Bid leveling and buyout
- Updated
- Written by
- Alexander J. Hale
- Reading time
- 9 min
- Sheet
- 21 of 44
Bid leveling is how a general contractor compares subcontractor bids for one trade after adjusting each bid to cover the same work. The estimator adds a price for anything a bidder left out, takes out work that belongs in another trade’s package and prices the owner’s options the same way for every bidder, and only then compares totals. Buyout follows the owner’s signature on the construction contract or the guaranteed maximum price (GMP), when the contractor turns the chosen bids into signed subcontracts and purchase orders and each trade comes in under or over what the estimate carried for it.
What bid leveling means
A general contractor splits a building into bid packages, one per trade or group of trades, and sends each to several subcontractors with its drawings, specification sections and a scope sheet saying what the package includes. The bids come back in different shapes. One prices the hoisting and another assumes the contractor’s crane. One lists six items it left out, and another throws in work from the package next door. A leveling sheet lines them up, scope items down the side and bidders across the top, so every gap and overlap shows up as a cell.
On some public jobs the sheet is a public record. Utah’s state facilities division requires the construction managers it hires to record every bid and bidder on a subcontractor leveling sheet, send a copy to the division with the bid package and keep it open to public inspection. Elsewhere the owner’s view comes from the contract. A133, the American Institute of Architects (AIA) standard agreement for construction manager at risk, has the construction manager deliver subcontractor bids to the owner and architect, marked with the ones it intends to accept, and gives the owner audit rights that reach subcontractors’ proposals.
Scope gaps, exclusions and alternates
| Term | What it is | What the leveler does |
|---|---|---|
| Exclusion | Work a bidder says in writing it didn’t price | Confirms it with the bidder, then adds a plug |
| Qualification | A condition the bidder attached to its price, such as weekday hours only | Prices the condition or asks the bidder to drop it |
| Scope gap | Work no bid includes, because the package doesn’t clearly assign it to anyone | Writes it into one package or carries it in the contractor’s own estimate |
| Overlap | Work two packages both include | Deducts it from one of them |
| Alternate | A separately priced add or deduct the owner decides on later | Levels each alternate and compares totals on the same set |
| Unit price | A rate for work whose quantity nobody knows yet, such as rock removal per cubic yard | Multiplies every bidder’s rate by the same assumed quantity |
| Plug | The contractor’s own price for a missing item, taken from its takeoff | Stays on the sheet until the bidder prices the item |
Scope gaps live at the edges between packages. Firestopping where pipes pass through a rated wall falls between the plumber who made the hole and the crew that built the wall. Access panels for valves above drywall ceilings and protection of finished floors until move-in drift between packages the same way. The cure is in the scope sheets, written so each item lands in exactly one package. A gap in work the drawings showed, found after signing, generally falls to the contractor, and the contingency vs allowance page explains which pot usually covers it.
Alternates can flip the ranking once the owner chooses. Defense Department solicitations that list alternates handle this with a fixed rule. Under DFARS 252.236-7007, the government settles the funds available before bids open, then finds the low bidder by starting from the base bid and adding or deducting alternates in the bid schedule’s priority order as far as the money reaches, with every bid evaluated on the same items.
How to level subcontractor bids
- Build the rows from the scope sheet. Every inclusion in the package and every addendum gets a row, so a bidder’s silence on an item shows as an empty cell.
- Read each bid to the last page. Exclusions and qualifications usually follow the price. Mark each row included, excluded or silent.
- Ask each bidder about its own bid only. On Utah state jobs, for one, the manual lets a construction manager discuss a bid with the firm that sent it, to clarify it and verify scope and exclusions, and never with any other bidder. Get the answers in writing.
- Price each hole once. Where a bid excludes an item, add a plug for it, and put the same plug on every bid missing that item. The construction estimating page explains the takeoff behind it.
- Take out overlaps. Deduct work a bidder included that another package already carries, so the owner doesn’t buy it twice.
- Check the paperwork. Utah’s manual for its state jobs allows a typo, a math error or a missed addendum acknowledgment to be corrected when that’s fair to the other bidders, but never a mistake in judgment. A bid that looks too low can be sent back for written confirmation.
- Level the alternates, then compare. Rank the leveled totals with and without the alternates the owner might take.
A sample bid leveling sheet
Generic example. The package, the three bidders and every dollar figure below are invented to show the method. They don’t come from 1200 Walnut Street or any real project.
The package is drywall and ceilings for a mid-size building, and the plugs come from the contractor’s own takeoff.
| Scope item | Bidder A | Bidder B | Bidder C |
|---|---|---|---|
| Base bid as submitted | $1,212,000 | $1,286,000 | $1,178,000 |
| Framing, board and finishing per the drawings and specifications | Included | Included | Included |
| Firestopping at rated-wall penetrations | Excluded, plug $46,000 | Included | Excluded, plug $46,000 |
| Wood blocking for wall-hung items | Included | Included | Excluded, plug $19,000 |
| Installing door frames, already carried in the doors package | Not included | Included, deduct $27,000 | Not included |
| Hoisting and material handling | Included | Included | “By GC,” plug $14,000 |
| Addendum 2, added corridor soffits | Included | Included | Excluded in writing, plug $11,000 |
| Leveled base bid | $1,258,000 | $1,259,000 | $1,268,000 |
| Alternate 1, upgraded acoustical ceiling in the lobby | Add $21,000 | Add $12,500 | Add $16,000 |
| Leveled total with Alternate 1 | $1,279,000 | $1,271,500 | $1,284,000 |
Bidder C looked $34,000 cheaper than A on bid day and ends with the highest leveled base bid. B’s deduct keeps the owner from paying for door frames twice. A and B finish $1,000 apart on the base bid, so the owner’s call on Alternate 1 decides the package. Without the upgraded ceiling, A is low. With it, B is low by $7,500.
What buyout means in construction
Once the owner signs, the contractor stops pricing subcontracts and starts buying them. It negotiates final terms with each chosen bidder, checks the scope once more against the leveling sheet and the drawing set the price was based on, and signs a subcontract or purchase order. Every inclusion and exclusion from the leveling sheet belongs in the subcontract’s scope exhibit, so the trade signs for exactly what was compared.
Equipment built to order goes first. A133 has the construction manager prepare a procurement schedule during preconstruction for items that must be ordered in advance of construction, and if the owner agrees to buy any of them before the GMP is set, it buys them on terms the construction manager accepts. Under the same form, the owner also gets a say in who is hired. It can object to a proposed subcontractor, but once the GMP is signed, an owner that insists on a different firm over a qualified, recommended bidder whose bid met the documents without exceptions can be charged the difference by change order.
Public rules can limit bargaining. Washington’s statute for public general contractor/construction manager jobs lets the builder negotiate a lower price with the lowest responsible, responsive bidder, through agreed changes to the plans and specifications, only when every responsive bid came in over the published estimate and the low bid is no more than 10 percent over it. If those talks fail, the work must be rebid.
When a package signs below the figure the estimate held for it, the gap is buyout savings, and one that signs above it is a loss, sometimes called a bust. Under a lump sum the owner pays the agreed sum, changed only by change order, so both are the contractor’s own. Under a GMP, the contract decides whether savings go back to the owner, get shared or move into the contractor’s contingency, which the GMP page covers, and a bust is usually paid from that contingency first.
Buyout is also where bid shopping tempts. Utah’s manual defines it as disclosing the low bid to other bidders to get it matched or beaten. Subcontracts written in buyout settle the bonds too, which the builder’s risk and bonds page explains.
At 1200 Walnut Street
At 1200 Walnut Street, the fictional six-story building the book follows, all the leveling had to fit between one Friday and one signature. All Walnut Street figures are illustrative, and the example sets no bid figures for any trade.
| When | What happened |
|---|---|
| A Friday | The 90 percent construction documents were issued, the set the GMP would be priced from |
| Two weeks later | Fernwood Development reviewed the 90 percent set |
| A week after that | The GMP was due |
| At signing | The $60 million GMP was signed, and the construction loan closed right after |
| Then | Buyout of about 30 subcontracts |
The framing, mechanical, electrical and plumbing subcontractors had joined during design as design-assist trades, so their scopes took shape alongside the drawings. Everything priced in those three weeks went into a number that Victor Price, the contractor’s chief estimator, would be held to for about 20 months of construction. A gap missed on a leveling sheet would be paid first from the contingency the contractor carries within the GMP, then from a fee worth between $2.4 million and $4.2 million, 4 to 7 percent of the GMP. Once that contingency was spent, a miss worth 1 percent of the GMP, $600,000, would take a quarter of the fee at its low end. Fernwood’s $3.0 million owner’s contingency sits outside the GMP, in Fernwood’s own budget, and an estimating miss earns no change order to reach it.
What newcomers get wrong about bid leveling and buyout
- Reading the lowest bid as the cheapest. In the sample, C’s $34,000 head start disappeared once its exclusions were priced. Compare totals only after the scopes match.
- Treating leveling as negotiating. Leveling asks each bidder what its own number covers. Showing one bidder another’s price is bid shopping, and public owners such as Utah ban it.
- Blaming the subcontractor for a scope gap. An exclusion written on a bid is information for the leveler to price. A gap that no bid covers usually traces back to how the packages were written.
Sources
- DFCM Construction Managers/General Contractors (CM/GC) Subcontractor Procurement Manual, Utah Division of Facilities Construction and Management, June 1, 2025, accessed November 26, 2026
- AIA Document A133-2019, Owner and Construction Manager as Constructor, Cost of the Work Plus a Fee with a Guaranteed Maximum Price, contract exhibit, City of Happy Valley, Oregon, accessed November 26, 2026
- DFARS 252.236-7007, Additive or Deductive Items, Acquisition.gov, accessed November 26, 2026
- RCW 39.10.380, Subcontract work, Washington State Legislature, accessed November 26, 2026
- 5 Construction Contract Payment Methods: How To Choose the Right One, AIA Contract Documents, accessed November 26, 2026
- The Contractor’s Contingency: What Contractors and Construction Managers Need to Know and Be Wary Of, ConsensusDocs, November 3, 2023, accessed November 26, 2026