What is an owner's representative?

Updated
Written by
Alexander J. Hale
Reading time
9 min
Sheet
5 of 44

An owner’s representative is a person or firm an owner hires to run its side of a construction project, from choosing the architect and builder through move-in, while holding none of the design or construction contracts. The rep keeps the budget and schedule, reviews everything the architect and contractor send the owner for approval, from monthly payment requests to change orders, and recommends what to do about each. An owner with construction-savvy staff of its own can give the same job to an employee instead.

What does an owner’s representative do in construction?

The rep does the owner’s work on a project, the part that takes someone who knows how buildings get designed, priced and built. It draws nothing and builds nothing. The Construction Management Association of America (CMAA) files the service under agency construction management, in which the manager acts as the owner’s representative or an extension of its staff. The owner signs every design and construction contract itself, and the contractors carry much of the cost and performance risk. A rep that oversees a whole program of projects, or one very large and complex project, is called a program manager.

Massachusetts shows the job most clearly, because its law requires one on public building projects. A public agency there planning a building project estimated at $1.5 million or more must hire an owner’s project manager (OPM) before it signs a design contract, choose the firm on qualifications, and keep it independent of the designer, the general contractor and every subcontractor. The OPM must be a registered architect or engineer with at least five years of experience in building construction and its supervision, or anyone with seven.

The Massachusetts School Building Authority (MSBA) publishes the scope its OPMs work to on a construction manager at risk job. During construction, the rep:

  • reviews every payment application and invoice from the designer, the builder and the vendors, and recommends the amount due
  • keeps the project budget and schedule, and reports every variance in a monthly progress report due by the 12th
  • reviews each change order proposal, prices any over $100,000 independently, and recommends accepting, modifying or rejecting it
  • checks that the builder’s cost records support what it bills against the guaranteed maximum price (GMP)
  • runs the punch list to the end and gathers the closeout papers, from the occupancy permit to the warranties and manuals

The rep recommends and reports. The owner still signs.

Before construction, the rep sets the baseline budget that every estimate, bid and GMP is later measured against, helps choose a project delivery method, and helps pick the architect. Plante Moran, an accounting and consulting firm that sells the service, advises bringing a rep in before the architect is hired, while those decisions are still open.

Owner’s representative vs construction manager, architect and lender’s inspector

Several people on a job act for the owner in some way. What separates them is whose contract they hold and whose money they risk.

Role Hired by Holds the construction contracts Carries construction cost risk Acts for
Owner’s representative or agency CM Owner No, the owner does No The owner, as its agent
Program manager Owner No, in its usual agency form No The owner, across a program of projects
Construction manager at risk Owner Yes, once the GMP is signed Yes, above the GMP The owner during preconstruction, then itself as the builder
Architect Owner No No The owner during construction, only as far as the contract documents allow, and impartially when interpreting them
Lender’s inspector The bank No No The bank

In practice an owner’s rep and an agency CM do much the same job, and the titles overlap. ConsensusDocs, a standard contract publisher, titles its form 810 an agreement between owner and owner’s representative, and describes that representative as a construction manager acting as an independent contractor. The general contractor page sets an agency CM beside a CM at risk.

How much does an owner’s representative cost?

Fees are negotiated job by job. Some of the most detailed public numbers come from Massachusetts public school projects, where the MSBA tracks what each district budgeted for its OPM and its designers as a share of construction cost.

Massachusetts school projects OPM fees Designer fees
Elementary schools 4.02% 11.11%
Middle schools 3.72% 10.76%
High schools 3.63% 10.48%
Middle and high schools combined 4.06% 11.80%
All schools, about $14.6 billion of construction 3.77% 10.76%

The figures cover projects with an estimated construction start in 2014 or later, as of April 29, 2026. They come from budgets the MSBA reviewed at schematic design, so final contracts may differ. About 59 percent of the OPM money sits in the construction administration phase. Expect a private owner’s percentage to come out differently, because a Massachusetts school OPM also prepares the state’s reports, labor-law paperwork and building committee agendas.

The method behind the fee decides who pays when the job runs long. CMAA lists the usual ones.

Method How the bill is built Who absorbs extra months
Salary times a multiplier, plus expenses Actual salaries times a factor for overhead, plus an agreed profit, with expenses billed separately The owner
Hourly billing rates A set rate for each class of staff The owner
Cost plus a fixed fee Salaries times a multiplier, plus profit as a fixed sum The owner pays the hours, and the rep’s profit stays fixed
Lump sum One agreed price, often billed in equal monthly parts The rep, until the contract’s change triggers apply
Percent of construction cost A share of the construction price Tied to the price, not to the effort

CMAA, the construction managers’ own association, recommends against the last method, calling it arbitrary and unrelated to the effort a job takes. A small building on a compressed schedule can need more of a rep’s hours than a large, orderly one. A fee that grows with the construction price also grows with the one number the owner hired the rep to hold down. CMAA also warns that a lump sum suits services of predictable length, and a rep’s months depend on the contractors’ schedule. Its way to negotiate one starts from a staffing plan for an agreed duration, adds expenses and a contingency, and writes into the contract what would change the fee.

When does an owner need an owner’s representative?

An owner needs one when nobody on its staff both knows construction and has the hours to run a project. A company building its first headquarters fits that description. A developer that employs development managers has the people already, and CMAA notes that an owner can staff the role in house, contract it out or combine the two. Massachusetts public agencies need an OPM either way, though the law lets an agency use its own employee who meets the same qualifications.

Hiring a rep doesn’t settle who can say yes. CMAA repeats the industry saying that delay from indecision is the most frequent cause of project disruption, and it urges owners to give the power to commit their money to one qualified person or a small group. The AIA’s general conditions, A201, have the owner name in writing a representative with express authority to bind it. The ConsensusDocs 810 form goes further and lets the rep bind the owner without asking first, in every project matter that would otherwise need the owner’s sign-off. Write the rep’s dollar limit for change orders into its contract before the first one arrives.

At Walnut Street: a development manager instead of a rep

1200 Walnut Street, the fictional six-story building the book follows, has no outside owner’s rep. Its owner, Fernwood Development, has its development manager, Lana Landry, do the rep’s job alongside two other projects. All Walnut Street numbers are illustrative.

Rep’s task At Walnut Street
Hire the builder Fernwood signs a construction manager at risk once schematic design wraps up, and pays it a fee for preconstruction work
Check the design against the budget Fernwood reviews the 90 percent set two weeks after it’s issued, and the GMP is due a week later
Approve payments Each month’s pay application holds back 10 percent retainage, dropping to 5 percent at half complete
Settle changes ASI 22 becomes a time-and-materials change directive, then about $3,100 in change order 6
Settle disputes A drain stack lands on a podium beam. After two weeks of letters, Lana and Victor Price, the contractor’s chief estimator, split the cost in one meeting
Protect the date Near the end, each late day costs Fernwood about $11,000 to $37,000

Applied purely for scale, the Massachusetts public-school average of 3.77 percent would put an outside rep on the $60 million GMP at about $2.3 million, what Fernwood loses in about 60 to 200 days of late opening. Fernwood’s budget has no such line. It pays in Lana’s attention instead, and the two weeks of letters over one drain stack came out of the same hours as her other two projects.

What newcomers get wrong about owner’s representatives

What newcomers assume How it works
“Owner’s representative” in the contract means the hired rep In A201 the owner’s authorized representative is the person the owner names in writing with express authority to bind it, and section 4.2.1 calls the architect “an Owner’s representative during construction” with only the authority the documents give. A hired rep binds the owner only if the owner names it or its own contract says so
The rep guarantees the budget Under agency construction management the contractors carry much of the cost risk and the owner keeps the decisions. The rep’s product is the recommendation
The bank’s inspector looks out for the owner too The inspector visits for the bank, to confirm the billed work is in place before money goes out. Banks without in-house expertise often hire an outside construction consultant to do it
The architect can do the rep’s job The architect administers the construction contract, but when a change order turns on whether the drawings were wrong, it’s answering for its own work