Construction schedules and the critical path
- Updated
- Written by
- Alexander J. Hale
- Reading time
- 11 min
- Sheet
- 40 of 44
A construction schedule lists every activity it takes to finish a building, how long each one lasts and which ones must finish before others can start. The critical path method (CPM) runs through those links to find the critical path, the longest chain of dependent activities, which sets the earliest possible finish date, so any slip on that chain pushes the finish back by the same number of days. Every activity off it has float, a number of days it can slip before the finish moves.
How a construction schedule is built
A scheduler first breaks the job into activities, each small enough for one crew in one area with a clear finish, such as “set steel, east half” or “inspect level 3 rough-in.” Submittals, design review, fabrication, delivery, permits and inspections get their own lines too, because any of them can stop a crew.
Each activity then gets a duration in working days, usually a quantity from the estimate divided by what one crew installs in a day. Last comes the logic. Most links are finish-to-start, so the slab waits for the underground pipe, and some are start-to-start with a lag, so drywall can follow framing up the building a few floors behind. The schedule guide from the US Government Accountability Office (GAO) expects every activity except the first and last to have at least one predecessor and one successor, since a loose end lets the software report a critical path, and a finish date, that the work won’t follow.
AIA Document A201-2017, the general conditions behind many US private projects, makes the contractor submit a construction schedule promptly after award and revise it at appropriate intervals, without naming a method. Owners who want CPM require it in Division 01, the opening division of the specifications that sets project-wide rules, as the Defense Department’s guide specifications do for military work. One trap for newcomers is that A201 counts calendar days unless the contract says otherwise, while many schedules count working days.
The critical path method, worked through
Take the shell of a small one-story steel-framed shop building, with illustrative numbers.
| ID | Activity | Duration (working days) | Can start after |
|---|---|---|---|
| A | Steel shop drawings, prepared and approved | 15 | Notice to proceed |
| B | Fabricate and deliver steel | 25 | A |
| C | Footings and foundations | 12 | Notice to proceed |
| D | Underground plumbing and electrical | 6 | C |
| E | Slab on grade | 4 | D |
| F | Erect steel and roof deck | 10 | B and E |
| G | Roofing | 8 | F |
| H | Exterior walls and storefront | 12 | F |
The forward pass runs from the start. Each activity’s early start is the latest early finish among its predecessors. Erecting steel needs the delivered steel (day 40) and the slab (day 22), so it starts on day 40, and the job ends when H finishes on day 62. The backward pass runs back from day 62, and each late finish is the earliest late start among the activity’s successors. Total float is late start minus early start. Free float is how far an activity can slip before it delays the early start of the next one.
| ID | Duration | Early start | Early finish | Late start | Late finish | Total float | Free float | Critical |
|---|---|---|---|---|---|---|---|---|
| A | 15 | 0 | 15 | 0 | 15 | 0 | 0 | Yes |
| B | 25 | 15 | 40 | 15 | 40 | 0 | 0 | Yes |
| C | 12 | 0 | 12 | 18 | 30 | 18 | 0 | No |
| D | 6 | 12 | 18 | 30 | 36 | 18 | 0 | No |
| E | 4 | 18 | 22 | 36 | 40 | 18 | 18 | No |
| F | 10 | 40 | 50 | 40 | 50 | 0 | 0 | Yes |
| G | 8 | 50 | 58 | 54 | 62 | 4 | 4 | No |
| H | 12 | 50 | 62 | 50 | 62 | 0 | 0 | Yes |
The dates count working days already completed, so an early start of 15 means work begins on day 16.
The critical path is A, B, F and H, which add up to 62 days. Everything a passerby would watch, from the digging to the slab, has 18 days to spare. The finish is set by a detailer’s desk, the design team’s review and a steel shop.
- If the footings run 10 days late, the finish holds, but that chain has only 8 days of float left, because the footings, underground work and slab draw on one pool.
- If the slab runs 20 days late, 2 days past its float, the finish moves to day 64 and the critical path shifts to the footings, underground work and slab.
- If the steel shop drawings come back revise and resubmit and cost 5 days, the finish moves to day 67.
- If roofing runs 5 days late, against 4 days of float, the finish moves 1 day.
Total float vs free float
The GAO guide defines total float as the time an activity can slip without moving the finish, and free float as the part of it available before the slip reaches the next activity. An activity can have plenty of the first and none of the second. In the example, the footings, underground work and slab share the same 18 days, and only the slab has free float, so a crew that spends float early spends it for everyone after it. When the projected finish passes the contract date, float goes negative, and GAO counts any activity at zero or below as critical.
Who owns float
Contracts vary, and A201 says nothing about float. A Stoel Rives article sets out three positions. The contractor may own the float and use it to soak up its own delays, as early court decisions generally held. The owner may claim it with a clause that gives no extension for float used up. A float-sharing clause gives it to the project, for whoever needs it first. On military work, the Army Corps of Engineers’ schedule specification takes the shared view and says float belongs to the project, open to the contractor and the government alike. Where a contract is silent, the same article says courts and boards now generally treat float as the project’s, first come, first served. Float can also be hidden. The Corps specification bans artificial constraints such as “zero free float”, and a Navy-prepared one bans techniques that artificially adjust durations to use it up.
Baseline schedule vs schedule updates
The baseline is the approved plan, the target the GAO guide says progress is measured and reported against. The Navy-prepared guide specification for military projects wants it within 30 calendar days of award, with no progress recorded, and construction can’t start until it is accepted. After that the schedule is updated, monthly at minimum in the Army Corps of Engineers’ project schedule specification, with actual start and finish dates, remaining durations and percent complete as of a data date, the line between work done and work remaining.
Each update, laid against the baseline, shows what slipped and how much float is left. Changing the baseline itself is a formal step under change control, and the Corps specification prohibits making progress look better by editing logic, constraints, durations or calendars.
Three-week look-ahead schedules
A look-ahead schedule pulls the next few weeks out of the master schedule and adds the detail, crew by crew and floor by floor, along with every condition a crew is waiting on, such as delivered material, an approved submittal, an answered request for information (RFI) or a passed inspection.
Three weeks is a common window in owners’ specifications. Colorado Springs Utilities wants a weekly report of last week’s completed work and the next three weeks, using the logic and activity numbers of the current progress schedule. Chicago Public Schools asks for a three-week look-ahead at every progress meeting. The Lean Construction Institute’s Last Planner System typically looks five to six weeks out, screening each activity for anything that would stop it and clearing the problem before the crew shows up. On site the look-ahead belongs to the superintendent, who often builds it with the foremen by planning backward from the next milestone.
Long-lead items
A long-lead item is anything built to order that takes months to arrive, such as switchgear, transformers, generators, elevators, rooftop mechanical units and curtain wall. Each one is a chain of activities, from preparing the submittal through review, fabrication and shipping, and that chain can be the critical path, as the steel was in the worked example. A Wood Mackenzie analysis of equipment for US utility transmission and distribution grids, not building projects, put average switchgear lead times at 44 weeks in the second quarter of 2025.
A201 bars work on anything that needs a submittal until it is approved, so review time sits inside the lead time. Long-lead submittals go first for that reason, and a slow shop drawing review on switchgear costs more than the same delay on a package with weeks of float.
Construction scheduling software
Primavera P6 is the government’s own tool on military work, where the Corps schedule specification names it and asks contractors using it for XER export files. Microsoft Project calculates the critical path and by default shows the single path that drives the finish. Asta Powerproject, from Elecosoft, is sold as construction planning software with critical path analysis. Look-aheads often live on a trailer whiteboard, a wall of sticky notes or a pull-planning app. Every one of these calculates only the logic it’s given, and a missing link produces a wrong critical path that looks entirely official.
How schedule delays lead to time extensions
A201 section 8.3.1 extends the contract time by a reasonable period, as the architect determines, when the contractor is delayed by the owner, the architect or a separate contractor, by changes, by labor disputes, fire, unusual delivery delays or unavoidable casualties, by documented adverse weather, or by other causes beyond its control. The contractor has to claim it, with written notice within 21 days of the event or of first recognizing it, whichever is later, and an estimate of the cost and of the delay’s probable effect on progress. For weather it needs data showing conditions were abnormal for the period and unforeseeable, and that they set back work the schedule had planned.
The schedule is the evidence. The Corps specification grants no extension unless the delay uses up all available float and pushes the projected finish past the contract completion date, shown by a time impact analysis on the last approved schedule. Under that rule, with a contract finish of day 62, an owner’s change that holds up the example’s slab for 20 days earns 2 days, because the other 18 were float. Delays the contractor causes earn none.
Time and money are separate questions. An extension moves the date from which liquidated damages, a set amount owed for each day of late finish, start to run. Payment for the extra days depends on who caused them and on the contract. A201 leaves delay damages to its other provisions, and it has owner and contractor waive consequential damages, including the owner’s lost income and financing costs.
The schedule at 1200 Walnut Street
1200 Walnut Street, the fictional six-story building the book follows, takes about 20 months to build, close to the Census Bureau’s 2025 average of 19.1 months for buildings with 20 or more apartments. The contractor keeps the schedule in Primavera P6. All Walnut Street numbers are illustrative.
| Construction month | On the schedule |
|---|---|
| 2 | Excavation hits loose fill beneath part of the garage. The crew recompacts it in thin lifts, each one tested, and that area loses two weeks |
| 6 to 11 | Framing the five wood floors |
| 9 | After a 12-day review, the roof truss package is returned marked revise and resubmit. The approved version then goes to the city as a deferred submittal |
| 11 | Topping out, when the final roof truss is set |
| 19 | First temporary certificate of occupancy (TCO), for the podium plus levels 2 to 4. Levels 5 and 6 still have painters on them |
| About three weeks later | The second TCO |
Of all the equipment on order, the switchgear worried the team most. Until it is set and energized, nothing that depends on the permanent electrical service, from the elevators to the heating and the fire alarm, can be tested on it, and the fire alarm’s acceptance test must be passed before the first temporary certificate of occupancy in month 19. At that stage, every day of delay runs roughly $17,000 to $49,000, and the contract decides how much of it lands on Fernwood Development, the owner, and how much on the contractor.
Sources
- AIA Document A201-2017, General Conditions of the Contract for Construction, blank copy posted with bid documents, City of Rochester, New Hampshire, accessed November 26, 2026
- Schedule Assessment Guide: Best Practices for Project Schedules, GAO-16-89G, US Government Accountability Office, December 2015, accessed November 26, 2026
- UFGS 01 32 01.00 10, Project Schedule, USACE, NAVFAC and AFCEC, August 2026, via the Whole Building Design Guide, accessed November 26, 2026
- UFGS 01 32 17.00 20, Cost-Loaded Network Analysis Schedules, USACE, NAVFAC and AFCEC, May 2025, via the Whole Building Design Guide, accessed November 26, 2026
- Who Owns the Project’s Float, and What Should Be Done About It, Stoel Rives LLP, October 15, 2021, accessed November 26, 2026
- Section 01 32 16, Schedule Requirements, Colorado Springs Utilities, accessed November 26, 2026
- Section 01 31 00, Project Management and Coordination, Chicago Public Schools Infrastructure Handbook, accessed November 26, 2026
- Last Planner System Workbook, Lean Construction Institute, 2007, accessed November 26, 2026
- Mind the gap: tackling supply-chain challenges in the electric T&D sector, Wood Mackenzie, October 15, 2025, accessed November 26, 2026
- Show the critical path of your project in Project, Microsoft Support, accessed November 26, 2026
- Powerproject, Elecosoft, accessed November 26, 2026
- Average Length of Time from Start to Completion of New Privately Owned Residential Buildings, Survey of Construction, US Census Bureau, accessed November 26, 2026