loan disbursements begin, because letting the borrower put its share in later can significantly raise the risk that the project never gets finished. Cash, marketable securities, land bought with cash, and early costs the developer has paid, for example design fees and permit costs, count as equity. Deferred developer profit, unearned developer fees, overhead and interest on contributed land generally don’t.

Bank capital rules push the same way. A loan that regulators class as high-volatility commercial real estate (HVCRE) carries a 150 percent risk weight, so the bank must hold more capital against it. A commercial project escapes that label if, among other routes, its loan-to-value is within the supervisory limit and the borrower puts in capital worth at least 15 percent of the property’s appraised “as completed” value before the bank advances anything, then keeps it in until the loan is reclassified.

How construction loan draws work

Each month the owner sends the lender a draw request, a breakdown of that month’s costs built around the contractor’s certified bill, which the pay applications page walks through line by line. Commercial loans usually pay on a progress payment plan, and the OCC says the bank normally holds back 10 to 20 percent of each payment until the final draw to cover overruns or unpaid bills. That holdback is separate from the owner’s own retainage on its contractor. The balance, and with it the monthly interest, climbs as the building rises.

What the lender’s inspector and title updates check

The OCC says banks typically require an architect’s or engineer’s inspection report with each draw. The report says whether the work follows the plans and specifications, supports the percentage complete being billed, and says whether the job is on schedule. Monthly figures for costs to date, costs to complete and loan funds remaining then show whether the loan is in balance, with enough money left to finish the building. The OCC expects an overrun caused by poor projections or management to be paid by the borrower, and leaves the loan’s contingency line for reasonable but unexpected increases, such as a jump in material prices.

Each draw also waits on a title update, often a date-down endorsement, confirming that no mechanic’s lien has been recorded since the last one, because in some states such a lien can outrank the bank’s. The lien waivers page covers that check and the releases the bank collects before the final draw.

How the interest reserve works

An interest reserve is money set aside inside the loan to pay the loan’s own interest during construction and lease-up, usually as one line in the loan budget. The developer doesn’t write interest checks on a building that earns nothing yet, but the reserve is borrowed money and earns the bank interest like the rest. The OCC says sizing depends on possible changes in interest rates, when the money will be drawn, and how long construction and lease-up will take. Once tenants move in, rent pays the interest before the reserve does, and once rent covers it the OCC says the reserve should stop paying.

Reserves run dry when a job runs late or the market softens, and the bank then generally requires the borrower or a guarantor to put in cash. Lending more money to refill the reserve, called repacking, can keep a failing loan looking current, and the OCC calls that decision a red flag. Badly administered reserves, it adds, have been a major contributor to bank losses on construction lending.

The Walnut Street construction loan, worked through

1200 Walnut Street, the fictional six-story building the book follows, is 200 apartments over a concrete base, built for Fernwood Development under a $60 million guaranteed maximum price. All its numbers are illustrative.

Item Walnut Street How it’s figured
Total development cost $87.0 million Land, the GMP, soft costs and Fernwood’s contingency
Equity, Fernwood plus investors $37.0 million Of which the land took $7.5 million in cash
Construction loan $50.0 million At an assumed 8 percent floating rate
Loan-to-cost 57.5 percent $50.0 million ÷ $87.0 million
Value once full About $104.7 million Net operating income ÷ a 5.25 percent cap rate
Loan-to-value once full About 48 percent Well under the 80 percent supervisory limit
Interest on the full balance About $11,000 a day $4.0 million a year
Interest reserve $4.0 million One line in the $87.0 million budget

The loan closes right after the GMP is signed, but Fernwood’s equity pays the first bills, and by month 9 of a build of about 20 months every draw comes from the loan. The first temporary certificate of occupancy arrives in month 19. A year later about 178 apartments are leased, and their rent, after operating costs, more than covers the full-balance interest. A small balance early and rent paying interest late are why one year of full-balance interest can carry a loan that isn’t repaid until nearly three years after groundbreaking. The permanent loan pays it off in about month 34, once 180 apartments have been occupied for three straight months.

How a permanent loan pays off the construction loan

Bankers call the permanent loan the take-out. It can come from the construction lender, another bank or nonbank lenders such as life insurance companies, pension funds and commercial mortgage-backed securities, whose loans the OCC says usually run 10 years or more at fixed rates and are commonly nonrecourse. A permanent lender typically sizes its loan from the building’s income, and bank lending policies set a minimum debt service coverage ratio, net operating income divided by a year of loan payments.

A forward commitment, made before construction ends, promises to refinance the construction loan once the building is complete and, almost always, leased. A standby commitment is backup financing, often priced to discourage its use. The OCC warns that either may remove little of the construction lender’s risk, since both require completion and usually a lease-up to break-even, so the lender should analyze what happens if the take-out never funds. Without one, a bridge loan, usually written for up to three years, can carry a new building through lease-up until it qualifies for permanent financing.

How a home construction loan differs

The Consumer Financial Protection Bureau (CFPB) describes two kinds. A construction-only loan is usually short-term, pays out in several disbursements, and has the borrower pay only accrued interest until the house is finished, when separate permanent financing takes it out. A construction-to-permanent loan converts at completion into a loan that amortizes like a standard mortgage. Fannie Mae, which buys mortgages from lenders, calls these two-closing and single-closing transactions, and buys a single-closing loan only after it converts. Its construction period can’t run past 12 months at a stretch or 18 in total, with no exceptions, so a slow build has to be handled as a two-closing loan.

Building project, such as apartments Home construction loan
Interest during construction Often paid from an interest reserve Usually paid monthly by the borrower, interest only
How draws are released Monthly progress payments, less a holdback Most commonly five equal installments at set stages that an inspection confirms, the OCC says
HVCRE capital rule Applies unless the value and equity tests are met Exempt
Federal consumer disclosures Regulation Z exempts credit primarily for a business purpose Loan Estimate and Closing Disclosure rules can apply

What newcomers get wrong about construction loans

  1. Treating the commitment as cash on hand. A $50 million loan pays out only as inspected work goes in, and only after the owner’s equity is spent.
  2. Assuming the construction lender keeps the loan. Its plan from the first day is to be repaid by a permanent loan, which is why the OCC has it collect monthly rent rolls during lease-up.