Building inspections and special inspections
- Updated
- Written by
- Alexander J. Hale
- Reading time
- 12 min
- Sheet
- 38 of 44
During construction, the city’s building inspector checks each stage of permitted work before the next layer hides it, from footings and foundations through under-slab work, rough plumbing, mechanical and electrical, framing, insulation and fire-rated wallboard to a final inspection, and work can’t go past any of those stops until it passes. On top of that, the model International Building Code (IBC), which states and cities adopt, often with changes, requires special inspections of work such as structural concrete, steel, soils and fireproofing, done by an independent agency the owner hires and planned in a statement of special inspections written by the building’s architect or engineer. A failed inspection means the work is corrected and inspected again before anything covers it.
How building inspections work during construction
The IBC is a model code from the International Code Council (ICC). States and cities adopt different editions, some with amendments, so the rules below are the model and the local version decides. Under section 110 of the 2024 edition, any work that needs a permit is subject to inspection and has to stay visible and reachable until it’s approved. The permit holder calls for each inspection when the work is ready (110.5). Then the building official either approves that portion or tells the permit holder what fails, and failed work can’t be covered until the official allows it (110.6). If something has to be torn off so an inspector can see behind it, the code says neither the building official nor the city pays for removing or replacing it (110.1).
A pass is narrower than it sounds. Under 110.1 it can’t be read as approval of a code violation, so a problem the inspector missed still has to be fixed.
The trades often run on permits of their own. Fort Worth, Texas, requires electrical, mechanical and plumbing work to be permitted by a licensed contractor. Some tests fall to the trades. Where a city adopts the 2021 International Plumbing Code, section 312 has the permit holder give the code official advance notice and run the tests, such as holding at least a 10-foot head of water in the drain and vent piping for 15 minutes. Fitting those visits around the crews waiting behind them is a large part of a construction superintendent’s week.
Building inspection sequence, as the IBC lists it and as two cities do
Section 110.3 of the IBC lists the inspections a building official makes, roughly in the order the work gets covered. Cities publish their own lists, so no single sequence is national. The table sets the model code beside the commercial lists of Philadelphia and Fort Worth.
| Stage | IBC 2024, section 110.3 | Philadelphia, commercial building permit | Fort Worth, commercial |
|---|---|---|---|
| Before work starts | A preliminary inspection is allowed before the permit (110.2) | Initial site inspection | Stakeout, with property lines marked to check setbacks |
| Footings and foundation | After excavation, with any required reinforcing steel and forms in place (110.3.1) | Footing, foundation footing, foundation wall, then dampproofing and backfill | Foundation, after underground plumbing or electrical passes and the slab steel is in place |
| Under the slab | Reinforcing and building service equipment in place, before concrete (110.3.2) | Under slab | Part of the foundation inspection |
| Flood areas | Lowest floor elevation certificate (110.3.3) | Floodplain, only in the special flood hazard area | Not listed |
| Rough-in | Rough electrical, plumbing, heating and ductwork approved before the frame inspection (110.3.4) | All trades’ rough-ins finished before in-wall framing | Rough-ins signed off on the permit card before framing |
| Framing | After roof sheathing, framing, fireblocking and bracing are in place (110.3.4) | Exterior framing, in-wall framing, above-ceiling framing | Framing, plus a masonry check of brick ties and steel lintels |
| Insulation and energy | Insulation values, window U-values, duct insulation and equipment efficiency (110.3.9) | Insulation | Not listed |
| Fire-rated penetrations | Firestopping in rated assemblies stays exposed until approved (110.3.8) | Not listed separately | Not listed |
| Wallboard | Gypsum panels in fire-rated or shear assemblies, before taping (110.3.6) | Wallboard | Not listed |
| Final | After all work on the permit is complete (110.3.12) | Prefinal walkthrough, then final | Final |
Philadelphia calls its entries potential inspections and points owners to the permit for the ones that apply, and Fort Worth warns that inspections not on its list may be required. The building final, with sign-offs from fire, health and other departments, leads to the certificate of occupancy.
What special inspections are, and who hires the special inspector
A special inspection, in the IBC’s definition, is inspection of construction that calls for the expertise of an approved special inspector. Chapter 17 lists the work that needs one, and section 1704.2 makes these checks an addition to the building official’s own. They exist because a city inspector visiting at a hold point can’t watch every truck of concrete or every lift of soil.
Section 1704.2 puts the hiring on the owner or the owner’s agent, and says that agent can’t be the contractor. A contractor who is also the owner may hire the agency itself. The agency must be independent of the contractor and disclose possible conflicts of interest (1703.1.1), though the project’s design professionals may act as the agency for work they designed, if they qualify (1704.2.1). On the contract side, section 13.4.1 of the American Institute of Architects (AIA) general conditions, A201-2017, leaves most tests to the contractor but has the owner arrange and pay directly for those the building code requires.
Each special inspection is either continuous, with the inspector present the whole time the work is done, or periodic, with the inspector there at intervals during or after the work.
The statement of special inspections
The registered design professional in responsible charge, a licensed architect or engineer, prepares the statement of special inspections, the plan for all of this, and the applicant submits it with the permit application as a condition of the permit (1704.2.3). Under section 1704.3 it has to name every material, system and kind of work needing inspection or testing, the type and extent of each inspection, whether each is continuous or periodic, any extra wind or seismic requirements, and any deferred submittals (pieces of the design submitted after the permit application) that will need a supplemental statement.
Contractors building a main wind- or seismic-force-resisting system also sign a statement of responsibility before starting that work (1704.4). The inspection agencies send their reports to the building official and the design professional in responsible charge. A discrepancy goes to the contractor first, and if it isn’t fixed, to the building official and the designer before that phase of work is done (1704.2.4).
Special inspections list under IBC section 1705
| Work | IBC 2024 section | What gets inspected or tested | Frequency |
|---|---|---|---|
| Structural steel | 1705.2 | Inspection and nondestructive testing under the AISC 360 steel standard’s quality assurance rules, plus steel deck, open-web joists and metal building systems | Set by AISC 360 |
| Concrete | 1705.3 and Table 1705.3 | Rebar and tendon placement, cast-in anchors, the design mix, fresh-concrete samples with slump, air and temperature, placement, curing, tendon stressing, in-place strength before stressing or stripping shores, formwork | Sampling, placement and stressing continuous. Rebar, mix, curing and formwork periodic |
| Masonry | 1705.4 | The quality assurance program of the TMS 402 and TMS 602 masonry standards | As those standards set |
| Wood | 1705.5 | Shop-built elements under the fabricator rules, high-load diaphragms, bracing of metal-plate-connected trusses with clear spans of 60 feet or more, mass timber | As the statement lists |
| Soils | 1705.6 and Table 1705.6 | Bearing material under shallow foundations, excavation depth, classification and testing of fill, fill placement and density, subgrade before fill goes down | Fill placement continuous, the rest periodic |
| Deep foundations | 1705.7 to 1705.10 | Driven piles, cast-in-place piles, helical piles, integrity of deep foundation elements | Helical pile installation continuous (1705.9), others as the statement lists |
| Shop-fabricated structural members | 1704.2.5 and 1705.11 | Inspection during fabrication, unless the fabricator is approved and issues a certificate of compliance | At the fabricator |
| Wind and seismic resistance | 1705.12 to 1705.14 | Fastening and connections of lateral systems, designated seismic systems, some nonstructural components, where the building’s design calls for them | As the statement lists |
| Fireproofing and EIFS | 1705.15 to 1705.17 | Sprayed fire-resistive material thickness, density and bond, intumescent coatings, exterior insulation and finish systems | Fireproofing tested on samples |
| Firestops and fire-resistant joints | 1705.18 | Penetration firestops and joint systems in high-rises, Risk Category III or IV buildings and fire areas with Group R occupant loads over 250 | As the statement lists |
| Smoke control | 1705.19 | Leakage and device tests during duct erection, then pressure and flow tests before occupancy | Two test stages |
| Mass timber sealing | 1705.20 | Sealants and adhesives on designated mass timber elements | Periodic |
Some cities add to the code’s list. Columbus, Ohio’s special inspector qualification sheet, dated April 2026, includes photovoltaic systems, medium- and high-voltage systems and private water mains.
Structural observation is a different job. Under section 1704.6, a design professional the owner hires visits to check general conformance with the approved drawings on high-rises, Risk Category III and IV buildings and some others, and the code says those visits don’t replace any required inspection.
Third-party testing labs
IBC section 1703.1 has every approved agency, whether an inspection firm or a testing lab, show the building official that it is independent of the contractor, keeps its equipment calibrated and employs experienced staff. ASTM E329, now in a 2026 edition, gives building officials minimum criteria for judging inspection and testing agencies, and an agency complies only with a certificate of accreditation that lists its scope.
The National Ready Mixed Concrete Association (NRMCA) says ACI 318, the concrete building code, requires labs to meet ASTM C1077, and that field technicians making cylinders must hold a current American Concrete Institute (ACI) Grade I Field Testing Technician certification or equivalent. Cylinders are usually tested at 28 days. Seven-day breaks give an early read but don’t count for acceptance. A strength test passes when the average of three consecutive tests meets the specified strength and no single test falls more than 500 psi below it, for concrete specified at 5,000 psi or less. NRMCA notes that ACI 318 and ACI 301 expect a mix proportioned to the standards to miss those criteria about once in 100 tests from normal variability alone.
Soil tests compare the density of each compacted layer with a lab maximum. Where section 1803 doesn’t require the geotechnical report to cover fill placement, IBC section 1705.6 sets the floor at 90 percent of the maximum dry density from the ASTM D1557 test.
Who counts as qualified is a local call. Columbus accepts an ICC soils certification or NICET Level II for soils work, and ICC itself says its special inspector certifications don’t by themselves qualify anyone under IBC Chapter 17, since that call rests with each building official.
What happens when an inspection fails
| Kind of check | What a fail looks like | What happens next |
|---|---|---|
| City inspection | The inspector notifies the permit holder of noncompliance (IBC 110.6) | Crews correct the work and call for a reinspection, and nothing covers it until it passes. Fort Worth may charge a reinspection fee when work isn’t ready, and warns that skipping an inspection can mean removing work |
| Unsafe or noncompliant work | A written stop work order (IBC 115) | Work stops until the order’s conditions are met, and working on brings locally set fines |
| Special inspection | A discrepancy in the special inspector’s report | The contractor corrects it, or it goes to the building official and designer before that phase ends (IBC 1704.2.4) |
| Concrete strength test | A test below the acceptance criteria | NRMCA says faulty cylinder handling, curing and testing is the usual cause, so the test records get checked first. If the strength is really needed, ACI 318-19 permits three cores for each low test and treats the concrete as adequate if they average at least 85 percent of the specified strength, none below 75 percent |
| Soil compaction test | A layer below the required density | The layer is reworked and retested before the next one buries it |
The contract decides who pays. Under A201 section 13.4.3, when a test or inspection shows work that doesn’t meet the contract documents, every cost the failure causes falls on the contractor, repeat tests and the architect’s extra time included. Under section 12.1.1, work covered against the architect’s request or the contract’s stated requirements gets uncovered, if the architect asks in writing, and replaced at the contractor’s expense with no extra time.
Re-compacting loose fill at 1200 Walnut Street
1200 Walnut Street, the fictional six-story building the book follows, has a shallow dig for its street-level garage. In month 2 the excavation turns up loose fill, and re-compacting and testing it costs two weeks in one corner. All Walnut Street numbers are illustrative. The table shows what the IBC’s Table 1705.6 calls for on fill work like that.
| Step in a fix like this | What Table 1705.6 calls for | Continuous or periodic |
|---|---|---|
| Before new fill goes down | Inspect the subgrade and verify the site was prepared properly | Periodic |
| Choosing the fill | Classify and test the compacted fill material | Periodic |
| Placing and compacting each layer | Verify the materials and procedures against the approved geotechnical report, and check density and layer thickness as each layer is placed and compacted | Continuous |
On work like this the code has Fernwood Development, as owner, hire the special inspection agency (1704.2), so the person judging each layer doesn’t work for the contractor whose schedule just lost two weeks. The density target comes from the approved geotechnical report and the construction documents, usually the earthwork section of the specifications. Whether the two weeks cost Fernwood or the contractor is a contract question, worked through on the page about differing site conditions.
Sources
- Chapter 1 Scope and Administration, 2024 International Building Code as adopted in the GSA Building Code 2024, UpCodes, accessed November 26, 2026
- Chapter 17 Special Inspections and Tests, 2024 International Building Code as adopted in the GSA Building Code 2024, UpCodes, accessed November 26, 2026
- Special inspection definitions, 2024 International Building Code as adopted by the Texas Windstorm Insurance Association, UpCodes, accessed November 26, 2026
- Chapter 3 General Regulations, 2021 International Plumbing Code as adopted in Colorado, UpCodes, accessed November 26, 2026
- Inspections by permit type, Philadelphia Department of Licenses and Inspections, accessed November 26, 2026
- General Inspection List for Commercial, revised March 2023, City of Fort Worth Development Services, accessed November 26, 2026
- International Codes, Adoption by State, January 2024, International Code Council, accessed November 26, 2026
- Special Inspector Qualifications, City of Columbus Building and Zoning Services, April 2026, accessed November 26, 2026
- Special Inspector Exams, International Code Council, accessed November 26, 2026
- ASTM E329-26, Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection, ASTM International, accessed November 26, 2026
- CIP 9, Low Concrete Cylinder Strength, National Ready Mixed Concrete Association, accessed November 26, 2026
- Low-strength cylinder test results, frequently asked questions, American Concrete Institute, accessed November 26, 2026
- AIA Document A201-2017, General Conditions of the Contract for Construction, blank copy posted with bid documents, City of Rochester, New Hampshire, accessed November 26, 2026