A differing site condition is a physical condition at the site, usually underground or hidden inside an existing building, that turns out materially different from what the contract documents indicated (a Type I condition) or from what is ordinarily found in that kind of work (a Type II condition). When the contract has a differing site conditions clause, such as the federal one at FAR 52.236-2 or section 3.7.4 of the AIA’s A201 general conditions, the contractor can get more money, more time or both, provided it gives written notice promptly and before the condition is disturbed. A condition the documents specifically warned about usually doesn’t qualify, so every claim starts with what the geotechnical report and the drawings said.
What a differing site conditions clause does
Nobody knows the ground under a site except where someone drilled a test hole and logged the soil it brought up, a record called a boring log. A contractor bidding a fixed price has to guess about everything between those holes. Assume firm soil and a soft pocket eats the profit. Price for the worst case and a competitor wins the job.
The clause takes part of that guess off the bidders. The owner agrees to pay when the ground proves materially worse than the documents showed, so bidders can price the site as described. A 2026 article published by ConsensusDocs, a publisher of standard construction contracts, traces the reasoning to a 1970 decision of the federal Court of Claims, which said the clause exists to “take at least some of the gamble on subsurface conditions out of bidding.” A contract that strikes the clause, or calls the boring reports “information only,” leaves the risk of what lies below with the contractor, the article warns.
The adjustment runs both ways. FAR 52.236-2 changes the contract for an increase or a decrease in cost or time, so ground easier than shown can lower the price. Federal agencies must use the clause in fixed-price construction contracts above the simplified acquisition threshold (FAR 36.502), and federal-aid highway projects carry a standard version under 23 CFR 635.109. On private work the clause comes with whatever standard form the owner picks, and the owner can edit it or strike it.
Type 1 and Type 2 differing site conditions
The two types come from the two numbered paragraphs of FAR 52.236-2(a), and A201, the federal highway clause and California’s statute use the same split.
| Type I | Type II | |
|---|---|---|
| Measured against | What the contract indicated, such as boring logs, drawings and specifications | What is ordinarily found in work of that kind |
| What the contractor has to prove in federal cases | The contract affirmatively indicated a condition, the contractor read and relied on it as a reasonably prudent contractor would, the actual condition differed materially and was reasonably unforeseeable, and the extra cost came solely from it | The condition was unknown, unusual and materially different from what comparable work meets |
| Illustrative case | Rock where the boring logs show clay | A buried structure that no record or surface sign hinted at |
| The hard part | Showing the documents said something definite | Proving what normal looks like before showing the departure |
The Type I list is the set of “six indispensable elements” the Court of Federal Claims repeated in Weston/Bean Joint Venture v. United States (2014), judged from what the documents told a bidder.
A Federal Circuit case from December 2023 shows how a warning in the documents sinks both types. Nova Group/Tutor-Saliba designed the piles for a Navy aircraft carrier pier in Bremerton, Washington, from the geotechnical report in the solicitation, and when they drove hard, its request for more than $10 million failed. The Court of Federal Claims found that the documents had disclosed unpredictable ground and possible obstructions and said hard driving was to be expected, which defeated Type I, and that the contractor hadn’t shown the causes were unknown or unusual in the region, which defeated Type II. The Federal Circuit affirmed.
Concealed or unknown conditions in AIA A201
A201-2017 covers the subject in section 3.7.4, Concealed or Unknown Conditions, with the same two categories. Its phrase “subsurface or otherwise concealed” reaches conditions hidden in an existing building as well as in the ground. After the contractor’s notice, due within the deadlines in the table below, the architect investigates. If it finds a material difference that changes the contractor’s cost or time, it recommends an equitable adjustment to the contract sum, the contract time or both. On a job with a guaranteed maximum price that usually means a change order raising the GMP, paid from the owner’s contingency, as the contingency vs allowance page explains. If it finds none, it says why, and either party can take the question to a claim under Article 15.
Two neighboring clauses stop the affected work. Under section 3.7.5, unexpected human remains, burial markers, archaeological sites or wetlands halt any operation that would affect them until the owner gets government approval to resume. Under section 10.3, an unaddressed hazardous material such as asbestos stops work in that area if reasonable precautions can’t keep people safe, and the owner hires a licensed laboratory to test it.
Notice deadlines for differing site conditions
| Clause | Applies to | Tell whom | Deadline | What else to know |
|---|---|---|---|---|
| FAR 52.236-2 | Federal fixed-price construction | The contracting officer, in writing | Promptly, before the conditions are disturbed | No adjustment without the notice, though the contracting officer may extend the time. No request after final payment |
| AIA A201-2017, section 3.7.4 | Jobs on AIA contracts | Owner and architect | Promptly, before the conditions are disturbed, and within 14 days of first observing them | A dispute over the architect’s answer becomes a claim, which must start within 21 days (section 15.1.3.1) |
| 23 CFR 635.109 | Federal-aid highway projects | Whichever party finds the condition tells the other, in writing | Before the site is disturbed and before the affected work is done | No contractor gain without written notice, and adjustments exclude anticipated profit |
| California Public Contract Code 7104 | Local public works with trenches or excavations deeper than 4 feet | The public agency, in writing | Promptly, before the conditions are disturbed | Measures against site information made available to bidders, covers possible hazardous waste, and keeps the contractor working through a dispute |
A201 treats a claim notice as served only when it goes by certified mail, registered mail or a courier that proves delivery (section 1.6.2), and a claim for more money needs that notice before the contractor goes ahead with the disputed work (section 15.1.5). Federal courts have sometimes excused missing written notice when the government already knew and wasn’t harmed, the Weston/Bean decision notes, but counting on that turns a change order into a lawsuit. Days added under the clause also move the date liquidated damages begin.
What the geotechnical report decides
The owner normally hires the geotechnical engineer. The AIA’s owner-architect agreement, B101-2017, puts test borings, test pits and soil bearing values on the owner’s side (section 5.5), and where the International Building Code calls for an investigation, the report goes in with the permit application (section 1803.6). The site due diligence page covers what the report contains and how it gets ordered.
For a Type I claim the report is the yardstick, but only if it belongs to the contract. A201 section 1.1.1 leaves out of the contract documents any information the owner handed out in anticipation of bids unless the owner-contractor agreement lists it, so a soils report given to bidders and never listed sits outside what section 3.7.4 measures against. On federal jobs, FAR 52.236-3 has the contractor acknowledge it checked the site and the government’s exploratory data, and the government disclaims the contractor’s own conclusions from that data. The Nova court added that a design-build contract doesn’t shift the risk of errors in the government’s representations onto the contractor.
Some public owners split the report in two. The Washington State Department of Transportation’s geotechnical manual (December 2020) gives design-build bidders a factual data report and a geotechnical baseline report with the agency’s interpretation of the ground, both contract documents, and uses the baseline report after award to judge differing site conditions claims.
A worked example at 1200 Walnut Street
At 1200 Walnut Street, the fictional six-story building the book follows, the garage sits at street level, so the dig is shallow. In month 2 the excavator opens a pocket of loose fill under one corner. All Walnut Street figures are illustrative.
| Test | What the record shows | Result |
|---|---|---|
| Type I, the contract showed something different | The soils report warned that pockets of loose fill might sit under the lot, without saying where | Not met. The find matches the warning |
| Type II, the condition was unknown and unusual | The same warning made it a known possibility | Not met |
| Who pays | Victor Price, the contractor’s chief estimator, priced loose fill as a risk when he built the GMP | The contractor’s contingency, with no change order |
| The fix | The fill comes out and goes back in compacted layers, each one tested by a special inspector the owner hires, as the building code requires | That corner loses two weeks |
The building inspections page follows those density tests. Under a report that showed firm native soil at that corner and never mentioned fill, the same pocket would point to a Type I condition, with written notice due to Fernwood Development and to Rosa Archer, the project architect, before the excavator dug any further and within 14 days in any case.
What to do when the dig finds something
- Stop work in the affected area, since notice has to come before the condition is disturbed, and keep working elsewhere, as A201 section 15.1.4 requires while a claim is open. Clear the area first if the find could be hazardous material or human remains.
- Record it before anything moves, with photos that show scale, measurements, a mark on the drawings, and the date, time and witnesses.
- Pull the nearest boring logs, the report’s description of that area and the drawings, and check whether the agreement lists the report as a contract document.
- Send written notice the way the contract requires, saying what was found, where and how it differs, and keep proof of delivery.
- Leave the condition open for the owner’s side to inspect, and bring in the geotechnical engineer and the special inspector, whose records become evidence.
- Get written direction, a change order or a construction change directive, before doing extra work, as the RFIs, submittals and change orders page describes.
- Track the affected work’s labor, equipment, trucking, testing, material and schedule effect separately from day one.
- If the answer is no, file the claim on time, within 21 days under A201 and before final payment on a federal job.
Sources
- FAR 52.236-2, Differing Site Conditions, Acquisition.gov, accessed November 26, 2026
- FAR 52.236-3, Site Investigation and Conditions Affecting the Work, Acquisition.gov, accessed November 26, 2026
- FAR 36.502, Differing site conditions, Acquisition.gov, accessed November 26, 2026
- 23 CFR 635.109, Standardized changed condition clauses, Legal Information Institute, Cornell Law School, accessed November 26, 2026
- California Public Contract Code 7104, statute text via California Public Law, accessed November 26, 2026
- AIA Document A201-2017, General Conditions of the Contract for Construction, blank copy posted with bid documents, City of Rochester, New Hampshire, accessed November 26, 2026
- AIA Document B101-2017, Standard Form of Agreement Between Owner and Architect, copy issued with a design-team request for proposals, ASHRAE, accessed November 26, 2026
- He Chose…Poorly: How Bad DSC Clauses Lead to Project Doom, Curt Martin and Lee Banta, Peckar & Abramson, ConsensusDocs, February 16, 2026, accessed November 26, 2026
- Weston/Bean Joint Venture v. United States, No. 11-31C, US Court of Federal Claims, March 14, 2014, GovInfo, accessed November 26, 2026
- Nova Group/Tutor-Saliba v. United States, No. 22-1740, US Court of Appeals for the Federal Circuit, December 11, 2023, accessed November 26, 2026
- Chapter 18 Soils and Foundations, 2024 International Building Code as adopted in the GSA Building Code 2024, UpCodes, accessed November 26, 2026
- Chapter 17 Special Inspections and Tests, 2024 International Building Code as adopted in the GSA Building Code 2024, UpCodes, accessed November 26, 2026
- Geotechnical Design Manual M 46-03.13, Chapter 22, Geotechnical Project Development, Reports, and Support for Design-Build Projects, Washington State Department of Transportation, December 2020, accessed November 26, 2026