What does a project engineer do in construction?

Updated
Written by
Alexander J. Hale
Reading time
9 min
Sheet
8 of 44

At a general contractor, a project engineer keeps a building job’s paper current. The job covers the requests for information (RFIs) sent to the architect, the submittals that show what will be installed, the drawing log, meeting minutes and the backup for every change, and the person doing it usually reports to the project manager and works beside the superintendent. The job doesn’t require an engineering license, and it is often the first rung of an office ladder that runs through assistant project manager to project manager.

What a project engineer does in construction

A project engineer’s day moves between the site trailer, the floors and the inbox. Foremen bring questions the drawings don’t answer, suppliers send drawings of what they plan to make, the architect’s office sends answers and revised sheets, and each of those has to reach the right person and land in the right log.

The contract decides what the project engineer has to check. Under A201-2017, the standard general conditions published by the American Institute of Architects (AIA), the contractor reviews and approves each submittal before sending it to the architect (3.12.5). By sending it, the contractor tells the owner and architect that it has checked the package against the contract documents, verified the field measurements and coordinated it with the rest of the work (3.12.6). Errors in the package stay the contractor’s problem even after the architect approves it (3.12.8). A project engineer who forwards a package unread is putting the company’s name behind work nobody checked.

Experienced field staff add advice of their own. Bud Lester, a superintendent at the builder Nabholz, wrote in 2017 that a new project engineer should keep the superintendent informed every day and should show the superintendent each RFI before it goes out.

Two jobs with the same title

Project engineer at a general contractor Project engineer at a design firm
Works for The builder An engineering or architecture firm
The work Logs, RFIs, submittals, minutes and change backup for one job Designing and running the engineering on projects
License Not needed for the job A Professional Engineer license, which the US Bureau of Labor Statistics (BLS) says civil engineers typically need once they provide services directly to the public
Where BLS counts it No category of its own. The job leads to construction manager O*NET, the Labor Department’s job database, lists project engineer among the titles reported by civil engineers

The contract draws the same line. A201 says the contractor doesn’t have to provide services that amount to practicing architecture or engineering unless the contract documents call for them on some part of the work, or its own means and methods need them (3.12.10). When the contract does hand a piece of design to the builder’s side, such as the engineering of roof trusses, A201 expects an appropriately licensed design professional to seal that work (3.12.10.1), and the project engineer moves the sealed package through review.

The project engineer’s logs

Every log is a table with one row per item, a due date for each row and a column naming whoever owns the next move, which builders call the ball in court. The RFIs, submittals and change orders page shows what goes into a single RFI and a sample submittal log.

Log One row per What the project engineer watches Who is waiting
RFI log Question sent to the architect Days open, the date the answer is needed, any cost or time effect The foreman whose crew needs the answer
Submittal log, or register Package the specifications require The date it must go out to arrive in time, the reviewer, the action stamped on it, resubmittals The supplier’s factory and the crew that installs it
Drawing log Sheet in the current set Current revision and date, what changed it, which old sheets are superseded Everyone building from that sheet
Change log Possible change, known as a potential change order (PCO) The document that started it, the notice date, the price, its status The project manager and the owner
Meeting minutes Decision or open item Who acts next and by when Everyone at the table

RFI log

University of Houston’s master construction specification, one public owner’s version, asks the contractor for a tabular RFI log organized by number. When the architect acts on an RFI, the contractor has to update the log and send the answer to the affected parties right away. That second step is the one that slips. The log says “answered” the moment the architect replies, and the crew waiting on it knows nothing until someone walks the answer over.

Submittal log

A201 asks the contractor, promptly after award, for a submittal schedule coordinated with the construction schedule and leaving the architect reasonable time to review (3.10.2). A contractor that never sends that schedule, or doesn’t keep to it, gets no added time or money for the days the review takes, so a package sent late puts the review days on the builder’s own clock. The shop drawings page explains what the reviewer is looking at.

Drawing log

A201 has the contractor keep the contract documents at the site, including every change order and directive, “marked currently to indicate field changes,” along with the approved submittals (3.11). At the end of the job that set goes to the architect as the record of the building as built. Lester’s advice for the digital version is to mark it up the way a superintendent marks paper and to link each RFI and supplemental instruction to the sheets it changes. The drawing log is how anyone knows which revision of a sheet is current, and a crew working from an old print is the failure it exists to prevent.

Meeting minutes

Houston’s specification has whoever runs a meeting record its significant discussions and agreements and send the minutes to everyone concerned, owner and architect included, within three days. Each progress meeting’s agenda then starts with reviewing and correcting or approving the last set. When the contractor runs the meeting, writing the minutes often falls to the project engineer or assistant project manager, and once approved they are the written record of what everyone agreed.

A page of the logs at 1200 Walnut Street

1200 Walnut Street, the fictional six-story building the book follows, is in construction month 9, with the wood frame climbing and about 30 subcontractors on the job. Every number below is illustrative. The contractor keeps its logs in Procore. On a job this size the logs belong to a project engineer or an assistant project manager, and here is how five of the month’s rows look from that seat.

Item What happened Ball in court The log keeper’s next move
Roof truss shop drawings Returned after 12 days marked revise and resubmit The truss supplier, through the framing subcontractor Log the resubmittal as a new revision, then track the approved package to the city, which reviews it as a deferred submittal
RFI 187 The third-floor plumbing wall is drawn too thin The architect Tell the superintendent and the framing foreman when the answer is due
ASI 22 The architect’s answer to RFI 187, issued as supplemental instructions The contractor Enter the revised sheets in the drawing log, mark the old ones superseded and open a PCO
Change directive Owner and architect order the fix on time and materials The contractor Collect the signed daily tickets
Change order 6 Bundles the fix at about $3,100 Owner, architect and contractor, who all sign Attach the tickets and close the PCO

Four of those five rows grew from one question about one wall. When change order 6 comes back with all three signatures, the log keeper closes the PCO and marks RFI 187 closed.

Project engineer to assistant project manager to project manager

The usual office ladder at a general contractor runs from project engineer to assistant project manager to project manager, and where one title ends and the next begins varies by firm. Cal Poly’s construction management program lists project engineer, field engineer, assistant project manager and project manager among the traditional jobs its students and graduates take.

Each step adds a kind of responsibility. A project engineer owns the paper about the work. An assistant project manager adds money to it, rolling subcontractor bills into the monthly pay application and pricing changes. A project manager owns the contract, the budget and the fee, and the construction project manager page covers that job and the rungs above it. On the field side, a field engineer works toward the superintendent’s job instead, and the construction superintendent page covers that route.

Project engineer construction salary

BLS has no occupation for the general contractor’s project engineer, so it publishes no pay figure for the title. The nearest BLS figures come from two groups, one on the design side that uses the same title and one that the contractor’s job leads to. Both sets of figures below are for May 2025.

BLS occupation How it relates to the title Lowest 10 percent earned less than Median Top 10 percent earned more than
Civil engineers A design-side occupation that uses the title $68,240 $100,840 $163,220
Construction managers The job the contractor’s project engineer is training for $69,690 $114,990 $189,440

Neither row is a project engineer’s paycheck. The construction managers’ figure describes people who already run projects or sites, and a quarter of them earned less than $88,550. The surest number for a specific job is the one in its posting. Under Washington state law, for example, employers with 15 or more employees must include a wage scale or salary range in each job posting, along with a general description of benefits and of other pay such as bonuses.

What new project engineers get wrong

  • Stamping a submittal after checking only the part they were asked about. The stamp tells the architect the whole package was checked against the rest of the work.
  • Treating an answered RFI as finished before the foreman has the answer in hand.
  • Sending an RFI the superintendent hasn’t seen, when the superintendent may already know the answer or a better question.
  • Answering a foreman’s question on the spot without being sure of it. Lester’s advice is to bring in the superintendent when in doubt.
  • Leaving a wrong line in the minutes until the next meeting reads it back as agreed.
  • Building the drawing log as a list of sheet numbers without checking the set in the field against it.