What is the building envelope?

Updated
Written by
Alexander J. Hale
Reading time
11 min
Sheet
34 of 44

The building envelope, also called the building enclosure, is the roof, the exterior walls, the windows and doors, and the foundation walls and slab below ground, everything that separates a building’s inside from the outdoors. Its job is to control what crosses that line, and building scientist Joseph Lstiburek ranks the four things it controls as rain first, then air, then water vapor and then heat. The architect designs it, and its failures are among the most expensive defects in construction because water does its damage inside the wall long before anyone sees a stain.

Building envelope definition

The model energy code, the International Energy Conservation Code (IECC), defines the building thermal envelope as the basement walls, exterior walls, floors, ceilings and roofs, plus any other assemblies, that enclose heated or cooled space or separate it from space that isn’t. That second half catches newcomers. Under that definition, the floor over an unheated parking garage is part of the envelope, even though it sits inside the building’s outline. The IECC and the International Building Code (IBC) are model codes, which states and cities adopt in their own editions and often amend, so the locally adopted version is the one that governs.

Zoning uses the same two words for something else. In a zoning code, the building envelope is the three-dimensional space a building may fill on its lot, bounded by setbacks, height limits and bulk rules, as the City of Rome, New York, defines it. The page on zoning vs building codes covers that meaning.

What the building envelope controls

Each layer depends on the one before it, and a wall that lets rain in won’t be saved by good air sealing.

Rain comes first. The water-resistive barrier (WRB) is a sheet or fluid-applied coating on the sheathing behind the cladding, and it’s the layer the wall counts on to stop rain. The brick, siding or panels in front are expected to let some water past. For most walls, the IBC requires a continuous water-resistive barrier behind exterior veneer, flashing around every window and door, and a way for water that gets behind the cladding to drain back out.

Air comes second. An air barrier is a continuous layer that stops air from leaking through the envelope, and it can be a membrane, a coating or sheathing panels with every seam sealed. Leaking air carries heat and moisture, and the moisture can condense on cold surfaces inside the wall. The 2021 IECC calls for a continuous air barrier across every assembly, joint and transition, in every climate zone except 2B.

Vapor and heat come last. A vapor retarder limits how much moisture diffuses through the solid layers themselves, and insulation slows heat, in amounts the IECC sets by climate zone. The code’s continuous insulation runs across the framing without thermal bridges, the studs and other members that let heat bypass the batts.

For energy rules, a six-story apartment building counts as commercial. The IECC’s residential provisions cover apartment buildings only up to three stories above grade plane, so taller ones follow the commercial chapter and its air-leakage tests.

The parts of a building envelope

Part What keeps water out Typical materials Who installs it
Roof A membrane sloped to drains and flashed at every edge and opening Single-ply, modified bitumen or built-up roofing over insulation Roofers
Exterior walls A water-resistive barrier behind the cladding, with flashing and a drainage path Brick, metal panels, fiber cement or stucco over sheathing Masons, carpenters, cladding installers
Windows and doors Factory-sealed units, plus flashing and sealant where they meet the wall Windows, storefront, curtain wall Glaziers, carpenters
Below grade Dampproofing or waterproofing on walls and slab, plus a perimeter drain Sheet or fluid-applied membranes Waterproofing subcontractors

Roofs

Low-slope roofs, the kind on most commercial and apartment buildings, still have to shed water. The IBC wants single-ply and modified bitumen membranes laid to a slope of at least a quarter inch per foot, flashing wherever the roof meets a wall or is cut by an opening, and a second set of overflow drains or scuppers wherever a parapet could trap water. Every rooftop curb, pipe and duct is a hole in that membrane, so the roofer’s flashing has to follow the MEP systems layout.

Walls

Cladding hung in front of a drained gap, with the water barrier behind it, is called a rainscreen. A wall that relies on its outer face and its caulked joints to stop every drop is face-sealed, and one failed joint there can feed water straight into the framing.

On many buildings taller than 40 feet, depending on the construction type, the IBC requires an exterior wall that contains a combustible water-resistive barrier to pass NFPA 285, a two-story fire test of the whole wall assembly. The exceptions cover walls where the barrier is the only combustible part and either sits behind brick, stone, concrete, stucco or steel of a set thickness or passes smaller material tests.

Windows, doors and the joints around them

A window arrives as a finished factory product, but the joint between window and wall is built on site. The water barrier has to lap around the opening like shingles, with flashing over the head and the barrier tucked under at the sill, so water running down the face of the wall is always turned outward.

Below-grade waterproofing

Below ground, the code sorts the work by water pressure. Where the lowest floor sits below the ground outside, the soil investigation has to find out whether the water table is above that floor or within 5 feet below it. Where groundwater won’t press on the walls, they get dampproofing, a coating that slows moisture, and a drain around the foundation. Where a high water table creates hydrostatic pressure, the walls and floor need waterproofing, a continuous membrane built to hold back water under pressure, unless a drainage system keeps the water table at least 6 inches below the lowest floor.

Curtain wall vs storefront

Both are aluminum frames holding glass, and they’re built for different jobs.

Storefront Curtain wall
Where it goes Ground-floor entrances and shopfronts, set between slabs or in a masonry wall Across the building’s face, running past the floor slabs
How it’s held up Anchored inside its opening, with little capacity for sideways load Hung from the slab edges, carrying its own weight and the wind back to the frame
Typical size Each section commonly limited to about 10 feet tall Floor to floor, and as tall as the building
How it drains Water runs down the vertical members to weeps at the sill, over a sill pan with end dams Each horizontal member drains through its own weeps, and no sill pan is required

Leave out a storefront’s sill pan or end dams and the water it collects can reach the inside at the bottom corners of the opening. Curtain wall is often engineered on the glazing contractor’s side under delegated design, which the page on shop drawings explains, and the federal guide specification wants its structural calculations signed by a registered professional engineer. A third system, window wall, fills the height between slabs one floor at a time.

Why envelope failures are among the costliest defects

Water that gets past a bad lap soaks the sheathing and framing behind finished cladding, and the first sign indoors may come after rot has spread. The repair means scaffolding, stripping cladding that was fine and rebuilding every layer in order, often around people living inside. A detail drawn once is built at every window where it appears, so one mistake repeats across a building.

ASHRAE’s handbook chapter on moisture management, citing 2008 data from the National Association of Insurance Commissioners, calls humidity and moisture problems in buildings the single largest category of claims against architects’ and engineers’ errors and omissions insurance, at 84 percent. That figure counts moisture claims of every kind, so it isn’t a measure of envelope failures alone. One forensic engineering firm, VERTEX, reviewed 46 construction defect cases litigated from 2011 to 2019 and found missing or failed sealant joints and unsealed penetrations alleged in 78 percent, and badly lapped water barriers in 67 percent. In eight of the ten cases it studied for cost, alleged envelope problems made up at least 45 percent of the claimed repair cost. The defects alleged most often in that study sat at laps, joints and penetrations, where one trade’s work meets the next trade’s.

Who designs and tests the building envelope

The architect designs the envelope and seals the drawings that show it. An owner or architect can add a building envelope consultant to review details and submittals, watch the installation and run or witness tests. The International Institute of Building Enclosure Consultants (IIBEC) registers roof, waterproofing and exterior wall consultants. Building enclosure commissioning turns that work into a defined process, and ASTM E2813 sets two levels of it, fundamental and enhanced. Both require an independent design review, and the standard makes performance testing mandatory.

Testing starts before the wall goes up. A mockup, a full-size sample of a typical bay, proves the details and sets the standard the finished wall has to match. The federal guide specification for curtain wall has the system tested in a lab for water at 20 percent of the design wind pressure, never less than 12 pounds per square foot. It then repeats the water test on the finished wall at two-thirds of the lab pressure, run by a testing agency with no tie to the installer.

Field test What it does Used on
ASTM E1105 Sprays water on the outside face while air pressure pushes inward, held steady or cycled Installed windows, doors, skylights and curtain wall
AAMA 501.2 Aims a specified hose nozzle at a set water pressure along joints while an observer inside watches for leaks Storefronts, curtain walls and sloped glazing
ASTM E779 or E3158 Pressurizes a whole building or unit with a fan, a blower door test Whole buildings and apartments
ASTM D7877 Scans a membrane electrically for breaches Roofs and plaza decks
ASTM D5957 Ponds up to 4 inches of water on a membrane Plaza and garage decks, not roofs

Walnut Street: where water could get in

1200 Walnut Street, the fictional six-story building the book follows, has a brick base with storefront openings on its concrete podium and five wood-framed apartment floors above. All Walnut Street numbers are illustrative. Each spot below is where two trades’ work has to join. The last column lists a test that suits each spot, and nothing on this page records which tests were run at Walnut Street. The air-barrier row assumes the city enforces the 2021 IECC without amendments and sits outside Climate Zones 2B, 3C and 5C, which that edition exempts from apartment testing. Under those conditions each apartment is its own testing unit, and the code calls for the greater of seven units or 20 percent, which is 40 of the 200. They must include a top-floor unit, a ground-floor unit (Walnut Street’s lowest apartments are on level 2, above the podium) and the unit with the largest enclosure area, and every unit that fails adds two more.

Spot What has to connect Who builds it A test that could check it
Storefront openings in the brick base A sill pan with end dams, tied into the wall’s flashing Glaziers and masons AAMA 501.2 or ASTM E1105
The top of the brick, where the wood-framed wall starts Flashing over the brick, with every layer above lapped onto it Masons and carpenters A look before cladding covers it
Apartment windows on levels 2 to 6 One detail lapped into the water barrier, repeated at every window Carpenters or window installers ASTM E1105 on sample windows
The roof, with its amenity space and rooftop equipment Membrane flashed up every curb and sloped to drains Roofers Electronic leak detection before anything covers it
The air barrier around 200 apartments A continuous seal around each unit Several trades Blower door tests on 40 apartments, the code minimum under the conditions above

Sources