Lump sum, cost-plus and unit price contracts

Updated
Written by
Alexander J. Hale
Reading time
9 min
Sheet
17 of 44

A construction contract type is the rule that sets how the builder gets paid. Under a lump sum, which the American Institute of Architects (AIA) calls a stipulated sum in its forms, the contractor commits to one fixed price, keeps whatever it saves and absorbs whatever it overspends. Under cost-plus, the owner pays the actual cost of the work plus a fee and carries any overrun itself unless a guaranteed maximum price (GMP) caps it, while a unit price contract fixes a rate for each measured unit of work and time and materials (T&M) pays hourly rates plus materials, usually up to a ceiling.

Who signs with whom, and when the builder joins, is a separate question, the delivery method, covered on the project delivery methods page.

Lump sum vs cost plus vs unit price compared

The forms in the last column come from the AIA and from ConsensusDocs, a rival set written by a coalition of more than 40 industry groups.

Contract type How the price is set Who pays an overrun Standard forms
Lump sum (stipulated sum) One price for the defined scope, usually bid on finished drawings The contractor AIA A101, or A104 for limited scope. ConsensusDocs 200, or 205 short form
Cost plus a fee, no cap Actual cost of the work plus a fixed or percentage fee The owner AIA A103, or A134 with a construction manager. ConsensusDocs 235 short form
Cost plus a fee with a GMP Actual cost plus the fee, up to a ceiling The contractor, above the ceiling AIA A102, or A133 with a construction manager. ConsensusDocs 230, or 500 with a construction manager
Unit price A rate per cubic yard, linear foot or other unit, times the quantity measured in the field The contractor on its rates, the owner on the quantity No separate AIA agreement. A101 has a section for listing unit prices
Time and materials Fixed hourly labor rates plus materials at cost The owner, up to any ceiling AIA suggests A104, A103 or its residential A110, plus a not-to-exceed amount. ConsensusDocs notes its 235 form is sometimes called T&M

Lump sum (stipulated sum) contracts

A lump sum puts the estimate at the contractor’s risk. If a crew runs slow or steel costs more than the estimate assumed, the difference comes out of the contractor’s profit. Chris Hendrickson’s construction management text at Carnegie Mellon University names what the owner pays for that, since a contractor holding nearly all the cost risk can be expected to ask for a higher markup.

The number still moves. Work the owner adds, errors in the owner’s drawings and conditions nobody could see come back as change orders, which the RFIs, submittals and change orders page walks through. Between changes, the owner pays monthly against a schedule of values, the contractor’s split of the price across portions of the work, and each request under A101 shows the percentage complete of every line. The owner doesn’t see what the work actually cost the contractor.

Federal agencies start here. The Federal Acquisition Regulation (FAR) says construction should generally be bought at a firm fixed price, with lump-sum pricing preferred over unit pricing except in listed cases, such as large quantities of grading or paving, excavation nobody can estimate with confidence, or quantities likely to shift during construction (FAR 36.207).

Cost plus fixed fee vs percentage fee

Under cost-plus, the owner reimburses the cost of the work, a defined term, and pays a fee on top. AIA describes A103 for projects whose cost isn’t fully known when construction starts, and says the form isn’t meant for competitive bidding. Under it, someone on the owner’s staff has to check the invoices behind every monthly bill. The fee carries the contractor’s incentive, and A103 lets the parties write in a lump sum, a percentage of the cost of the work or another method.

A fixed fee stays put whatever the work costs. The federal rule, FAR 16.306, sets it at the start and changes it only when the work itself changes. Hendrickson notes that a fixed fee gives the contractor some reason to finish quickly, since a longer job earns it nothing extra.

A percentage fee rises with spending, and Hendrickson’s text advises owners to avoid it without a compelling reason. The federal government bars it on its own contracts. FAR 16.102(c), citing 10 U.S.C. 3322(a) and 41 U.S.C. 3905(a), rules out the cost-plus-a-percentage-of-cost system.

Take a hypothetical job with the cost of the work estimated at $10 million and the fee written two ways.

Actual cost of the work Fixed fee Fee at 5 percent of cost
$9 million $500,000 $450,000
$10 million $500,000 $500,000
$11 million $500,000 $550,000

The fixed fee pays $500,000 at either end. The percentage fee pays the contractor $100,000 more for the job that cost $2 million more.

Cost-plus with a GMP

A cap keeps the owner paying actual costs plus the fee and adds a ceiling the contractor pays above. The GMP page covers what sits inside the number, when it gets set and how savings are split.

Unit price contracts

A unit price contract fixes the rate and leaves the quantity open. The bid form lists each item with an estimated quantity, such as cubic yards of rock or linear feet of pipe, the contractor bids a rate per unit, and payment follows what gets measured in the field. Hendrickson warns that bidders sometimes unbalance a bid, loading the rates on items they think the owner underestimated and trimming the rest, and that an owner can disqualify a bid unbalanced too far.

A quantity far off the estimate breaks the math behind the rate, because the bidder spread its setup and equipment costs over the quantity on the form. FAR 52.211-18 handles this for federal work. Once the measured quantity differs from the estimate by more than 15 percent, either side can demand an equitable adjustment, limited to the cost effect of the part above 115 percent or below 85 percent. AIA’s A101 gives each unit price a line for any quantity limits that go with it.

Take a hypothetical 1,000 cubic yards of rock excavation, bid at $150 a yard for $150,000, measured three ways under the federal 15 percent rule.

Measured quantity Paid at the bid rate Open to repricing on demand
1,100 cubic yards All 1,100, or $165,000 Nothing
1,400 cubic yards The first 1,150, or $172,500 The 250 yards above 115 percent
700 cubic yards All 700, or $105,000 The cost of falling 150 yards short of 850, such as equipment priced to spread over more rock

Time and materials contracts

T&M pays for inputs. In the federal version, FAR 16.601, the contractor bills hours at a fixed rate for each labor category that already includes wages, overhead and profit, and materials come at actual cost. The same section says a T&M contract “provides no positive profit incentive to the contractor for cost control or labor efficiency,” so the government has to watch the work. The FAR allows T&M only when nobody can estimate the extent or duration of the work with confidence, and every T&M contract needs a ceiling price the contractor exceeds at its own risk. AIA suggests a not-to-exceed amount or cost cap for the same reason. On building jobs, T&M often turns up inside contracts priced another way, for a change that has to be built before anyone can price it.

Which party carries which risk

Risk Lump sum Cost plus, no cap Cost plus with a GMP Unit price Time and materials
The estimate was too low Contractor Owner Contractor, above the cap Contractor, on its rates Owner, up to the ceiling
More work than the estimate showed Contractor, if the drawings showed it Owner Contractor above the cap, if the drawings showed it Owner, with repricing past any agreed band Owner
A crew works slower than planned Contractor Owner Contractor, above the cap Contractor Owner
Material prices climb after signing Contractor, unless an escalation clause applies Owner Contractor above the cap, unless an escalation clause applies Contractor, unless an escalation clause applies Owner
The owner changes what it wants Owner, by change order Owner Owner, by change order Owner Owner

Two risks sit outside the pricing method. Errors in drawings the owner supplied have generally been the owner’s responsibility since the Supreme Court’s 1918 Spearin decision, whichever pricing method the contract uses. Ground or hidden conditions that differ from what the contract showed are governed by a separate clause, explained on the differing site conditions page.

At 1200 Walnut Street

1200 Walnut Street, the fictional six-story building the book follows, runs on several pricing methods at once. All Walnut Street figures are illustrative.

Agreement How the price is set Walnut Street figure
Fernwood Development and the architecture firm A negotiated design fee $4.0 million
Fernwood and the contractor, from the end of schematic design A preconstruction fee for estimating and reviewing the drawings No amount set for the example
Fernwood and the contractor, for construction Cost of the work plus a fee, capped by a GMP priced from the 90 percent set $60.0 million, which includes the contractor’s $2.4 million to $4.2 million fee
One change in month 9 ASI 22 from the architect leads to a construction change directive on time and materials, priced afterward About $3,100, settled as change order 6

The month-9 change is the T&M case described above. The work went ahead before anyone could price it, and the record of hours and materials became the basis for the change order.

What newcomers get wrong

  1. Reading cost-plus as a blank check. The agreement defines which costs the owner reimburses, and A103 spells out the costs it won’t.
  2. Assuming the delivery method fixes the contract type. CM at risk jobs usually end in a GMP and design-bid-build jobs in a lump sum, but those are habits. AIA’s residential agreement, A110, offers a stipulated sum or cost plus a fee, with or without a GMP.
  3. Taking unit price quantities as promises. They’re estimates that let bids be compared, and payment follows the tape measure.
  4. Signing T&M without a ceiling. The FAR won’t allow it on federal work, and a private owner has no better reason to.