What is value engineering?
- Updated
- Written by
- Alexander J. Hale
- Reading time
- 9 min
- Sheet
- 19 of 44
Value engineering (VE) is a structured team review that names the functions each part of a project has to perform, then hunts for the lowest-cost way to deliver those functions over the project’s whole life without giving up the performance, quality or safety the owner requires. It began at General Electric in the late 1940s, and US federal agencies are required to use it on new projects estimated at $5 million or more. On many private jobs, the name gets attached to almost any late cost cut, including cuts that remove something the owner needed.
What value engineering means in construction
The federal definition, in the Office of Management and Budget’s Circular A-131, describes VE as a systematic look at the requirements, functions and elements of a project, aimed at getting its essential functions at the lowest life-cycle cost. Life-cycle cost is the total cost of owning the thing over its useful life, including buying it, running it, maintaining it and getting rid of it, with energy counted. The circular adds that the best answer may cost more up front if it meets the same basic function for less over time.
McGill University’s value engineering site defines value as the ratio of function to cost, so value goes up when the function improves or the cost falls. The method insists on naming each function in two words, an active verb and a measurable noun. A wall might “enclose space,” “resist fire” and “block sound,” and each of those can be met more than one way. Naming the function first keeps the team from defending the product already drawn.
OMB lists value analysis, value management, value planning and value control as other names for the same method, and the General Services Administration (GSA) uses “value management” across its building program. The Whole Building Design Guide, published by the National Institute of Building Sciences, says VE is neither a design review nor a cost-cutting exercise.
Where value engineering came from
Lawrence D. Miles created the techniques of value analysis at General Electric in 1947, according to the University of Wisconsin’s reference collection named for him. OMB’s circular traces the idea to industry during World War II and says federal agencies took it up because they saw the potential for a large return on investment. Practitioners formed the Society of American Value Engineers in 1959, now called SAVE International. GSA’s cost policy tells its value studies to follow SAVE International’s Value Methodology Standard along with two ASTM standards, E1699 for performing value studies of projects and E2013 for FAST diagrams, the charts that map how a project’s functions depend on one another.
The value engineering job plan
Circular A-131 describes a workshop run by a trained facilitator with a team from several disciplines, moving through six phases.
| Phase | What the team does | On a building project |
|---|---|---|
| Information | Gathers the facts and the constraints | Reads the program, the drawings, the cost estimate and the schedule |
| Function analysis | Names the basic functions and finds where they fall short of what the owner needs | Lists each major system’s functions in verb-noun pairs and marks the ones costing far more than they seem worth |
| Creative | Brainstorms alternatives, aimed at the high-cost items | Collects every idea before anyone judges one |
| Evaluation | Ranks the ideas against the project’s goals | Drops ideas that fail the code, the program or the owner’s requirements |
| Development and presentation | Turns the best ideas into proposals with net life-cycle savings and implementation details | Prices each proposal and lists the drawings and specification sections it would change |
| Implementation | Puts the accepted alternatives into the project | The design team revises the documents |
On its own projects, GSA hires an independent VE consultant directly instead of through the architect, and the design team and construction manager must take part at least through the information and function analysis phases. The architect then reports, with the 90 percent construction documents, how it carried out each accepted alternative or why it couldn’t.
Value engineering on federal projects
Under 41 U.S.C. 1711, every executive agency must keep cost-effective procedures for analyzing the functions of its projects, buildings and facilities, aimed at performance, reliability, quality, safety and life-cycle cost. Circular A-131, revised December 26, 2013, makes VE mandatory on new projects estimated at $5 million or more unless a senior agency official grants a waiver, and the major agencies report their results to OMB every year.
Contractors take part through the Federal Acquisition Regulation (FAR), Part 48, which sets out two approaches. In one, contractors volunteer ideas and share in any savings. In the other, the government requires and pays for a VE program, and no sharing at all is allowed on architect-engineer contracts. A value engineering change proposal (VECP) is a contractor’s offer to change the contract in a way that lowers the price without hurting essential functions. FAR 48.202 puts the construction clause, FAR 52.248-3, into construction contracts estimated above the simplified acquisition threshold, except incentive contracts. The clause invites VECPs voluntarily and has the contracting officer report a proposal’s status within 45 days. Until a change is approved, the contractor keeps building what the contract shows. Acceptance is the contracting officer’s call alone. On an accepted proposal, the savings are counted net of the contractor’s own development and implementation costs, the contract price drops by that amount, and the contractor gets a share of it back at rates the clause sets. It can also receive 20 percent of one typical year’s projected savings in the agency’s costs to run and maintain the item, capped at the greater of the contract price or $100,000.
How value engineering is used in practice
Outside federal work, VE often arrives with bad news. A 2024 AIA Architect article by Wanda Lau opens on the dread the phrase can cause, quotes one architect who prefers to call it value design, and argues that the work shouldn’t wait until bids come back. By then the drawings are finished, and the quickest savings come from taking things out. The article also warns architects against downgrading the building envelope, the mechanical, electrical and plumbing (MEP) systems and the lighting by reflex, since those are where cuts tend to start.
Items on a late VE log usually fall into one of three groups, and only the first is value engineering in the original sense.
| What the item does | What changes for the owner | How to spot it on the log |
|---|---|---|
| Delivers the same functions for less over the building’s life | Nothing the owner needs is lost | The proposal names the functions, shows each one still met and gives a life-cycle cost |
| Lowers the construction price and raises later costs | More energy, upkeep or earlier replacement | The saving is shown for construction only, with no operating or replacement figures |
| Removes scope or performance | The building does less than the program or specification asked | A space, feature or performance level from the owner’s requirements is gone |
An owner may well choose an item from the second or third group, as long as the log calls it what it is.
When value engineering does the most good
Early. OMB tells agencies that VE savings are likely greatest in feasibility, planning, design and other early phases, the Whole Building Design Guide says the return generally rises the earlier VE is applied, and GSA’s policy says value work must begin early in design. Design-stage workshops usually start once schematic design gives the team something to analyze.
The reason is how changes spread. An idea adopted in schematic design changes a few sheets that are still moving anyway. The same idea at 90 percent construction documents touches drawings from several disciplines, and after the price is fixed it becomes a change order, the process covered on the RFIs, submittals and change orders page. The design phases page explains what each phase locks in.
ConsensusDocs 541, a standard addendum for design-assist, brings construction managers and trade contractors into design development and lists value engineering and life-cycle cost analysis among their optional services. A VE idea priced by the trade that would build it is easier to trust, and the construction estimating page covers how estimates tighten as the drawings fill in.
Value engineering example at 1200 Walnut Street
At 1200 Walnut Street, the fictional six-story building the book follows, the contractor was hired as construction manager at risk once schematic design wrapped up, and its framing and MEP subcontractors joined early through design-assist. All Walnut Street figures are illustrative. The table follows one VE idea through the job’s calendar.
| When the idea comes up | What adopting it takes | Where the money comes from |
|---|---|---|
| Design development, with the contractor and its design-assist trades at the table | Redrawing by the design team, while no price is fixed | Comes off the estimate before the GMP exists |
| The three weeks from the 90 percent set to the GMP | Getting the change onto the drawings and into the price in a window where the set goes out on a Friday, Fernwood reviews it two weeks later and the GMP is due a week after that | Lands inside the GMP only if the set the contractor priced shows it |
| After the $60.0 million GMP is signed | A change order | The saving lowers the GMP, and any redesign cost competes for Fernwood’s $3.0 million owner’s contingency |
| In the field | Rework on built work | Split by negotiation, as the stack below shows |
Walnut Street’s own record shows both ends of the table. When the contractor priced the design development set, it found four plumbing stacks landing in the garage’s drive aisle, early enough that moving them meant only redrawing. One later stack moved in a late unit-layout change, after the last weekly clash run, and came down on a podium beam. Fernwood paid the redesign and new pipe from its owner’s contingency, and the contractor absorbed its own rework labor. A VE change made that late gets the same exposure.
Checklist for weighing a VE item
- Name the function the part serves, in two words. If nobody can, the team isn’t ready to change it.
- Confirm the alternative still meets the code, the specification and the owner’s requirements.
- Price the effect on energy, maintenance and replacement. A-131 counts the whole life cycle.
- List the drawings, specification sections and trades the change touches, and who redraws them.
- Net out the cost of making the change. The federal clause counts savings only after the contractor’s development and implementation costs, and a private owner should subtract redesign fees and schedule time the same way.
Sources
- Circular No. A-131 (Revised), Value Engineering, Office of Management and Budget, December 26, 2013, accessed November 26, 2026
- 41 U.S.C. 1711, Value engineering, Legal Information Institute, Cornell Law School, accessed November 26, 2026
- Value Engineering, CEE 440, University of Washington, accessed November 26, 2026
- FAR 48.101, Value engineering, general, Acquisition.gov, accessed November 26, 2026
- FAR 48.202, Clause for construction contracts, Acquisition.gov, accessed November 26, 2026
- FAR 52.248-3, Value Engineering, Construction, Acquisition.gov, accessed November 26, 2026
- P-120, PBS Cost and Schedule Management Policy Requirements (GSA Order PBS 1000.6B), US General Services Administration, November 7, 2022, hosted by the Whole Building Design Guide, accessed November 26, 2026
- Value Engineering, Whole Building Design Guide, National Institute of Building Sciences, accessed November 26, 2026
- The Lawrence D. Miles Value Engineering Reference Center Collection, University of Wisconsin, accessed November 26, 2026
- About Value Engineering, McGill University, accessed November 26, 2026
- Five Ways to Maximize the Value of Value Engineering, Wanda Lau, AIA Architect, American Institute of Architects, October 3, 2024, accessed November 26, 2026
- Addendum for Design-Assist Services, ConsensusDocs 541, accessed November 26, 2026