Site due diligence before you build

Updated
Written by
Alexander J. Hale
Reading time
10 min
Sheet
11 of 44

Site due diligence is the investigation a buyer runs on a piece of land after signing the purchase contract and before its deposit stops being refundable, looking for anything that would stop the project or change what the land is worth. The usual package is a title commitment, an ALTA/NSPS land title survey, a Phase I environmental site assessment, a geotechnical report on the soil, a zoning check and letters from the utilities saying whether they could serve the building. A finding that arrives after the contract’s deadline can still change the design, but it no longer gets the deposit back.

How the feasibility period works

Almost every commercial purchase contract gives the buyer a window to study the site, called the feasibility period or due diligence period. The buyer puts down earnest money, a deposit usually held by an escrow agent. Two real estate lawyers, in materials for a 2022 legal conference of the International Council of Shopping Centers (ICSC), put deposits at 3 to 5 percent of the purchase price in their experience, with significant variations, and the periods at generally 30 to 90 days.

Inside the window, most contracts let the buyer cancel for any reason and get the deposit back, as long as the notice is in writing and on time. A guide from the law firm Baker Donelson tells buyers to settle whether silence counts as waiving the contingency, and to fix the deadline to the hour. After the deadline the deposit goes hard, and a buyer who walks away for a reason the contract no longer covers forfeits it. Extensions usually cost an added payment, which the ICSC authors say is often non-refundable.

Sellers often allow only noninvasive testing without their written consent, and soil borings and groundwater samples are invasive. A buyer whose plan needs a rezoning or another discretionary approval should also bargain for a separate permit contingency, since the ICSC authors warn that the timing of those approvals is hard to predict.

Site due diligence checklist

This sample is set up as a development manager might on day 1, with start dates set by lead times. A survey usually takes at least 30 days, according to the ICSC authors, and the surveyor needs the title commitment first.

Item Who prepares it What it answers A finding that changes the deal When to start
Title commitment Title insurance company Who owns the land, and what a policy would leave out An easement under the planned footprint, a covenant limiting the use, or a lien the seller can’t clear Day 1
ALTA/NSPS land title survey Licensed land surveyor Where boundaries, easements, encroachments and visible utilities sit A neighbor’s wall over the line, or an easement cutting into the buildable area When the title commitment arrives
Zoning check Zoning consultant, land use lawyer or the city Whether use, height, setbacks, density and parking fit the district A use that needs a rezoning, or a height or density cap that cuts the unit count Week 1
Phase I environmental site assessment Environmental professional Whether records, interviews and a site visit point to contamination A former gas station on the site, or other signs that call for Phase II sampling Early, with key parts updated to within 180 days of closing
Geotechnical report Geotechnical engineer What foundations the soil can carry and where groundwater sits Soft soil, old fill or high groundwater that calls for deep foundations or pumping Once the seller consents to borings
Will-serve letters Water, sewer, electric and gas providers Whether each could serve the project, and at what connection cost No capacity in a main, or an off-site line extension the buyer must pay for Week 1
Flood zone and wetlands Surveyor (flood zone) and environmental consultant (wetlands) Whether the land is in a mapped flood zone or holds wetlands A Special Flood Hazard Area, or wetlands that need a federal permit to fill With the survey
Rents and costs Market analyst and the developer Whether the finished building can carry the land price Rents too low or costs too high for the development pro forma to work Day 1, revised as reports arrive

What goes in a site due diligence report

A site due diligence report can mean the stack of separate reports below, or a single summary that a civil engineer or land use consultant writes from them for the buyer and its lender.

Title commitment

Before a title insurer issues a policy, it issues a title commitment, a written promise to insure on stated terms. On the American Land Title Association’s 2021 form, Schedule A names the proposed insured, the amount and the current owner. Schedule B, Part I lists what must happen before the policy issues, such as paying the price and recording the deed. Schedule B, Part II lists the exceptions the policy won’t cover, which is where easements and recorded restrictions that can move a building show up. The commitment ends if Part I is still unmet 180 days after its date, and a lender usually wants its own policy too.

ALTA/NSPS land title survey

An ALTA/NSPS land title survey follows a national standard from ALTA and the National Society of Professional Surveyors, written so a title insurer can cover the land without a blanket exception for whatever a survey would have shown. The current version took effect on February 23, 2026. The surveyor plots the easements listed in the title commitment, then walks the ground for what the records miss, such as a fence or driveway across the line. Optional Table A items add more, and a development buyer will often order the flood zone (item 3), zoning limits taken from a zoning report the client supplies (items 6(a) and 6(b)), underground utilities (item 11) and a table of potential encroachments (item 20). The standard itself warns that without excavation, underground features can’t be shown accurately or completely.

Phase I environmental site assessment

Federal Superfund law, CERCLA, can make an owner pay to clean up contamination it never caused. As amended in 2002, the law offers buyers three protections, as a bona fide prospective purchaser, a contiguous property owner or an innocent landowner, and each requires all appropriate inquiries into the land’s past before the purchase, under EPA’s rule at 40 CFR Part 312. The standard way to meet the rule is a Phase I environmental site assessment done to ASTM E1527-21, which EPA recognizes, or to ASTM E2247-23 for forestland and rural land.

An environmental professional reviews government records, interviews past and present owners and occupants, and inspects the site and the properties next to it. The rule doesn’t require sampling, as EPA’s 2019 guidance notes, so a clean Phase I means the records and the walk found nothing. When they point to hazardous substances or petroleum from a past, likely or threatened release, ASTM calls it a recognized environmental condition, and the usual next step is a Phase II with soil or groundwater samples.

Timing catches long deals. The inquiries must be done within a year before the purchase, and the interviews, lien search, records review, site visit and the professional’s declaration within 180 days of it, so a Phase I finished early in an extended window can go stale before closing. The protection also brings duties after the purchase, among them taking reasonable steps about any contamination and obeying land use restrictions.

Geotechnical report

AIA’s standard owner-architect agreement, B101-2017, puts the surveys and the geotechnical services on the owner’s side, so the owner hires the geotechnical engineer and the architect designs from the findings. Where the International Building Code (IBC) calls for an investigation, the report goes to the building department with the permit application and covers the boring logs, the soil profile, any groundwater found, foundation recommendations, expected settlement and fill requirements. During the feasibility period its main use is pricing the foundations, ordinary footings or deep ones such as piles, and any pumping the excavation will need. Conditions the borings missed can still surface during digging, which the page on differing site conditions covers.

Utilities and fees

Each provider answers with a will-serve letter, saying in writing whether it has the capacity for the project. Salt River Project, an Arizona utility, says its letters don’t guarantee service, only that it could serve the property. The letters also open the money questions, including connection charges, any line extension the developer must build and the impact fees many cities charge new buildings toward public roads, parks and pipes.

Zoning check

The buyer confirms the district, the allowed uses and the limits on height, setbacks, density or floor area and parking, through a zoning report or the city’s zoning verification letter, and the page on zoning vs building codes explains each rule. Hagerstown, Maryland, says its letter names the district, whether a use is permitted, any variances granted and any violations, and that lenders often ask for one. A project that fits by right, under the rules as written, keeps the normal schedule, and one that needs a rezoning or variance needs the longer permit contingency.

Flood zones and wetlands

FEMA’s Special Flood Hazard Area is land with a 1 percent chance of flooding in any year, and a federally regulated or insured lender must require flood insurance on a building there that secures its loan. Filling wetlands that count as waters of the United States takes a permit under Section 404 of the Clean Water Act, reviewed by the US Army Corps of Engineers or an approved state or tribal program.

Worked example: due diligence at 1200 Walnut Street

1200 Walnut Street, the fictional six-story building the book follows, puts the checklist to work, and all of its numbers are illustrative. Fernwood Development, a regional developer that keeps its buildings to rent out, puts the site under a purchase contract with a feasibility period. Lana Landry, its development manager, works the list herself alongside two other projects, since Fernwood hires no outside owner’s representative. An architecture firm runs an early feasibility and massing study of how much the site can hold.

The zoning check finds that the site allows the use and the height without a rezoning, but the city’s design review, with public notice, is required. Its notice sign on the fence will stay up until the contractor mobilizes.

Fernwood closes on the land with $7.5 million in cash, and full design starts after that. The survey and reports sit in the soft costs, in a $2.0 million line shared with legal fees, title and insurance, and permit, impact and utility fees get their own $3.5 million line. Borings sample only the spots they hit. In month 2 of construction the dig turns up loose fill in one corner, and re-compacting and testing it costs that corner two weeks.