Liquidated damages in construction

Updated
Written by
Alexander J. Hale
Reading time
10 min
Sheet
26 of 44

Liquidated damages, or LDs, are a daily dollar amount written into a construction contract that the contractor owes the owner for every day the job finishes late for a reason the contract doesn’t excuse. The parties fix the rate at signing as a reasonable estimate of the owner’s future losses, so nobody has to prove those losses later, and courts enforce it unless it works as a penalty. The clock usually starts the day after the contract completion date, moves when the contractor earns a time extension, and stops at substantial completion.

What liquidated damages are, and why contracts use them

A late building costs its owner real money that is hard to prove. Interest keeps running on the construction loan, tenants who would have moved in sign leases elsewhere, and the owner’s staff stay on the job longer. Proving each loss in court means expert witnesses and an argument about what would have happened in a world where the building opened on time. The US Supreme Court said in 1947 that LD clauses are especially useful where damages are uncertain or can’t be measured.

Both sides get something from the bargain. The owner gets a number it can collect without a trial over lost rent. The contractor gets a known price for lateness that it can weigh when it plans the schedule and prices the job, and in some states the agreed rate is the owner’s only remedy for that delay, even when the real loss runs higher.

A contract has LDs only if the parties write them in. A133, the AIA’s standard agreement for a construction manager at risk working to a guaranteed maximum price, leaves a blank for liquidated damages “if any.” A201, the general conditions that go with it, lets the owner impose LDs without filing a formal claim, and lets the architect hold back payment when the unpaid balance won’t cover the LDs a late finish is heading toward.

How a daily rate is set

The rate starts as arithmetic. The owner adds up what a late day will cost it, and a 2023 ConsensusDocs article by a Peckar & Abramson construction lawyer names the entries to consider, from financing past the planned finish and added management and overhead to LDs the owner itself owes someone else and planned uses of the building that will have to wait. Federal agencies follow FAR 11.502, which builds the daily rate on the government’s cost of inspection and superintendence for each day of delay, plus costs such as renting substitute property.

Some public owners publish a schedule. Louisiana’s Office of Facility Planning and Control, in a June 2026 guide its managers may adjust, starts at $2,000 a day for jobs with $10 million to $12 million of construction funds and leaves the rate to be determined above $15 million.

No standard liquidated damages percentage

The rate is a dollar figure per day, built from the owner’s own costs. Louisiana’s $2,000 works out to 0.02 percent of a $10 million budget for each late day, but that percentage is only a result of the schedule, which lists dollar amounts. Percentages do show up in caps, covered below.

The enforceability test for liquidated damages

Courts ask whether the clause compensates or punishes. In Priebe & Sons v. United States (1947), the Supreme Court said courts enforce LD clauses that are fair and reasonable attempts to fix just compensation for an expected loss, and it refused to enforce the one before it because the amount could not possibly be a reasonable forecast of that compensation. The test looks at the situation on the day the contract was signed, so an owner whose loss turns out smaller can still collect. State law varies, and the differences decide cases.

Jurisdiction When the rate is judged What sinks the clause
Federal contracts At signing (Priebe, 1947) A rate that could not be a reasonable forecast of just compensation
California, non-consumer contracts At signing (Civil Code 1671) The challenger proving the rate was unreasonable in the circumstances at the time
Texas At signing (Phillips v. Phillips, 1991), and again at the breach (Atrium Medical Center, 2020) Harm that was easy to estimate or a rate that wasn’t a reasonable forecast, which the party seeking LDs must rule out, or an “unbridgeable discrepancy” with the actual loss, which the breaching party has to prove

The Texas third step has teeth. In FPL Energy v. TXU Portfolio Management (2014), a power-contract case, the state’s Supreme Court refused to enforce about $29 million of LDs against about $6 million of actual damages. Because every test starts from the forecast, the owner’s best evidence is the worksheet its daily rate was built from.

Liquidated damages vs actual damages

Question Liquidated damages Actual damages
Amount The daily rate times the late days, up to any cap Whatever the owner can prove
What the owner proves The contractor finished late with no excuse Each loss, and that the delay caused it
Lost rent and loan interest on an A201 job Collectible through the agreed rate Waived as consequential damages
Main risk A court calls the rate a penalty Proving every dollar, while the waiver bars the largest items

When liquidated damages start and stop

The clock starts the day after the contract completion date, meaning the original date plus every time extension granted. AIA contracts measure the contract time to substantial completion, so on those jobs the clock usually stops there. That is the stage when the work is finished enough, by the contract’s own standard, that the owner can move in or put it to the use it was built for, and the architect certifies the date. A remaining punch list doesn’t keep the clock running. Some states may refuse LDs for days after the owner could already use the building, and the federal clause runs until the work is completed or accepted.

Where an owner takes a building in stages, the contract can set a date and a rate for each part. A201 lets a designated portion reach substantial completion on its own, and FAR 11.503 requires a separate LD amount for each part or stage that has its own completion date.

Excusable delays and time extensions

A time extension is the contractor’s main defense against LDs, because it moves the date the clock starts from. A201 section 8.3.1 extends the contract time, by as much as the architect finds reasonable, for delays caused by the owner or architect, changes in the work, labor disputes, fire, unusual delays in deliveries, unavoidable casualties, documented adverse weather and other causes beyond the contractor’s control. A weather claim needs records proving conditions were abnormal for that time of year, beyond what the contractor could reasonably have planned for, and damaging to the work on the schedule. A claim for more time must be started within 21 days of the event, or of the day the contractor first recognizes the problem, whichever is later.

Federal jobs run on similar terms. The default clause, FAR 52.249-10, excuses delays from unforeseeable causes beyond the contractor’s control, such as acts of the government, fires, floods, epidemics, strikes and unusually severe weather, if the contractor gives written notice within 10 days of the delay’s start. On federal jobs with separate completion dates for parts of the work, FAR 52.211-13 ties extensions for changes to how far the changes actually delay completion, which is the question a critical path schedule answers. Some delays bring money as well as days. FAR 52.242-14 pays the contractor the added cost, without profit, of an unreasonable delay the contracting officer caused.

Caps and the waiver of consequential damages

A201 section 15.1.7 has the owner and contractor each give up claims for consequential damages, the indirect losses that flow from a breach. On the owner’s side that covers rental expenses and lost use, income and financing, among others. On the contractor’s side it covers the cost of running its main office and any profit other than what the work itself was expected to earn. The section’s last sentence keeps liquidated damages alive. On an A201 job with that waiver left in place, the LD rate is the owner’s one route to recovering interest and lost rent caused by a contractor’s delay.

Caps limit the total. AIA Contract Documents recommends including one where possible, and construction lawyers writing for ConsensusDocs describe caps set as a fixed sum or as a percentage of the contract price or of the contractor’s fee. FAR 11.501 tells contracting officers to use a maximum amount or period when that limit reflects the government’s maximum probable damage.

Federal practice: FAR 11.501 and 52.211-12

FAR 11.501 allows LDs only where timely performance is important enough that the government can expect to be harmed by lateness, and where the harm would be hard to estimate or prove. It says LDs aren’t punitive or a negative incentive, and it tells contracting officers to take reasonable steps to mitigate them. The construction clause, FAR 52.211-12 (September 2000), has a blank for the daily amount the contractor pays for each calendar day of delay until the work is completed or accepted. If the government terminates the contractor for default, LDs keep running until the work is finished, on top of the extra cost of hiring someone else to finish it. FAR 11.503 calls for the clause in construction contracts other than cost-plus-fixed-fee whenever the contracting officer decides LDs are appropriate.

The price of one late day at Walnut Street

At 1200 Walnut Street, the fictional six-story building the book follows, each late day in the last months of construction draws on both parties’ money. All figures are illustrative.

One late day near the end Fernwood, the owner The contractor
Interest on the $50 million construction loan, at an assumed 8 percent About $11,000
Rent not collected, 200 apartments and two shops, if all were leased Up to about $25,800
General conditions (site staff, trailer, equipment), 6 to 12 percent of the $60 million GMP over about 600 days About $6,000 to $12,000
Each side’s cost About $11,000 to $37,000 About $6,000 to $12,000

Together, one late day costs the two parties about $17,000 to $49,000. Fernwood’s interest is certain the moment a day slips, but its rent isn’t, since only about 80 of the 200 apartments are leased three months after the first move-ins. Fernwood’s contract has an LD clause, but the book never states its rate. Suppose, for this page only, the rate were the interest alone, $11,000 a day, and a design-caused delay earned the contractor its extra general conditions, as it usually does.

Ten days late because of Time extension Fernwood’s net cost Contractor’s net cost
The contractor’s own slip None $0 to $260,000, after $110,000 of LDs $170,000 to $230,000, including the LDs
Documented abnormal weather 10 days $110,000 to $370,000 $60,000 to $120,000
A design error 10 days $170,000 to $490,000, with the contractor’s extra general conditions About $0 once those are paid

Sources