Construction specifications and MasterFormat

Updated
Written by
Alexander J. Hale
Reading time
13 min
Sheet
31 of 44

Construction specifications are the written requirements that travel with a building’s drawings, saying what each material and system must be, how well it has to perform, how it gets installed and tested, and what the builder must submit for approval before buying it. In the US and Canada they are numbered by MasterFormat, a list of 50 divisions (00 to 49, 35 of them in use in the 2020 edition) from Construction Specifications Canada and the Construction Specifications Institute (CSI), and each section is written in three parts called General, Products and Execution. When the specifications and the drawings disagree, the construction contract decides which one wins, and the standard general conditions of the American Institute of Architects (AIA) rank neither.

What construction specifications cover that drawings don’t

The AIA’s general conditions, document A201-2017, define the two halves of the design. The drawings are the graphic part of the contract documents, showing the design, location and dimensions of the work. The specifications are the written part, covering materials, equipment, systems, standards and workmanship.

Specifications start as a short narrative in schematic design and grow into full sections by construction documents, a path the page on design phases follows. A wall on a floor plan shows where the wall runs and tags its type. The specifications say what the studs are made of, how flat the finished board must be and which product data the contractor sends the architect before ordering any of it.

What a project manual is

The project manual is the bound book or PDF that holds the specifications along with the bidding and contract forms. Under AIA document B101-2017, the owner-architect agreement, the architect compiles it during construction documents, and it includes the conditions of the contract and the specifications and may include bidding requirements and sample forms.

Not every page in it is part of the contract. A201 section 1.1.1 says the contract documents leave out the invitation to bid, the instructions to bidders, sample forms, information the owner handed out to bidders and the contractor’s own bid, unless the agreement lists them.

Part of the project manual Where MasterFormat files it What’s in it Contract document under A201
Introductory pages Division 00, 00 01 01 to 00 01 20 Title page, seals page, table of contents, list of drawing sheets Not addressed, since these pages index the rest
Procurement requirements Division 00, 00 10 00 to 00 40 00 Invitation to bid, instructions to bidders, “available information” such as 00 31 32 Geotechnical Data, bid forms No, unless the agreement lists them
Contracting requirements Division 00, 00 50 00 to 00 70 00 Agreement form, bond forms, general conditions, supplementary conditions Yes
General requirements Division 01 Allowances, alternates, substitution procedures, submittal procedures, quality requirements, temporary facilities, closeout procedures Yes
Technical sections Divisions 02 to 49 One section per kind of work, such as 03 38 00 Post-Tensioned Concrete Yes

The numbers in this table, and the section numbers used as examples below, come from CSI’s 2011 numbers and titles list. Later editions may have moved some of them, so check the edition a project manual names.

MasterFormat divisions list

The current edition is MasterFormat 2026. CSI says it adds 2,185 new listings and reorganizes 617, with most of the changed content staying in the same divisions, and sells it by subscription through its CSI Dynamic Standards service. CSI’s public pages don’t list all the 2026 divisions, so the titles below come from CSI’s page for the MasterFormat 2020 Edition. The Whole Building Design Guide (WBDG) of the National Institute of Building Sciences lists the same titles and marks the missing numbers as reserved for future expansion.

A full number reads in pairs. In the 2011 list’s 00 61 13.13, Performance Bond Form, 00 is the division, 61 narrows it to bond forms, 13 to the combined performance and payment bond form, and the digits after the decimal to the performance bond alone.

Division Title What it holds
00 Procurement and Contracting Requirements Bidding instructions and forms, available site information, the agreement, bonds and conditions of the contract
01 General Requirements Rules every trade follows, from payment and submittal procedures to quality, temporary facilities and closeout
02 Existing Conditions Assessment, subsurface investigation, demolition, remediation
03 Concrete Forming, reinforcing, cast-in-place and precast concrete, grouting, cutting and boring
04 Masonry Brick and block, stone assemblies, manufactured masonry
05 Metals Structural steel framing, joists, deck, cold-formed framing, metal stairs and railings
06 Wood, Plastics, and Composites Rough and finish carpentry, architectural woodwork, structural plastics and composites
07 Thermal and Moisture Protection Waterproofing, insulation, roofing, flashing, firestopping, joint sealants
08 Openings Doors and frames, storefronts and curtain walls, windows, skylights, hardware, glazing, louvers
09 Finishes Plaster and gypsum board, tile, ceilings, flooring, wall finishes, paint
10 Specialties Signage, toilet and bath accessories, fireplaces, safety items, mailboxes
11 Equipment Vehicle, commercial, residential, foodservice and healthcare equipment, including household appliances
12 Furnishings Art, window treatments, casework, furniture, multiple seating
13 Special Construction Special purpose rooms, special structures, instrumentation
14 Conveying Equipment Elevators, escalators, lifts, dumbwaiters, chutes
15 to 20 Reserved
21 Fire Suppression Sprinklers and other water-based systems, fire pumps, extinguishing systems
22 Plumbing Piping, plumbing equipment, fixtures, gas and vacuum systems
23 Heating, Ventilating, and Air Conditioning (HVAC) Fuel systems, HVAC piping and pumps, ductwork, central and unit equipment
24 Reserved
25 Integrated Automation Networked building controls
26 Electrical Medium- and low-voltage distribution, generating and storage equipment, lighting
27 Communications Structured cabling, data, voice, audio-video
28 Electronic Safety and Security Surveillance, detection and alarm, monitoring and control
29 and 30 Reserved
31 Earthwork Clearing, earth moving, shoring, excavation support, piles and other special foundations
32 Exterior Improvements Paving, site improvements, irrigation, planting
33 Utilities Water, sewer, storm drainage, fuel, electrical and communications utilities
34 Transportation Rail, traction power, signaling, fare collection, bridges
35 Waterway and Marine Construction Coastal, waterway, marine and dam construction
36 to 39 Reserved
40 Process Interconnections Piping, protection, commissioning and controls that tie industrial process equipment together
41 Material Processing and Handling Equipment Handling, manufacturing, packaging and storage equipment
42 Process Heating, Cooling, and Drying Equipment Industrial heating, cooling and drying equipment
43 Process Gas and Liquid Handling, Purification, and Storage Equipment Industrial gas and liquid handling, purification and storage
44 Pollution and Waste Control Equipment Air, noise, odor and water pollution control, solid waste
45 Industry-Specific Manufacturing Equipment Equipment for particular industries
46 Water and Wastewater Equipment Chemical feed, clarification and treatment equipment
47 Reserved
48 Electrical Power Generation Power plant generating equipment
49 Reserved

CSI groups the divisions too. Division 00 is the procurement and contracting group, and 01 to 49 form the specifications group, split into subgroups for general requirements (01), facility construction (02 to 14), facility services (21 to 28), site and infrastructure (31 to 35) and process equipment (40 to 48). An apartment or office building mostly lives in 00 to 14, 21 to 28 and 31 to 33, and the process divisions turn up in plants and treatment works. CSI’s own pages disagree on one title. Its 2020 list calls Division 40 Process Interconnections, and its 2026 summary page calls it Process Integration, the name in the 2011 list.

Before 2004 MasterFormat had 16 divisions, with mechanical work in Division 15 and electrical in 16, so a manual from the 1990s files pipes and wires where the current list doesn’t.

Where 1200 Walnut Street’s work sits in the manual

At 1200 Walnut Street, the fictional six-story building the book follows, the contractor set the guaranteed maximum price from the 90 percent set. All Walnut Street numbers are illustrative. That set’s project manual files the main pieces like this.

Part of the building Division
Concrete podium and its post-tensioned top slab 03 Concrete
Brick base 04 Masonry
Five wood-frame apartment floors and the roof trusses 06 Wood, Plastics, and Composites
Storefront openings for the two retail spaces 08 Openings
Mailboxes in the mail room 10 Specialties
A washer and dryer in each of the 200 apartments 11 Equipment
Elevators and the trash chute 14 Conveying Equipment
Sprinklers 21 Fire Suppression
Re-compacting the loose fill found in month 2 31 Earthwork

The roof trusses are the row to watch. On a job like this the truss section usually sets the loads and design criteria and leaves the truss design to the supplier’s engineer, a split the page on shop drawings explains. In month 9 the structural engineer returned the truss package marked revise and resubmit after 12 days of review, over a load issue. The corrected package then went to the city as a deferred submittal, a piece of the design the building official accepts after the permit application.

SectionFormat: the three parts of a spec section

Inside each numbered section, CSI’s SectionFormat standard (published with PageFormat, in its December 2009 printing) sorts the text into three parts, then articles, paragraphs and subparagraphs. Missouri’s state facilities office publishes a 2003 format guide built on the same outline, and the table below follows its article lists.

Part Question it answers Typical articles
Part 1, General What’s covered here, and what paperwork comes first Summary, references, definitions, submittals, quality assurance, delivery, storage and handling, site conditions, warranty
Part 2, Products What gets bought, and to what quality Manufacturers, materials, equipment, mixes, fabrication, finishes, source quality control
Part 3, Execution How it goes in, and how it’s checked Examination, preparation, installation, field quality control, adjusting, cleaning, protection, schedules

Every article is optional, and a part a section doesn’t need still appears with the words “Not Used” so readers know the gap is on purpose. Part 1 extends Division 01 for that one section, which is why its submittals article becomes rows on the contractor’s submittal log, the loop the page on RFIs, submittals and change orders follows.

Types of specifications: prescriptive, performance, proprietary and reference standard

Specifiers name four methods, and one section often mixes several. A prescriptive specification (also called descriptive, or method) spells out materials and steps. A performance specification states the result and how it will be measured. A reference standard specification points to a published standard, and a proprietary specification names manufacturers or products.

Type What the section says Illustrative wording Watch for
Prescriptive The materials and the steps A lumber grade, a fastener size and a nailing pattern The Federal Highway Administration (FHWA) notes that a contractor who follows a method spec “is not responsible for performance deficiencies of the end product”
Performance The result, and the test that proves it FHWA’s example measures compaction and doesn’t dictate roller type or number of passes Gaps in the criteria. Under A201 section 3.12.10.1 the contractor may rely on the criteria the owner and architect wrote
Reference standard Compliance with a published standard Ready-mixed concrete complying with ASTM C94 Which edition the section cites, and whether the standard covers the real condition
Proprietary Named manufacturers or products “Open” lists makers and allows “or equal,” “closed” allows no substitutes, “sole-source” names one product Lost competition. Federal rules in FAR 11.105 bar brand-name requirements without a documented justification, and some states, such as North Carolina and New Jersey, discourage or prohibit proprietary specs on public work

The FHWA guidance is written for highways, but its test for choosing works on buildings too. Among the conditions it lists for a method spec is end-product performance that “cannot be easily or economically measured and verified.” Performance wording fits work a test can judge on site, such as compaction, and prescriptive wording fits work nobody can test once it’s built.

Many sections name one product as the basis of design. In Yale University’s Division 01 product requirements, for example, that product’s published attributes become the yardstick for judging comparable products from the other manufacturers listed, and the drawings may show sizes and profiles taken from it.

Specifications vs drawings: who governs in a conflict

Which document wins a conflict depends on the contract in front of you. The building code doesn’t rank them, and the common contract forms disagree. The table gives what each form says, and a signed contract can change any of it.

Contract source What it says about a conflict between drawings and specifications
AIA A201-2017, sections 1.2.1, 3.2.2 and 4.2.11 The documents are complementary, and what one requires binds as if all required it. Neither is ranked. The contractor reports an inconsistency it finds as a request for information, and the architect interprets in writing
AIA A503, the guide for writing supplementary conditions Advises against a fixed order of priority and offers model wording that gives the drawings and Divisions 02 to 49 equal standing, with the architect deciding
EJCDC C-700-2018, the engineers’ joint general conditions Also complementary, with the engineer resolving conflicts, and the engineer’s own documents prevailing over referenced standards and manuals
FAR 52.236-21, the clause federal agencies put in construction contracts “In case of difference between drawings and specifications, the specifications shall govern.” A contractor that settles a discrepancy without the contracting officer’s written decision carries the cost and the risk
An owner’s own order-of-precedence clause Whatever it lists. A “more stringent requirement governs” clause pushes every bidder to price the costlier reading, so the owner pays for hidden contingencies whether or not a conflict exists

The A503 and EJCDC rows are second-hand, taken from a 2025 post on CSI’s site by specifier Kevin O’Beirne, who argues that standard forms leave precedence clauses out for good reason. On any job, read the agreement and supplementary conditions first, and send a conflict to the architect as an RFI before pricing or building either version. The guide to reading construction drawings shows how to trace one item from the sheets to its section.

What newcomers get wrong about specifications

  1. Treating a division as a subcontract. A201 section 1.2.2 says the split of the specifications into divisions and sections doesn’t decide which subcontractor does what. Division 09 holds both gypsum board and paint, and the contractor’s own bid packages set the boundaries.
  2. Treating the whole project manual as the contract. Under A201 section 1.1.1, the instructions to bidders and the information the owner gave bidders sit outside the contract documents unless the agreement lists them.
  3. Reading “or equal” as permission. Under A201 section 3.4.2, a substitution needs the owner’s consent after the architect evaluates it, by change order or construction change directive.
  4. Assuming an approved submittal changes the specification. A201 section 3.12.8 keeps the contractor responsible for a deviation unless the submittal flagged it and the architect approved that specific deviation in writing, or a change order or construction change directive covers it.

Sources