Shop drawings

Updated
Written by
Alexander J. Hale
Reading time
12 min
Sheet
32 of 44

Shop drawings are drawings that a fabricator, supplier or subcontractor prepares for one project to show exactly how it will make and install its part of the building, down to every bolt hole in a steel beam or every member of a roof truss. The general contractor checks each package first and passes it to the architect and engineers, and fabrication waits for their answer. They are one kind of submittal, and they never replace the design drawings and specifications, which still say what the contract requires.

What are shop drawings in construction

The design team’s drawings describe the finished building and then stop. A structural plan can show a steel beam and the force its end connections must carry without placing a single hole, because that depends on how one particular shop cuts and drills its steel. The fabricator fills the gap with its own drawings, detailed enough for its shop floor and its erection crew to build from.

AIA Document A201-2017, the general conditions many US private projects start from, defines shop drawings in section 3.12.1 as drawings, diagrams, schedules and other data made specially for the job by the contractor or anyone below it, down to a manufacturer or distributor. The Defense Department’s guide specification for structural steel, which governs that one owner’s projects, adds that fabrication drawings must not be reproductions of the contract drawings.

A steel fabricator often hires an outside detailer, while a truss plant runs each truss through its own design software. Each package goes through the subcontractor to the general contractor, whose project engineer or assistant project manager reviews and stamps it first. The split has a reason. The designers know what the building must do. The fabricator knows its machines and the connections its crews bolt up fastest, and those choices drive much of its price.

Shop drawings vs construction drawings, product data and samples

A201 sorts submittals into three kinds. All three differ from the design drawings in who makes them and what they can change.

Document Who prepares it What it shows Part of the contract? Example
Construction drawings Architect and engineers The finished building, with sizes, locations, materials and performance Yes A framing plan giving a beam’s size and end loads
Shop drawings Fabricator, supplier or subcontractor How one part will be made and installed, piece by piece, for this project only No A steel sheet showing every hole, cope and weld on one beam
Product data Manufacturer, through the contractor A standard product, shown in brochures, standard schedules, performance charts and instructions No A rooftop unit’s cut sheet with its weight and electrical load
Samples Supplier or installer A physical example of a material or finish, kept as the yardstick for the installed work No A brick and mortar panel

Shop drawings vs submittals

Every shop drawing is a submittal, but submittals also include calculations, test reports, certificates and closeout manuals. A201 section 3.12.4 says none of them are contract documents. Their job is to show the builder’s plan for meeting the design, and approving one leaves the contract’s requirements exactly where they were. The general process, with the review actions, review clocks and a sample log, is on the page about RFIs, submittals and change orders.

Which trades produce shop drawings

Nearly any package built to order produces them. These are the ones a newcomer meets most often.

Trade What its shop drawings show Who seals them or sets the rules
Structural steel Each member’s size, holes, welds and cuts, plus erection drawings placing every piece AISC 303, the American Institute of Steel Construction’s Code of Standard Practice. Where connection design is delegated, the Defense Department’s guide specification has a registered engineer seal the calculations
Precast concrete Erection drawings with connections, and production drawings with each piece’s reinforcing and lifting inserts The Department of Veterans Affairs guide specification, written for its own projects, has a professional structural engineer seal the erection drawings
Wood trusses A design drawing for every truss and a placement diagram The International Building Code (IBC) has the building official approve the truss drawings before installation
Curtain wall Elevations, anchors, joints, glass, and wind and seismic calculations Often delegated. The Defense Department’s guide specification has a registered engineer prepare and sign the structural calculations
Ductwork Scaled plans with duct sizes, bottom elevations, fittings and fire dampers, coordinated with other trades SMACNA’s HVAC Duct Construction Standards, from the sheet metal contractors’ association. The University of Houston’s master specification, for one, requires them
Fire sprinklers Working plans with every head and pipe size, plus hydraulic calculations NFPA 13, the National Fire Protection Association’s sprinkler standard. The Defense Department’s guide specification requires a designer certified by NICET at Level III or IV
Millwork Dimensioned elevations, profiles, species, finish, blocking and cutouts Quality standards from the Architectural Woodwork Institute (AWI). Yale University’s design standards, for one, require an AWI-certified shop

Reinforcing steel, elevators, stairs and railings, and storefront usually produce them too.

Delegated design and deferred submittals

Under delegated design, the engineer of record decides what a piece must carry and how it must perform. An engineer on the fabricator’s side then works out the piece itself and puts a professional seal on those drawings and calculations. A201 section 3.12.10 says the contractor owes design work only where the contract documents specifically ask for it, or where its own means and methods need it, as with temporary shoring. When they do, the owner and architect must state every performance and design criterion, and the builder is entitled to treat that information as correct. The builder’s engineer seals everything it designs, and the owner and architect may rely on that work as long as they supplied the criteria. B101-2017, the owner’s agreement with the architect, adds in section 3.6.4.3 that the architect isn’t responsible for the delegated engineer’s work. A piece the contract never delegates stays with the design team, however much detail the fabricator adds.

A permit is often issued before those packages exist, since a truss plant can’t design trusses until it has an order. The IBC covers that gap with deferred submittals. Section 107.3.4.1, in the 2021 and 2024 editions, works in four steps.

  1. The building official approves the deferral in advance.
  2. The registered design professional in responsible charge lists the deferred items on the construction documents.
  3. The finished packages go to that design professional, who reviews them and forwards them to the building official with a note that they conform generally to the building’s design.
  4. Nothing deferred is installed until the building official approves it.

The 2009 IBC numbered this 107.3.4.2, so older sets may cite that. Local lists vary. Portland’s covers trusses, manufactured guardrails and special stairs, and Maricopa County’s adds fire alarm and sprinkler systems. Each deferred package faces the design team’s review and then the city’s, and the submittal schedule needs room for both.

How shop drawings are reviewed and stamped

The package moves from the fabricator to the subcontractor and on to the general contractor, which stamps it and sends it to the architect. The architect logs it and passes it to the consultant responsible for that discipline. The reviewer’s action returns by the same chain, and a deferred package then goes on to the city. Under A201 section 3.12.7, work that needs a submittal waits for approval, and the Defense Department’s steel specification, for one, holds fabrication until then too.

Stamp or seal Who applies it What it says What it doesn’t say
Delegated engineer’s seal The fabricator’s licensed engineer This engineer designed the piece and answers for it professionally That it fits the rest of the building
Contractor’s review stamp The general contractor The package was reviewed and approved, field measurements were or will be verified, and it was coordinated with the work (A201 section 3.12.6) That the design team agrees
Design team’s action stamp The architect or consultant engineer Whether the package conforms with the information given and the design concept in the contract documents That dimensions, quantities or erection methods are right
General conformance note The design professional in responsible charge, on deferred items The package fits the building’s design That the city agrees
Building official’s approval The city’s plan reviewer The deferred package meets the code and may be installed Anything about the contract

Two more A201 rules decide who pays when a stamped drawing is wrong. Under section 3.12.8, approval doesn’t excuse a deviation from the contract documents unless the contractor pointed it out specifically at submittal and then either the architect approved it in writing as a minor change or a change order or construction change directive authorized it. Under section 3.12.9, a resubmittal must point out any revision the reviewer didn’t request, or the approval doesn’t reach it.

Why the architect’s review doesn’t make the architect responsible for dimensions

A201 section 4.2.7 says the architect reviews submittals “only for the limited purpose of checking for conformance” with the contract documents and the design concept. It says the review doesn’t test the accuracy of details such as dimensions and quantities, which remain the contractor’s, and that approving one item doesn’t approve the assembly around it. B101 section 3.6.4.2 puts the same limit into the architect’s agreement with the owner.

Each party has its reason. The contractor runs the site, verifies field measurements under A201 section 3.12.6 and has sole control of means and methods under section 3.3.1. The architect never sees the shop, and its fee pays for a design check. The owner gets one firm that answers for fit.

The limit has edges. An AIA practice article warns that an architect who writes wrong dimensions onto a submittal can own them, and a structural change inside a shop drawing is the engineer’s to catch. At the Hyatt Regency in Kansas City, the fabricator proposed hanging the second-floor walkway from the fourth-floor walkway on a second set of rods, roughly doubling the load on the fourth-floor connections, and, by the court’s findings, the project engineer approved shop drawings showing the change without confirming it would work. The walkways fell in 1981 and killed more than 100 people. The engineer of record lost his license along with the project engineer, both for gross negligence, and the Missouri Court of Appeals rejected their appeals.

How to check a shop drawing

The contractor’s stamp is the first real review, and A201 treats it as a representation to the owner and architect. A project engineer can work through a package in this order.

  1. Match it to the log. Check the specification section, submittal number, revision and sheet index.
  2. Find the set it was drawn from. Every architect’s supplemental instruction (ASI), bulletin and answered request for information (RFI) issued since should appear in it.
  3. Trace every support against the structural drawings, including bearing points, embeds and anchors.
  4. Add the other trades’ loads. Look up any equipment that sits on or hangs from the piece in the mechanical, plumbing and electrical drawings.
  5. Verify field dimensions of anything already built, and write the measured numbers on the sheet.
  6. Overlay the neighbors. Check sleeves, clearances and ceiling heights against the other trades’ drawings or the coordination model.
  7. Read the specification section, where grades, gauges, finishes and testing usually live.
  8. Cloud every deviation and list it in the transmittal, since an unflagged one stays the contractor’s after approval.
  9. Check delegated seals. The engineer should be licensed in the project’s state and should design to the engineer of record’s criteria.
  10. Read the exclusions. Every “by others” note is a scope gap until another subcontract covers it.
  11. Pull out buried questions. A note saying “verify” or “confirm with architect” is an RFI nobody has sent.
  12. Date the return, working back from the need date through fabrication time, review time and one resubmittal.

A shop drawing at 1200 Walnut Street

1200 Walnut Street, the fictional six-story building the book follows, has a concrete podium with five wood-framed floors above it, roofed with plant-built trusses. Like every Walnut Street number, the timing below is illustrative.

When Who What happens
Construction month 9 The truss supplier, under contract to the framer Submits a placement plan and sealed engineering for every roof truss
That week Nia Newman, the contractor’s assistant project manager Checks it and adds the contractor’s review stamp
On arrival Rosa Archer’s architecture firm Records it in the submittal log and hands it to the structural engineer
12 days later The structural engineer Returns it marked revise and resubmit. The calculations for the trusses below the rooftop mechanical units never counted those units’ weight
Next round The supplier’s engineer Redesigns the trusses in question and draws a cloud around each revision
After approval The structural engineer Passes it to the building department as a deferred submittal, noting general conformance with the building’s design
Once the city approves The truss plant Begins fabrication

The missing weight was on the mechanical drawings, which is what step 4 of the checklist is for. One missed check sent the package around the design team’s loop a second time before the city’s review could even begin, and the roof framing in the schedule waits on all of it.