Construction closeout and warranties

Updated
Written by
Alexander J. Hale
Reading time
10 min
Sheet
43 of 44

Construction closeout is the stretch from substantial completion, when the owner can start using the building, to final payment, while the contractor clears the punch list and turns over the record of what was built and how to run it, from drawings, manuals and warranties to spare materials, training, commissioning reports and final lien waivers. Under the AIA’s A201 general conditions, the final payment and the last of the retainage wait until those papers are in and the architect finds the work complete. The “one-year warranty” people mention is usually A201’s one-year correction period, a duty to come back and fix defects the owner reports, while the contractor’s warranty itself and each state’s deadlines for suing run longer.

Construction closeout documents

The list comes from the contract and the specifications, mostly Division 01, the general requirements, plus a clause in each trade’s own section.

Document What it is Who prepares it Who checks or keeps it
As-built drawings Drawings the crews mark up during the job wherever the work departs from the design, from RFI answers, changes, contractor-designed pieces and differing site conditions The contractor, collecting from each trade The architect reviews them
Record drawings The final clean set compiled from the as-builts The contractor or the architect, depending on the contract The owner keeps them
Operation and maintenance (O&M) manuals How each system runs, starts and shuts down, with its maintenance, wiring and control diagrams, parts and supplier contacts The contractor, from trades and manufacturers The owner’s maintenance staff
Warranties The contractor’s own warranty plus written warranties from manufacturers and installers, issued in the owner’s name or transferable to it The contractor collects them The owner
Attic stock and spare parts Extra finish materials and parts left behind for repairs The trades deliver them The architect signs for them and the owner stores them
Training records and videos Sessions where installers teach the owner’s staff to run and maintain the equipment Trades and manufacturers The owner’s maintenance staff
Commissioning reports Test results showing heating, cooling, hot water and lighting controls work as designed A commissioning provider The owner, and the code official on request
Final payment papers The contractor’s sworn statement that its bills are paid, proof of continuing insurance, the surety’s consent and any final lien waivers the owner requires The contractor, its subcontractors and its surety The architect, before certifying final payment

As-built drawings vs record drawings

A201 section 3.11 has the contractor keep the contract documents at the site, marked currently with field changes, and deliver them at completion as the record of the work as built. The table’s two terms follow the federal closeout guide specification, UFGS 01 78 00 (August 2026). The International Energy Conservation Code (IECC) wants record documents showing every change in the size, type and location of mechanical, electrical and control components. The IECC is a model code that states and cities adopt with their own changes, and its figures on this page come from Colorado’s adoption of the 2021 edition, so local rules may differ. A valve moved two feet during the job can be found years later only if someone marked it the week it moved.

O&M manuals, training and attic stock

The federal O&M specification, UFGS 01 78 23, asks for a progress submittal of the manuals at about 50 percent construction and, on military construction, a complete prefinal manual 90 days before the owner is due to occupy the building. Training needs a written plan at least 60 days ahead, and the sessions are recorded on video. The IECC’s minimum training covers the manuals, hands-on demonstrations of normal maintenance and of emergency shutdown and startup, and a completion report.

Attic stock is boxed surplus finish material, so a damaged ceiling panel in year four gets replaced with one that matches. Each trade’s specification section sets the quantity. Kutztown University’s 2023 design guidelines, for one, require extra acoustical panels equal to 4 percent of each type installed, or 15 of each type, whichever is greater.

Commissioning reports

The IECC’s commissioning section, C408.2, exempts only buildings whose mechanical equipment totals less than 480,000 Btu per hour of cooling and less than 600,000 Btu per hour of combined space and water heating. A building at or above either figure must have those systems commissioned. New York’s state energy code uses those figures, and other adopters can change them. A preliminary report listing uncorrected deficiencies and tests deferred for the season has to be done before the building can pass final inspection. The final commissioning report and the air and water balancing report go to the owner within 90 days of the certificate of occupancy.

Final lien waivers and the final payment

A201 section 9.10.2 holds the final payment and the remaining retainage, the share of each monthly payment kept back until the end, until the contractor delivers those final payment papers and documentation of the special warranties. The lien waivers and retainage pages explain both.

Final payment also closes off claims. An owner that pays gives up its claims except for unsettled liens, work that doesn’t comply with the contract documents, special warranties and audits the contract allows (section 9.10.4). A contractor, subcontractor or supplier that accepts final payment gives up every claim it hasn’t already made in writing and listed as unsettled on its final application (section 9.10.5).

A filled-in closeout checklist

Here is an illustrative closeout log for a made-up two-story medical office building, two weeks before the contractor’s final application for payment.

Item Owed by Checked by Status
Record drawings, all disciplines General contractor, from the trades’ as-builts Architect Returned. The storm drain behind the building isn’t shown where it was laid
O&M manual, fire alarm Fire alarm subcontractor Owner’s facilities manager Open. Panel programming printout missing
Roofing manufacturer’s warranty Roofing subcontractor Architect Accepted, issued in the owner’s name
Attic stock, ceiling panels and floor tile Ceiling and flooring subcontractors Architect signs, owner stores Delivered, counted and signed for
Final lien waivers Every subcontractor and major supplier General contractor, then architect 14 of 16 received. Drywall and electrical still out
Contractor’s affidavit and surety’s consent General contractor and its surety Architect Waiting on the last two waivers
Punch list General contractor Architect Two items open

The money waits on the last two waivers and the affidavit behind them. The architect also can’t certify the work complete while the record drawings, the fire alarm manual and two punch items fall short.

When closeout documents are due

The deadlines sit in the specifications, and some fall well before final completion, when every punch item and paper is done. The University of Houston’s closeout specification wants record documents, manuals, warranties and attic stock in at least 10 days before the contractor asks for the substantial completion inspection, and warranties for any part the owner occupies early within 15 days of that part’s completion. The IECC allows the same 90 days after the certificate of occupancy for the record documents, the energy compliance file and the training completion report.

A worked example at 1200 Walnut Street

At 1200 Walnut Street, the fictional six-story building the book follows, residents move in about three months before the contractor’s last payment, and the building opens in two pieces. Each piece reaches substantial completion the week the city signs its temporary certificate of occupancy (TCO). All Walnut Street figures are illustrative.

When Milestone What it means for closeout
Month 19 First TCO, for the podium and apartment levels 2 to 4 Warranties and the one-year correction period start for that part
About three weeks later Second TCO, for levels 5 and 6 A second start date for the same warranties on the top two floors
About month 22 Final completion About $3 million of retainage goes to the contractor once the punch list, closeout documents and final waivers are done
About month 31 The first correction period ends The end of the year for reporting newly found defects on the podium and levels 2 to 4
About three weeks after that The second correction period ends The same cutoff for levels 5 and 6

From month 19 to month 22, residents live on floors the contractor is still closing out, so the manuals and warranty contacts have to be on the property manager’s shelf before the first key goes out.

The construction one-year warranty, correction period and statute of repose

The punch list page explains the basic split between the one-year correction period and the contractor’s open-ended warranty. Several more clocks start at handover.

Protection Where it comes from How long it lasts When the clock starts
Contractor’s warranty that the work conforms and is free of defects A201 section 3.5.1 No end date in the contract Applies to the work as built
Manufacturers’ and installers’ special warranties A201 section 3.5.2 and the specification sections Whatever each warranty says Substantial completion, unless the certificate of substantial completion says otherwise (section 9.8.4)
Correction period A201 section 12.2.2 One year Substantial completion of the work or of a designated part
Federal warranty of construction FAR 52.246-21 One year, and a fresh year for each repair Final acceptance, or when the government takes possession of a part
Statute of limitations State law, such as Florida Statutes 95.11(3)(b) Four years in Florida The earliest of the TCO, certificate of occupancy, certificate of completion or abandonment, or for a hidden defect, when it was or should have been found
Statute of repose State law, such as Florida 95.11(3)(b) and Virginia Code 8.01-250 Seven years in Florida, five in Virginia Florida uses the same dates as its limitations period, and Virginia counts from when the design and construction work was performed

A201 adjusts the year in two ways. A punch item first installed after substantial completion gets its year extended by the gap (section 12.2.2.2), and a repair doesn’t restart the year (section 12.2.2.3). The federal clause does the reverse and gives repaired work a new year.

A statute of limitations is the deadline to sue once a claim exists, and a statute of repose is an outer cutoff, counted from a fixed point near the end of construction, that closes no matter when the defect appears. Each state writes its own, so the Florida and Virginia rules in the table are examples, not national rules. Florida also says warranty repairs don’t extend either period. Virginia’s five-year bar covers suits against designers and builders over a defective and unsafe condition, and it doesn’t protect manufacturers and suppliers of installed equipment.

Federal owners put the checking on the calendar, and UFGS 01 78 00 calls for a warranty management plan, a durable tag on each warranted item, and joint warranty inspections 4 and 9 months after acceptance, while there’s still time to report defects inside the year.