Construction specifications are the written requirements that travel with a building’s drawings, saying what each material and system must be, how well it has to perform, how it gets installed and tested, and what the builder must submit for approval before buying it. In the US and Canada they are numbered by MasterFormat, a list of 50 divisions (00 to 49, 35 of them in use in the 2020 edition) from Construction Specifications Canada and the Construction Specifications Institute (CSI), and each section is written in three parts called General, Products and Execution. When the specifications and the drawings disagree, the construction contract decides which one wins, and the standard general conditions of the American Institute of Architects (AIA) rank neither.
What construction specifications cover that drawings don’t
The AIA’s general conditions, document A201-2017, define the two halves of the design. The drawings are the graphic part of the contract documents, showing the design, location and dimensions of the work. The specifications are the written part, covering materials, equipment, systems, standards and workmanship.
Specifications start as a short narrative in schematic design and grow into full sections by construction documents, a path the page on design phases follows. A wall on a floor plan shows where the wall runs and tags its type. The specifications say what the studs are made of, how flat the finished board must be and which product data the contractor sends the architect before ordering any of it.
What a project manual is
The project manual is the bound book or PDF that holds the specifications along with the bidding and contract forms. Under AIA document B101-2017, the owner-architect agreement, the architect compiles it during construction documents, and it includes the conditions of the contract and the specifications and may include bidding requirements and sample forms.
Not every page in it is part of the contract. A201 section 1.1.1 says the contract documents leave out the invitation to bid, the instructions to bidders, sample forms, information the owner handed out to bidders and the contractor’s own bid, unless the agreement lists them.
| Part of the project manual | Where MasterFormat files it | What’s in it | Contract document under A201 |
|---|---|---|---|
| Introductory pages | Division 00, 00 01 01 to 00 01 20 | Title page, seals page, table of contents, list of drawing sheets | Not addressed, since these pages index the rest |
| Procurement requirements | Division 00, 00 10 00 to 00 40 00 | Invitation to bid, instructions to bidders, “available information” such as 00 31 32 Geotechnical Data, bid forms | No, unless the agreement lists them |
| Contracting requirements | Division 00, 00 50 00 to 00 70 00 | Agreement form, bond forms, general conditions, supplementary conditions | Yes |
| General requirements | Division 01 | Allowances, alternates, substitution procedures, submittal procedures, quality requirements, temporary facilities, closeout procedures | Yes |
| Technical sections | Divisions 02 to 49 | One section per kind of work, such as 03 38 00 Post-Tensioned Concrete | Yes |
The numbers in this table, and the section numbers used as examples below, come from CSI’s 2011 numbers and titles list. Later editions may have moved some of them, so check the edition a project manual names.
MasterFormat divisions list
The current edition is MasterFormat 2026. CSI says it adds 2,185 new listings and reorganizes 617, with most of the changed content staying in the same divisions, and sells it by subscription through its CSI Dynamic Standards service. CSI’s public pages don’t list all the 2026 divisions, so the titles below come from CSI’s page for the MasterFormat 2020 Edition. The Whole Building Design Guide (WBDG) of the National Institute of Building Sciences lists the same titles and marks the missing numbers as reserved for future expansion.
A full number reads in pairs. In the 2011 list’s 00 61 13.13, Performance Bond Form, 00 is the division, 61 narrows it to bond forms, 13 to the combined performance and payment bond form, and the digits after the decimal to the performance bond alone.
| Division | Title | What it holds |
|---|---|---|
| 00 | Procurement and Contracting Requirements | Bidding instructions and forms, available site information, the agreement, bonds and conditions of the contract |
| 01 | General Requirements | Rules every trade follows, from payment and submittal procedures to quality, temporary facilities and closeout |
| 02 | Existing Conditions | Assessment, subsurface investigation, demolition, remediation |
| 03 | Concrete | Forming, reinforcing, cast-in-place and precast concrete, grouting, cutting and boring |
| 04 | Masonry | Brick and block, stone assemblies, manufactured masonry |
| 05 | Metals | Structural steel framing, joists, deck, cold-formed framing, metal stairs and railings |
| 06 | Wood, Plastics, and Composites | Rough and finish carpentry, architectural woodwork, structural plastics and composites |
| 07 | Thermal and Moisture Protection | Waterproofing, insulation, roofing, flashing, firestopping, joint sealants |
| 08 | Openings | Doors and frames, storefronts and curtain walls, windows, skylights, hardware, glazing, louvers |
| 09 | Finishes | Plaster and gypsum board, tile, ceilings, flooring, wall finishes, paint |
| 10 | Specialties | Signage, toilet and bath accessories, fireplaces, safety items, mailboxes |
| 11 | Equipment | Vehicle, commercial, residential, foodservice and healthcare equipment, including household appliances |
| 12 | Furnishings | Art, window treatments, casework, furniture, multiple seating |
| 13 | Special Construction | Special purpose rooms, special structures, instrumentation |
| 14 | Conveying Equipment | Elevators, escalators, lifts, dumbwaiters, chutes |
| 15 to 20 | Reserved | |
| 21 | Fire Suppression | Sprinklers and other water-based systems, fire pumps, extinguishing systems |
| 22 | Plumbing | Piping, plumbing equipment, fixtures, gas and vacuum systems |
| 23 | Heating, Ventilating, and Air Conditioning (HVAC) | Fuel systems, HVAC piping and pumps, ductwork, central and unit equipment |
| 24 | Reserved | |
| 25 | Integrated Automation | Networked building controls |
| 26 | Electrical | Medium- and low-voltage distribution, generating and storage equipment, lighting |
| 27 | Communications | Structured cabling, data, voice, audio-video |
| 28 | Electronic Safety and Security | Surveillance, detection and alarm, monitoring and control |
| 29 and 30 | Reserved | |
| 31 | Earthwork | Clearing, earth moving, shoring, excavation support, piles and other special foundations |
| 32 | Exterior Improvements | Paving, site improvements, irrigation, planting |
| 33 | Utilities | Water, sewer, storm drainage, fuel, electrical and communications utilities |
| 34 | Transportation | Rail, traction power, signaling, fare collection, bridges |
| 35 | Waterway and Marine Construction | Coastal, waterway, marine and dam construction |
| 36 to 39 | Reserved | |
| 40 | Process Interconnections | Piping, protection, commissioning and controls that tie industrial process equipment together |
| 41 | Material Processing and Handling Equipment | Handling, manufacturing, packaging and storage equipment |
| 42 | Process Heating, Cooling, and Drying Equipment | Industrial heating, cooling and drying equipment |
| 43 | Process Gas and Liquid Handling, Purification, and Storage Equipment | Industrial gas and liquid handling, purification and storage |
| 44 | Pollution and Waste Control Equipment | Air, noise, odor and water pollution control, solid waste |
| 45 | Industry-Specific Manufacturing Equipment | Equipment for particular industries |
| 46 | Water and Wastewater Equipment | Chemical feed, clarification and treatment equipment |
| 47 | Reserved | |
| 48 | Electrical Power Generation | Power plant generating equipment |
| 49 | Reserved |
CSI groups the divisions too. Division 00 is the procurement and contracting group, and 01 to 49 form the specifications group, split into subgroups for general requirements (01), facility construction (02 to 14), facility services (21 to 28), site and infrastructure (31 to 35) and process equipment (40 to 48). An apartment or office building mostly lives in 00 to 14, 21 to 28 and 31 to 33, and the process divisions turn up in plants and treatment works. CSI’s own pages disagree on one title. Its 2020 list calls Division 40 Process Interconnections, and its 2026 summary page calls it Process Integration, the name in the 2011 list.
Before 2004 MasterFormat had 16 divisions, with mechanical work in Division 15 and electrical in 16, so a manual from the 1990s files pipes and wires where the current list doesn’t.
Where 1200 Walnut Street’s work sits in the manual
At 1200 Walnut Street, the fictional six-story building the book follows, the contractor set the guaranteed maximum price from the 90 percent set. All Walnut Street numbers are illustrative. That set’s project manual files the main pieces like this.
| Part of the building | Division |
|---|---|
| Concrete podium and its post-tensioned top slab | 03 Concrete |
| Brick base | 04 Masonry |
| Five wood-frame apartment floors and the roof trusses | 06 Wood, Plastics, and Composites |
| Storefront openings for the two retail spaces | 08 Openings |
| Mailboxes in the mail room | 10 Specialties |
| A washer and dryer in each of the 200 apartments | 11 Equipment |
| Elevators and the trash chute | 14 Conveying Equipment |
| Sprinklers | 21 Fire Suppression |
| Re-compacting the loose fill found in month 2 | 31 Earthwork |
The roof trusses are the row to watch. On a job like this the truss section usually sets the loads and design criteria and leaves the truss design to the supplier’s engineer, a split the page on shop drawings explains. In month 9 the structural engineer returned the truss package marked revise and resubmit after 12 days of review, over a load issue. The corrected package then went to the city as a deferred submittal, a piece of the design the building official accepts after the permit application.
SectionFormat: the three parts of a spec section
Inside each numbered section, CSI’s SectionFormat standard (published with PageFormat, in its December 2009 printing) sorts the text into three parts, then articles, paragraphs and subparagraphs. Missouri’s state facilities office publishes a 2003 format guide built on the same outline, and the table below follows its article lists.
| Part | Question it answers | Typical articles |
|---|---|---|
| Part 1, General | What’s covered here, and what paperwork comes first | Summary, references, definitions, submittals, quality assurance, delivery, storage and handling, site conditions, warranty |
| Part 2, Products | What gets bought, and to what quality | Manufacturers, materials, equipment, mixes, fabrication, finishes, source quality control |
| Part 3, Execution | How it goes in, and how it’s checked | Examination, preparation, installation, field quality control, adjusting, cleaning, protection, schedules |
Every article is optional, and a part a section doesn’t need still appears with the words “Not Used” so readers know the gap is on purpose. Part 1 extends Division 01 for that one section, which is why its submittals article becomes rows on the contractor’s submittal log, the loop the page on RFIs, submittals and change orders follows.
Types of specifications: prescriptive, performance, proprietary and reference standard
Specifiers name four methods, and one section often mixes several. A prescriptive specification (also called descriptive, or method) spells out materials and steps. A performance specification states the result and how it will be measured. A reference standard specification points to a published standard, and a proprietary specification names manufacturers or products.
| Type | What the section says | Illustrative wording | Watch for |
|---|---|---|---|
| Prescriptive | The materials and the steps | A lumber grade, a fastener size and a nailing pattern | The Federal Highway Administration (FHWA) notes that a contractor who follows a method spec “is not responsible for performance deficiencies of the end product” |
| Performance | The result, and the test that proves it | FHWA’s example measures compaction and doesn’t dictate roller type or number of passes | Gaps in the criteria. Under A201 section 3.12.10.1 the contractor may rely on the criteria the owner and architect wrote |
| Reference standard | Compliance with a published standard | Ready-mixed concrete complying with ASTM C94 | Which edition the section cites, and whether the standard covers the real condition |
| Proprietary | Named manufacturers or products | “Open” lists makers and allows “or equal,” “closed” allows no substitutes, “sole-source” names one product | Lost competition. Federal rules in FAR 11.105 bar brand-name requirements without a documented justification, and some states, such as North Carolina and New Jersey, discourage or prohibit proprietary specs on public work |
The FHWA guidance is written for highways, but its test for choosing works on buildings too. Among the conditions it lists for a method spec is end-product performance that “cannot be easily or economically measured and verified.” Performance wording fits work a test can judge on site, such as compaction, and prescriptive wording fits work nobody can test once it’s built.
Many sections name one product as the basis of design. In Yale University’s Division 01 product requirements, for example, that product’s published attributes become the yardstick for judging comparable products from the other manufacturers listed, and the drawings may show sizes and profiles taken from it.
Specifications vs drawings: who governs in a conflict
Which document wins a conflict depends on the contract in front of you. The building code doesn’t rank them, and the common contract forms disagree. The table gives what each form says, and a signed contract can change any of it.
| Contract source | What it says about a conflict between drawings and specifications |
|---|---|
| AIA A201-2017, sections 1.2.1, 3.2.2 and 4.2.11 | The documents are complementary, and what one requires binds as if all required it. Neither is ranked. The contractor reports an inconsistency it finds as a request for information, and the architect interprets in writing |
| AIA A503, the guide for writing supplementary conditions | Advises against a fixed order of priority and offers model wording that gives the drawings and Divisions 02 to 49 equal standing, with the architect deciding |
| EJCDC C-700-2018, the engineers’ joint general conditions | Also complementary, with the engineer resolving conflicts, and the engineer’s own documents prevailing over referenced standards and manuals |
| FAR 52.236-21, the clause federal agencies put in construction contracts | “In case of difference between drawings and specifications, the specifications shall govern.” A contractor that settles a discrepancy without the contracting officer’s written decision carries the cost and the risk |
| An owner’s own order-of-precedence clause | Whatever it lists. A “more stringent requirement governs” clause pushes every bidder to price the costlier reading, so the owner pays for hidden contingencies whether or not a conflict exists |
The A503 and EJCDC rows are second-hand, taken from a 2025 post on CSI’s site by specifier Kevin O’Beirne, who argues that standard forms leave precedence clauses out for good reason. On any job, read the agreement and supplementary conditions first, and send a conflict to the architect as an RFI before pricing or building either version. The guide to reading construction drawings shows how to trace one item from the sheets to its section.
What newcomers get wrong about specifications
- Treating a division as a subcontract. A201 section 1.2.2 says the split of the specifications into divisions and sections doesn’t decide which subcontractor does what. Division 09 holds both gypsum board and paint, and the contractor’s own bid packages set the boundaries.
- Treating the whole project manual as the contract. Under A201 section 1.1.1, the instructions to bidders and the information the owner gave bidders sit outside the contract documents unless the agreement lists them.
- Reading “or equal” as permission. Under A201 section 3.4.2, a substitution needs the owner’s consent after the architect evaluates it, by change order or construction change directive.
- Assuming an approved submittal changes the specification. A201 section 3.12.8 keeps the contractor responsible for a deviation unless the submittal flagged it and the architect approved that specific deviation in writing, or a change order or construction change directive covers it.
Sources
- AIA Document A201-2017, General Conditions of the Contract for Construction, blank copy posted with bid documents, City of Rochester, New Hampshire, accessed November 26, 2026
- AIA Document B101-2017 sample, Internet Archive copy of the AIA’s own posting, American Institute of Architects, accessed November 26, 2026
- MasterFormat 2026, Construction Specifications Institute, accessed November 26, 2026
- CSI Dynamic Standards, plans and pricing, Construction Specifications Institute, accessed November 26, 2026
- MasterFormat 2020 Edition, Construction Specifications Institute, accessed November 26, 2026
- CSI MasterFormat, SpecsIntact help, Whole Building Design Guide, National Institute of Building Sciences, accessed November 26, 2026
- MasterFormat 2011 Numbers and Titles, Construction Specifications Institute and Construction Specifications Canada, hosted by NYC Office of Environmental Coordination, accessed November 26, 2026
- SectionFormat/PageFormat, Construction Specifications Institute, accessed November 26, 2026
- Format for Construction Specifications, Missouri Office of Administration, Facilities Management, Design and Construction, accessed November 26, 2026
- Development and Review of Specifications, Technical Advisory, March 24, 2010, Federal Highway Administration, accessed November 26, 2026
- Specifying Methods: Proprietary Specifying 101, Kevin O’Beirne, Construction Specifications Institute, accessed November 26, 2026
- FAR 11.105, Items Peculiar to One Manufacturer, Acquisition.gov, accessed November 26, 2026
- Interpretations and Clarifications Part 3: Order of Precedence Clauses, Kevin O’Beirne, Construction Specifications Institute, accessed November 26, 2026
- FAR 52.236-21, Specifications and Drawings for Construction, Acquisition.gov, accessed November 26, 2026
- 01 60 00 Product Requirements, Office of Facilities Procedure Manual, Yale University, July 2025, accessed November 26, 2026